Explotación de recursos de óxidos en Minera Rafaela

Ingeniero Civil de Minas / El objetivo de esta memoria es analizar la factibilidad de implementar la explotación de minerales oxidados de cobre en Minera Rafaela, faena ubicada en la V región de Chile en la comuna de Cabildo que actualmente explota minerales sulfurados de cobre a un ritmo de 1.500 a 1.800 toneladas mensuales de mineral aproximadamente, labor que actualmente no se realiza. Para esto se considera la cantidad total de recursos presentes en la mina y los métodos de explotación apropiados. Además se hace un análisis de dos alternativas de negocio: la venta directa del mineral a ENAMI y la asociación con una planta privada en la cual las utilidades son repartidas equitativamente.
Los recursos totales de minerales oxidados de cobre en mina Rafaela (demostrados e inferidos) estimados en este trabajo son 2,26 [MMTon], con una ley de 2,12 % y un consumo de ácido sulfúrico de 11,9 [kgAc/kgCuRec] (202 [kgAc/Ton]).
De todos los métodos de explotación minera considerados, se concluye que los más adecuados considerando forma del cuerpo, calidad geomecánica de la roca y las leyes presentes son Shrinkage Stoping para cuerpos tipo veta y Room and Pillar para mantos.
Para la presente evaluación económica se ha considerado un precio del cobre de 300 [cUS$/lb], un costo mina de 15 [US$/Ton] para los mantos (Room and Pillar) y 20 [US$/Ton] para vetas (Shrinkage), y un costo de ácido sulfúrico de 82 [US$/TonAc].
Para la opción ENAMI las variables económicas indican un beneficio total obtenido por Minera Rafaela de 42,16 [MMUS$], un costo total de 53,53 [MMUS$] con una inversión de 10,77 [MMUS$], con lo cual se obtiene un VAN de 16,02 [MMUS$], TIR de 55%, periodo de retorno del capital de 2 [años] y una vida útil de 8 [años].
Para la opción de venta a privados las variables económicas indican un beneficio total obtenido por Minera Rafaela de 41,97[MUS$], un costo total de 39,41 [MMUS$] con una inversión de 10,49 [MMUS$] con lo cual se obtiene un VAN de 16,21 [MMUS$], TIR de 56%, periodo de retorno del capital de 2 [años] y una vida útil de 8 [años].
Cabe destacar que en el escenario actual el negocio no es rentable, esto se debe a la baja en el precio del cobre y también a que actualmente el costo mina que se sitúa en los 30 [US$/Ton] con una operación mixta entre Room and Pillar y Shrinkage Stoping y se ha propuesto que se puede llegar a bajar hasta 15 [US$/Ton] en Room and Pillar y 20 [US$/Ton] en Shrinkage Stoping.
Las variables económicas estudiadas en este trabajo muestran un negocio factible, pero muy sensible a factores tales como el consumo de ácido, precio del cobre, costo mina y ley de cobre soluble. / The objective wich is of this memory is to analyze the feasibility of mining oxidized cooper
resources at Rafaela Mine, located in the V region of Chile in the commune of Cabildo currently
operating copper sulphide ores to a mining rate of 1500 to 1800 tons per month, labor which
currently is not being executed. For this the total present resources and the mining methods are
considered. Also two business models are analyzed: the direct selling of the ores to ENAMI and
the association with a private plant in which the profits are equally took.
The total oxidized cooper ores at Rafaela Mine (proved and inferred) estimated in this work are
2.26 [MMTon] with a grade of 2.12% and sulfuric acid consumption of 11.9 [kgAc/kgCuRec] (202
[kgAc/Ton]).
From all the considered mining methods, is concluded that the best methods taking account of the
shape of the body, quality of the rock and the present grades are Shrinkage Stoping for vein bodies
and Room and Pillar for bedrocks.
For this economic evaluation was considered a copper price of 300 [cUS$/lb] a mine cost of 15
[US$/Ton] for bedrocks (Room and Pillar) and 20 [US$/Ton] for vein bodies (Shrinkage), and a
cost of sulfuric acid of 82 [US$/TonAc].
From analyzed business alternatives, in the ENAMI option the economic variables shows an utility
of 42.16 [MMUS$], total cost of 53.53 [MUS$] with an investment of 10.77 [MMUS$], with wich
a NPV of 16.02 [MMUS$], IRR of 55%, the capital return period is 2 [years] and the lifespan is 8
[years] while with the private association the utility is 41.97 [MMUS$], total cost for Rafaela Mine
of 39.41 [MMUS$] with an investment of 10.49 [MMUS$], a NPV of 16.21 [MMUS$], IRR of
56%, the capital period return 2 [years] and the lifespan is 8 [years].
Note that in the present scenario the business is not profitable, this is due to the decline in copper
prices and also currently the mine cost stands at 30 [US$/Ton] with a mixed operation between
Room and Pillar and Shrinkage Stoping and has been proposed that can drop to 15 [US$/Ton] in
Room and Pillar and 20 [US $ / Ton] in Shrinkage Stoping.
The economic variables studied in this work shows a feasible business but very sensible to factors
like acid consumption, cooper price, mine cost and soluble copper grade.

Identiferoai:union.ndltd.org:UCHILE/oai:repositorio.uchile.cl:2250/140625
Date January 2016
CreatorsMoscoso Castillo, Elías Neftalí
ContributorsSilva Calonge, Fernando, Behn Theune, Bruno, Montes Atenas, Gonzalo
PublisherUniversidad de Chile
Source SetsUniversidad de Chile
LanguageSpanish
Detected LanguageEnglish
TypeTesis
RightsAttribution-NonCommercial-NoDerivs 3.0 Chile, http://creativecommons.org/licenses/by-nc-nd/3.0/cl/

Page generated in 0.0018 seconds