Otimização com múltiplos cenários aplicada ao planejamento da operação do sistema interligado nacional / Optimization with multiple scenarios applied to operational planning of interconnected brazilian system

Orientador: Alberto Luiz Francato / Dissertação (mestrado) - Universidade Estadual de Campinas, Faculdade de Engenharia Civil, Arquitetura e Urbanismo / Made available in DSpace on 2018-08-23T22:42:20Z (GMT). No. of bitstreams: 1
Deantoni_VictordeBarros_M.pdf: 2817178 bytes, checksum: 1c05a50aa818606a82c052b88f62c14d (MD5)
Previous issue date: 2013 / Resumo: O planejamento da operação do setor elétrico brasileiro é realizado com base em modelos que por meio de otimização determinam a geração de energia de fontes térmicas e hidráulicas. Utilizando a técnica de otimização estocástica robusta possibilita-se a análise com um conjunto de cenários históricos, com o objetivo de determinar a operação do primeiro intervalo de tempo do horizonte de planejamento, e assim obter uma solução que não necessariamente seja a melhor para um determinado cenário, mas sim uma solução que seja interessante para qualquer um dos cenários que possam ocorrer. O objetivo deste trabalho foi criar uma nova versão do modelo SolverSIN com um módulo de otimização estocástica robusta, chamado de SolverSINR, esse novo modelo permite o planejamento da operação considerando um conjunto de cenários históricos. As séries históricas são obtidas do relatório do programa mensal de operação, que é um arquivo de saída do NEWAVE. Para organização dessas séries foi desenvolvido um aplicativo chamado SHENA. O novo modelo apresentou resultados coerentes em comparação com o modelo SolverSIN determinístico e mostrou valores viáveis para a operação de reservatórios. A ferramenta permite a otimização assumindo a hipótese de repetição de uma série histórica. O modelo SolverSINR vem a contribuir como mais uma alternativa de avaliação crítica às políticas operacionais do SIN implementadas pelos modelos oficiais do SEB. Durante a avaliação de resultados notou-se que uma restrição de geração hidráulica mínima para o subsistema Nordeste causava infactibilidade em alguns cenários, adotou-se uma variável de folga para solucionar esse problema. Destaca-se que houve factibilidade nos procedimentos de operação em tempo de processamento compatível com otimização estocástica de processos em equipamentos usais para tal tarefa / Abstract: The operation planning of the interconnected power generation Brazilian system is carried out based on models through deterministic optimization power generation from thermal and hydraulic sources. Using the robust stochastic optimization technique enables the analysis grounded in a set of historical scenarios, in order to determine the operation of the first time interval of the planning horizon, and thus obtain a solution that is not necessarily the best for a selected scenario, but a solution that is interesting for any of the scenarios that might happen. The objective of this work was to create a new version of the model SolverSIN with a robust stochastic optimization module, called SolverSINR , this new model allows for the operation planning considering a set of historical scenarios . The time series is obtained from the monthly report called "pmo.dat" that is an output file from NEWAVE model. For organizing these series was developed an application called SHENA. The new model showed consistent results in comparison with the deterministic model (SolverSIN) and showed feasible values for reservoir operation. The tool allows the optimization under the assumption of repetition of a historical series. The model SolverSINR comes to contribute as an alternative assessment to critical operational policies implemented by SIN official models of SEB. During the evaluation of results was noted that a restriction of minimum hydraulic generation on Northeast subsystem caused infeasible answer in some scenarios, we adopted a penalty variable to solve this problem. It is noteworthy that there was feasibility in operating procedures in processing time compatible with stochastic optimization of processes in usual equipment for this task / Mestrado / Recursos Hidricos, Energeticos e Ambientais / Mestre em Engenharia Civil

Identiferoai:union.ndltd.org:IBICT/oai:repositorio.unicamp.br:REPOSIP/258039
Date23 August 2018
CreatorsDeantoni, Victor de Barros, 1989-
ContributorsUNIVERSIDADE ESTADUAL DE CAMPINAS, Francato, Alberto Luiz, 1969-, Barros, Mario Tadeu Leme de, Junior, Edevar Luvizotto
Publisher[s.n.], Universidade Estadual de Campinas. Faculdade de Engenharia Civil, Arquitetura e Urbanismo, Programa de Pós-Graduação em Engenharia Civil
Source SetsIBICT Brazilian ETDs
LanguagePortuguese
Detected LanguagePortuguese
Typeinfo:eu-repo/semantics/publishedVersion, info:eu-repo/semantics/masterThesis
Format147 p. : il., application/pdf