In my thesis, I applied project management in optimizing activities in the implementation of wooden buildings. I used methods of PERT and CPM, and then compared their contribution to practical use in the implementation of the historic wooden buildings of baroque truss. I suggested classification methodology sorting random effects in the implementation of timber, which will be useful in the practice of project management. Then I confronted estimates project duration calculated according to these methods with real historical truss during construction.