Factors that influence late payments in government new build infrastructure projects in Gauteng Province, South Africa

A research report submitted in partial fulfillment of the requirements for the degree of Master of Science in Building to the Faculty of Engineering and the Built Environment, School of Architecture and Planning at the University of the Witwatersrand, Johannesburg, 2017 / Payments are an essential component of construction contracts (Murdoch and Hughs, 2015). The nature of the payment regime has an effect on the contractor’s cash flow, project performance and therefore achievement of project objectives.
Finance has been claimed as the most important resource in the construction process (Mawdesley et al., 1997). As such, proper financial planning to ensure healthy cash flow during the lifespan of a project is central to its performance and ultimate success. The obligation of an employer is to pay the contractor timeously, as per agreed payment plan and likewise the obligation of a contractor is to produce the build works according to an agreed schedule of works and to set standards of quality. Project finance in its totality is therefore of major importance to the progression of the construction process.
Purpose - The main purpose of this study is to identify current problems in relation to late payment issues encountered by contractors that have been commissioned to construct public infrastructure for the government of South Africa. The paper seeks to highlight the extent of occurrence, to measure, and to assess the extent of late payment, in public infrastructure projects in the Gauteng Province. This study is done with a view to study the correlative relationship between the deviance in contractually scheduled payment time and time of actual payment and to identify factors that influence these.
Design methodology and approach – With regard to research methods, the study adopts a mixed approach. Both Qualitative and Quantitative approaches to the study were adopted. This was done by collecting data through structured questionnaires and the research instruments administered to key personnel in the various Sector Departments as well as the Finance Department and the Gauteng Department of Infrastructure Development. Sample invoices were gleaned and scrutinized from 189 projects with regard to invoice payment data. Respondents were asked to provide information on Invoice Date, Date Invoice Received By Department and Date Invoice Paid On. This information was gathered for approximately half the total number of invoices received per project. Adopting a project by project approach, respondents were asked to provide data and causal factors linked to late payment. The results were then analyzed to determine significant relationships between late payment patterns and the factors that influence these. / XL2018

Identiferoai:union.ndltd.org:netd.ac.za/oai:union.ndltd.org:wits/oai:wiredspace.wits.ac.za:10539/24099
Date January 2017
CreatorsDjokoto, Vincent Kojovi Tengey
Source SetsSouth African National ETD Portal
LanguageEnglish
Detected LanguageEnglish
TypeThesis
FormatOnline resource (129, [40], 5, [7] leaves), application/pdf, application/pdf, application/pdf