In the present work, stochastic network models representing a project as a set of activities are studied, as well as different approaches to these models. The critical path method, stochastic network models with probability constraints, finding a reference project duration, worst-case analysis in stochastic networks and optimization of the parameters of the probability distributions of the activity durations are studied. Use of stochastic network models in telecommunications networks is also briefly presented. In a numerical study, some of these models are implemented and the~related numerical results are analyzed.