碩士 / 國立中興大學 / 土木工程學系所 / 96 / The project has quite a lot of repetitiveness that arranges Cheng at construction stage at present, mostly adopted traditional CPM way to arrange Cheng in the past, but found much repeated homework was highly similar, cause the building site if meeting the factor of hindering, the transfer of change resources that can''t be prompt and effective, with making a adjustment of carrying on the working project, let alone continue and arrange Cheng last time, therefore cause the waste of operating point stopping and resources.
Project actual quite a lot hindrance that experience reach, for example pipeline is it move factor, weather factor, area factor, crossing pass through factor, common people entrances and exits factor,etc. Dr.eye: to cooperate, influence difficulty degree that the project constructed, cause and build manufacturer''s project cost to increase, the adding to of dropping in government''s budget enforcement rate and budget, cause the worker Gong Gong and Cheng YanDang to cause the decline of whole economy, the puzzlement causing common people even more is aggravated but resentment rise from all around, therefore can know to control the project progress and shorten time limit for a project and retrieving surplus resources to utilize and become the most important subject instantly again effectively.
This research will regard distance as and repeat the unit change in order to regard day as the unit of repeating originally, arranging Cheng linearly of the planning to make new advances and repeating type attitude, traditional CPM used generally to analyse separately arrange Cheng can overcome repetitiveness arrange planning complicated shortcoming of Cheng and simplify Engineer a step and approximate and perfect very much ( Factor without hitch) Arrange Cheng,arrange there aren''t Cheng as algorithm of performing, find out relevant pluses and minuses that contrast, through verify heuristic to perform algorithm arrange Cheng arrange than traditional CPM Cheng save more time limit for a project and reduce the project cost, reach benefit of the essence.
This research utilizes the true project to channel into the heuristic algorithm of performing and arrange Cheng linearly, the construction state of the detailed record and on-the-spot detail of project, analyse relevant data got, assess its utilization benefit and shortcoming, propose finally the solution on the suggestion is for studying and improving and setting out to press close to arranging Cheng of practice in the future.
Identifer | oai:union.ndltd.org:TW/096NCHU5015066 |
Date | January 2008 |
Creators | Wen-Chung Chou, 周文忠 |
Contributors | Machine Hsie, 謝孟勳 |
Source Sets | National Digital Library of Theses and Dissertations in Taiwan |
Language | zh-TW |
Detected Language | English |
Type | 學位論文 ; thesis |
Format | 54 |
Page generated in 0.0138 seconds