Diretrizes para implementação de fluxo continuo na construção civil : uma abordagem baseada na mentalidade enxuta / Guidelines for the implementation of continuous flow in the construction industry : an approach based on lean thinking

Orientador: Flavio Augusto Picchi / Tese (doutorado) - Universidade Estadual de Campinas, Faculdade de Engenharia Civil, Arquitetura e Urbanismo / Made available in DSpace on 2018-08-13T21:18:03Z (GMT). No. of bitstreams: 1
Bulhoes_IamaraRossi_D.pdf: 3095643 bytes, checksum: f334cd2fe1eec7e0b2f48cca80f0b04b (MD5)
Previous issue date: 2009 / Resumo: Os sistemas de produção na construção civil são caracterizados por muitas interrupções nos seus fluxos de trabalho, gerando desperdícios e a subutilização de recursos. Tais interrupções ocorrem principalmente devido à alta variabilidade nos processos de produção e à falta de sincronização entre os mesmos, resultando em elevadas percentagens de tempos improdutivos e de grandes estoques em processo. O presente trabalho tem como objetivo propor diretrizes para a implementação de fluxo contínuo na construção civil, com base nos conceitos e ferramentas da Mentalidade Enxuta. A estratégia de pesquisa adotada foi a pesquisa-ação, sendo realizados quatro estudos empíricos, dois em obras de edificações e dois em obras de montagem de estruturas pré-fabricadas de concreto. Duas principais contribuições desta pesquisa podem ser destacadas: (a) as diretrizes para implementar fluxo contínuo, vinculadas às etapas de diagnóstico, criação de condições iniciais, e planejamento e controle da produção; e (b) uma contribuição teórica no sentido de entender um conjunto de conceitos e princípios básicos de gestão da produção e a sua aplicação na indústria da construção. As diretrizes propostas para o contexto de obras de edificações são focadas no sistema de planejamento e controle da produção e na adaptação das ferramentas da Mentalidade Enxuta, tais como Mapa de Fluxo de Valor, Gráfico do Balanceamento do Operador e Tabela do Trabalho Padronizado Combinado, enquanto no contexto de obras de montagem de estrutura pré-fabricada as diretrizes enfatizam a realização do diagnóstico do processo de montagem, a introdução do planejamento integrado do projeto, fabricação e montagem, e a redução do tamanho do lote. Através destas diretrizes propõe-se o uso combinado das ferramentas tradicionais da Mentalidade Enxuta com ferramentas de Planejamento e Controle da Produção adequadas ao ambiente da construção civil. / Abstract: Production systems in the construction industry face many interruptions in work flows, causing waste and under-utilization of resources. Such interruptions are mostly due to high variability in production processes and also to the lack of synchronization between them, resulting in a large percentage of unproductive time and a high level of work in progress. The aim of this research work is to propose guidelines for the implementation of continuous flow in the construction industry, based on the Lean Thinking concepts and tools. Action research was the research strategy adopted in this study, involving four empirical studies, two in building projects and two in the fabrication and assembly of pre-fabricated concrete structures. Two main contributions of this research work are pointed out: (a) a set of guidelines for implementing continuous flow in production systems in the construction industry, which were related to the stages of diagnosis, establishment of the initial conditions, and planning and control; and (b) a theoretical contribution in terms of understanding a set of core production management concepts and principles and its application in the construction industry. The guidelines proposed for the context of building projects are focused on the production planning and control system and on the adaptation of Lean Thinking tools, such as Value Stream Mapping, Operator Balance Chart and Combined Standardized Work Chart, while in the context of prefabrication and assembly of concrete structures the guidelines emphasize the diagnosis of the assembly process, the introduction of an integrated planning and control process, including design prefabrication and assembly, and the reduction of lot size. Through those guidelines, the combined use of traditional Lean Thinking tools and planning and control tools that are suitable for the construction industry context. / Doutorado / Edificações / Doutor em Engenharia Civil

Identiferoai:union.ndltd.org:IBICT/oai:repositorio.unicamp.br:REPOSIP/258136
Date13 August 2018
CreatorsBulhões, Iamara Rossi
ContributorsUNIVERSIDADE ESTADUAL DE CAMPINAS, Picchi, Flavio Augusto, 1957-, Heineck, Luiz Fernando Mahlmann, Saurin, Tarcisio Abreu, Granja, Ariovaldo Denis, Ilha, Marina Sangoi de Oliveira
Publisher[s.n.], Universidade Estadual de Campinas. Faculdade de Engenharia Civil, Arquitetura e Urbanismo, Programa de Pós-Graduação em Engenharia Civil
Source SetsIBICT Brazilian ETDs
LanguagePortuguese
Detected LanguagePortuguese
Typeinfo:eu-repo/semantics/publishedVersion, info:eu-repo/semantics/doctoralThesis
Format339 p. : il., application/pdf
Sourcereponame:Repositório Institucional da Unicamp, instname:Universidade Estadual de Campinas, instacron:UNICAMP
Rightsinfo:eu-repo/semantics/openAccess

Page generated in 0.0026 seconds