Return to search

A generalized ANN-based model for short-term load forecasting

Short-term load forecasting (STLF) deals with forecasting of hourly system demand with a lead time ranging from one hour to 168 hours. The basic objective of the STLF is to provide for economic, reliable and secure operation of the power system.

This dissertation establishes a new approach to artificial neural network (ANN) based STLF. It first decomposes the prediction problem into representation and function approximation problems. The representation problem is solved using phase-space embedding which identifies time delay variables from load time series that are used in forecasting. The concept is inherently different from the methods used so far because it does not use correlated variables for forecasting. Temperature variables are included as well using identified embedding parameters. Function approximation problem is approached using ANN ensemble and active selection of a training set. Training set is selected based on predicted weather parameters for a prediction horizon. Selection is done applying the k-nearest neighbors technique in a temperature-based vector space. A novel approach of pilot set simulation is used to determine the number of hidden units for every forecast period. Ensemble consists of two ANNs which are trained and cross validated on complementary training sets. Final prediction is obtained by a simple average of two trained ANNs.

The described technique is used for predicting one week’s load in four selected months in summer peaking and winter peaking US utilities. Mean absolute percent errors (MAPEs) for 24-hour lead time predictions are slightly greater than 2% for all months. For 120-hour lead time (weekday) predictions, MAPEs are around 2.3%. MAPEs for 48- hour lead time (weekend) predictions are around 2.5%. Maximal errors for these cases are around 7%. Predictions for one-hour lead time are slightly higher than 1% for all months, with maximal errors not exceeding 4.99%. Peak load MAPEs are 2.3% for both utilities. Maximal peak-load errors do not exceed 6%. The technique shows very good performance faced with sudden and large changes in weather. For changes in temperature larger than 20° F for two consecutive days, forecasting error is smaller than 3.58%. / Ph. D.

Identiferoai:union.ndltd.org:VTETD/oai:vtechworks.lib.vt.edu:10919/38028
Date06 June 2008
CreatorsDrezga, Irislav
ContributorsElectrical Engineering, Rahman, Saifur, Broadwater, Robert P., VanLandingham, Hugh F., Conners, Richard W., Sarin, Subhash C.
PublisherVirginia Tech
Source SetsVirginia Tech Theses and Dissertation
LanguageEnglish
Detected LanguageEnglish
TypeDissertation, Text
Formatx, 192 leaves, BTD, application/pdf, application/pdf
RightsIn Copyright, http://rightsstatements.org/vocab/InC/1.0/
RelationOCLC# 37210432, LD5655.V856_1996.D749.pdf

Page generated in 0.002 seconds