Return to search

Interações entre o planejamento e o projeto U. H. E's. : o caso das pequenas centrais hidreletricas no Brasil

Orientador: Sergio Valdir Bajay / Tese (doutorado) - Universidade Estadual de Campinas, Faculdade de Engenharia Mecanica / Made available in DSpace on 2018-07-19T16:10:11Z (GMT). No. of bitstreams: 1
Martinez_CarlosBarreira_D.pdf: 84768858 bytes, checksum: 7fcee83e3f82ef3d267684463b21846a (MD5)
Previous issue date: 1994 / Resumo: Este trabalho tem por objetivo a análise crítica das etapas de planejamento e projeto de centrais hidrelétricas, dando-se uma ênfase especial ao caso das PCH's no país, à luz dos procedimentos aceitos pelo Setor Elétrico Brasileiro. Foram desenvolvidos estudos visando a identificação das diversas tecnologias apropriadas para a implantação de PCH's. Revisou-se, a seguir, criticamente os passos preconizados pela ELETROBRÁS para o estudo e projeto de UHE's, em geral. Foram sugeridos, então, procedimentos diferenciados para o caso das PCH's, com o intuito de se racionalizar os esforços dispendidos nos diversos estágios, etapas e fases do projeto da central. Elaborou-se estudos de caso, com o objetivo de aplicar as sugestões propostas. Para isto, abordou-se o planejamento e projeto de PCH's tanto para os sistemas isolados e interligados, com as características próprias de cada caso. A inserção da iniciativa privado na geração de energia elétrica é discutida à luz das experiências oriundas das concorrências públicas abertas pelo DNAEE a partir de 1988, onde a forma de avaliação das propostas e a legislação vigente acabaram por neutralizar os esforços dispendidos. Finalmente são apresentadas as conclusões gerais da tese e as recomendações para desdobramentos futuros do trabalho / Abstract: The objective of this thesis is a critical appraisal of the planning and design stages of hydroelectric power stations, with special enphasys to the analysis of Small Hydroelectc Power Stations ( SHPSs ) in Brazil, according to accepted procedures for the Brazilian Eletr ic Power Sector. Some studies were developd to identify appropriate technologies for SHPSs. The planning and des ign steps recommended by ELETROBRÁS for hydro power stations, in general, were critically reviewed. Specifc procedures for SHPSs were proposed, in order to simplify the calculations involved in the several stages, steps and phases of these power stations designo Some case-studies were carried out to illustrate the measures proposed. The planning and design of SHPSs for both iso1ated and interconnected systems were considered. A greater participation of the private sector in the e1ectricity generation business is discussed here, based on the experience of the pub1ic bids prommoted by DNAEE from 1988, where the way the tenders were evaluated and the current 1egis1ation ended up neutra1izing the whole exercise. Finally, the general conclusions of the thesis, together with some reccommendations for further developments, are put forward / Doutorado / Doutor em Engenharia Mecânica

Identiferoai:union.ndltd.org:IBICT/oai:repositorio.unicamp.br:REPOSIP/264522
Date22 September 1994
CreatorsMartinez, Carlos Barreira
ContributorsUNIVERSIDADE ESTADUAL DE CAMPINAS, Bajay, Sérgio Valdir, 1950-
Publisher[s.n.], Universidade Estadual de Campinas. Faculdade de Engenharia Mecânica, Programa de Pós-Graduação em Engenharia Mecânica
Source SetsIBICT Brazilian ETDs
LanguagePortuguese
Detected LanguagePortuguese
Typeinfo:eu-repo/semantics/publishedVersion, info:eu-repo/semantics/doctoralThesis
Format[388]f. : il., application/pdf
Sourcereponame:Repositório Institucional da Unicamp, instname:Universidade Estadual de Campinas, instacron:UNICAMP
Rightsinfo:eu-repo/semantics/openAccess
Relation(Publicação FEM)

Page generated in 0.0025 seconds