Methodology for the multi-objective, resource-constrained project scheduling problem

This study is concerned with the problem of resource-constrained project scheduling which includes splittable and nonsplittable jobs, renewable and nonrenewable resources, variation in resource availabi1ity, time-resource tradeoff, time-cost tradeoff, and multiple objectives.
The problem is formulated as a zero-one integer programming model. A specialized solution technique is developed for the preemptive goal programming, resource-constrained project. scheduling problem for time, cost, and resource leveling objectives. In addition, single objective algorithms are also provided for the time, cost, and resource leveling objectives. These algorithms are based on the idea of the implicit enumeration process, and use the special structures of the problem to expedite the search process.
Computer-generated problems are used to test each of the single objective algorithms. The results show that the algorithms give optimal solutions to tested problems with time and cost objectives using a reasonable computation time; however, heuristic solutions are more feasible for problems
with resource leveling objective. The multiple objective algorithm is illustrated through application to a warehouse
project problem. / Graduation date: 1993

Identiferoai:union.ndltd.org:ORGSU/oai:ir.library.oregonstate.edu:1957/35939
Date12 March 1993
CreatorsNudtasomboon, Nudtapon
ContributorsRandhawa, Sabah U.
Source SetsOregon State University
Languageen_US
Detected LanguageEnglish
TypeThesis/Dissertation

Page generated in 0.0024 seconds