The sewage sewer is in charge of the network and advance the risk of constructing to assess the research with quantitative analysis / 污水下水道分管網推進施工風險評估與量化分析之研究

碩士 / 國立中央大學 / 土木工程研究所 / 94 / The sewage system has become an indispensable public works. Its function has gradually evolved from its traditional goals to having multi-purpose benefits; it not only elevates the feasibility of water recycling, but is also listed by advanced countries as an important indicator of the urban environment. It is an indispensable public works in the modern city, and has the functions of elevating the culture of living and improving the water environmental aesthetic.
Sewage pipe network engineering usually uses tunnel jacking construction method, which is widely used and replaced the traditional open cut dredging method. The pipe jacking construction of sewage pipe network engineering is all conducted underground. If on-site conditions are unclear, the risk factors upon construction cannot be overlooked. Such risks should be analyzed and managed. The main effects caused by construction risks are “cost” and “progress.” A detailed consideration of the influence of risk factors on progress and cost before construction would be a basis for evaluating the construction budget and the construction period.
This study seeks to explore the various construction uncertainties while constructing a sewage pipe network, and establishes an appropriate risk quantification evaluation model and analysis, in hopes that the results of the risk quantification evaluation model can be used as a basis of reference upon establishing the construction budget and period. This method reflects the indirect effects caused on budget and construction period on the practically executed budget and construction period, so that the actual budget and construction period become reasonable. After systematic summarization and organization, this study divides construction uncertainty factors into five main aspects and fourteen sub-aspects of factors. It uses the quantification evaluation model established by this study in expert questionnaires for main sponsors of construction, engineering consulting firms, and professional construction companies to make assessments on the chances of occurrence of risk factors and impacts on losses, and calculates risk values as a reference basis for future studies relating to risk management strategies.

Identiferoai:union.ndltd.org:TW/094NCU05015065
Date January 2006
CreatorsSHU-FEN TSAI, 蔡淑芬
ContributorsJyh-Dong Lin, 林志棟
Source SetsNational Digital Library of Theses and Dissertations in Taiwan
Languagezh-TW
Detected LanguageEnglish
Type學位論文 ; thesis
Format199

Page generated in 0.0128 seconds