Modelagem do “tempo de execução” de obras civis: estudo de caso na Universidade Federal do Pará (UFPA) / Modeling the "time of execution" civil works: Case Study at the Federal University of Pará (UFPA)

Submitted by Edisangela Bastos (edisangela@ufpa.br) on 2012-04-09T22:33:36Z
No. of bitstreams: 2
Dissertacao_ModelagemTempoExecucao.pdf: 9983397 bytes, checksum: 7799f26cde2dae7e7a106ace38a5ab81 (MD5)
license_rdf: 23898 bytes, checksum: e363e809996cf46ada20da1accfcd9c7 (MD5) / Approved for entry into archive by Edisangela Bastos(edisangela@ufpa.br) on 2012-04-09T22:36:22Z (GMT) No. of bitstreams: 2
Dissertacao_ModelagemTempoExecucao.pdf: 9983397 bytes, checksum: 7799f26cde2dae7e7a106ace38a5ab81 (MD5)
license_rdf: 23898 bytes, checksum: e363e809996cf46ada20da1accfcd9c7 (MD5) / Made available in DSpace on 2012-04-09T22:36:22Z (GMT). No. of bitstreams: 2
Dissertacao_ModelagemTempoExecucao.pdf: 9983397 bytes, checksum: 7799f26cde2dae7e7a106ace38a5ab81 (MD5)
license_rdf: 23898 bytes, checksum: e363e809996cf46ada20da1accfcd9c7 (MD5)
Previous issue date: 2010 / O objetivo desta pesquisa é propor um modelo numérico prognóstico que trate a variável
“tempo” de forma eficiente e eficaz, com a finalidade de atender às reais necessidades dos
clientes-usuários e à sociedade em geral. Todavia, realizou-se um levantamento bibliográfico
sobre gestão pública, no tocante a obras públicas, estatística e pesquisa operacional para
sistema organizacional, visando à modelagem numérica. A pesquisa foi baseada em
metodologias quantitativas, com ênfase na pesquisa operacional para o estudo das obras
públicas executadas sob a gerência da Prefeitura (PCU) da Universidade Federal do Pará
(UFPA). Para a elaboração da base de dados, foram coletados informações de obras, reformas
e ampliações, executadas durante o período de 2006 a 2009, junto à Comissão Permanente de
Licitação (CPL) e à Fundação de Amparo ao Desenvolvimento da Pesquisa (FADESP).
Mediante as regressões lineares e, após as transformadas das funções, foram obtidos para o
modelo prognóstico os parâmetros estatísticos: coeficiente de correlação (R), de 0,899;
coeficiente de determinação (R²), de 0,808; coeficiente de determinação ajustado (R²
ajustado), de 0,796; e erro padrão (Se), de 0,41. Esses parâmetros demonstram forte
correlação linearizada entre as variáveis, indicando que 79,60% da variabilidade do tempo
para executar uma obra pública é causada ou produzida pela variação, em conjunto, da área;
do valor orçado; da capacidade técnica operacional da IFES; da capacidade operacional da
empresa; da tipologia de serviço; e da estação do ano. Com os resultados obtidos, conclui-se
que é possível aplicar e implementar o modelo prognóstico para execução de obras públicas,
pois se obteve uma ferramenta potente em sua aplicação para as melhorias dos procedimentos
administrativos, tanto na estrutura como no seu desempenho, cujo principal resultado é a
previsão do tempo para execução do empreendimento público. / The aim of this research is to propose a numerical model that treats the variable time so
efficient and effective in order to meet the real needs of customers, users and society in
general. However, was performed a survey bibliographic on public management, in respect of
public works, statistics and operational research to the organizational system, aiming to
numerical modeling. The research was based on quantitative methodologies, with emphasis
on operational research for the study of public works performed under the management of
PCU/UFPA. In developing the database, information was collected construction, renovations
and expansions, implemented during the period 2006 to 2009, with the Permanent
Commission for Bidding (CPL) and the Foundation that support the Research Development
(FADESP). By linear regressions and after the transformed functions were obtained for the
model prediction the statistical parameters: correlation coefficient (R) of 0.899, the coefficient
of determination (R²) of 0.808, the coefficient of determination (adjusted R²) of 0.796 and
error standard (Se) of 0.41. These parameters show a strong linearized correlation between the
variables, indicating that 79.60% of the variability of time to execute a public work is caused
or produced by variations together the area, the budgeted value, the operational capacity of
IFES; operational capacity of the company; the type of service, and the season. With the
results, it was concluded that it is possible to apply and implement the prognostic model for
public works, considering that it is a powerful tool in its application to improvement of
administrative procedures, both in structure and in its performance, whose main result is
forecast variable “time of execution” for the performance of public enterprise.

Identiferoai:union.ndltd.org:IBICT/oai:repositorio.ufpa.br:2011/2602
Date06 December 2010
CreatorsCOUTINHO, Lêda Sílvia de Aguiar Lédo
ContributorsNEVES, Renato Martins das, DUARTE, André Augusto Azevedo Montenegro
PublisherUniversidade Federal do Pará, Programa de Pós-Graduação em Engenharia Civil, UFPA, Brasil, Instituto de Tecnologia
Source SetsIBICT Brazilian ETDs
LanguagePortuguese
Detected LanguagePortuguese
Typeinfo:eu-repo/semantics/publishedVersion, info:eu-repo/semantics/masterThesis