Evaluation of Synthetic Unit Hydrograph Techniques For Utah Probable Maximum Flood Determinations

Every dam must be capable of safely passing a predetermined flood magnitude. For high-hazard dams, it is a common practice to require that this flood be the Probable Maximum Flood (PMF). The determination of the PMF starts with the determination of the Probable Maximum Precipitation (PMP). We used the generalized estimates of the PMP as outlined in Hydrometeorological Report (HMR) 49. In this study we used the storm event model approach to convert the PMP into PMF. Different synthetic unit hydrograph (SUH) techniques were then used in the conversion process. The Soil Conservation Service (SCS) curve number method was used to estimate the losses, and the U.S. Bureau of Reclamation (USBR) lag time relationship was used as the basis for estimating the time parameters for the different (SUH) methods.
The objectives of this study were 1) to evaluate the theoretical and empirical basis for the SUH methods that are commonly used for Utah PMF determinations; 2) to compare the PMF determinations for representative Utah watersheds based on alternative SUH methods using Geographic Information System (GIS) techniques, and to explore the effects of parameter uncertainty ; and 3) to make recommendations for the selection and use of SUH methods for Utah PMF determinations.
An interactive PMF modeling system was formulated. The modeling system processes the different databases and estimates the parameters required for HEC 1 model input to produce the PMF hydrograph. Five SUHs were used, tbe SCS, Clark, Snyder, USBR, and the Corps of Engineers (COE) LA valley S-graph. Seven representative Utah high-hazard dam sites were selected and used in the evaluation of the five SUH techniques, focusing on their procedure, practice and applicability, and analytical and empirical evaluations.
GIS procedures proved to be a very efficient and flexible means for obtaining rainfall-runoff model inputs. Deviation of the site-specific time-area curve from the default curve in HEC 1 leads to errors in the peak flow estimate. In the absence of suitable events for site-specific development of unit hydrographs, the USBR SUH technique is to be used, but careful consideration should be given to the appropriateness of the use of local storm K, values for Utah local storm PMFs.

Identiferoai:union.ndltd.org:UTAHS/oai:digitalcommons.usu.edu:etd-5564
Date01 May 1995
CreatorsShammet, Ashraf Mohammed
PublisherDigitalCommons@USU
Source SetsUtah State University
Detected LanguageEnglish
Typetext
Formatapplication/pdf
SourceAll Graduate Theses and Dissertations
RightsCopyright for this work is held by the author. Transmission or reproduction of materials protected by copyright beyond that allowed by fair use requires the written permission of the copyright owners. Works not in the public domain cannot be commercially exploited without permission of the copyright owner. Responsibility for any use rests exclusively with the user. For more information contact Andrew Wesolek (andrew.wesolek@usu.edu).

Page generated in 0.0022 seconds