碩士 / 國立臺灣海洋大學 / 商船學系 / 102 / On projects such as oil refining industry, petrochemical industry and even the power industry, shipbuilding industry for new construction or maintenance works in corrosive environments when considering different industries, using coat for blocking and inhibiting corrosion prevention method to improve industrial facilities, ships and corrosion resistance ensure the safety of the overall structure. Although the first line of defense paint protection system as a whole, but the project is in the works with the anti-corrosion paint throughout and comprehensiveness of the location, shipping companies and manufacturers of construction Individually its operating costs while considering the design, procurement, contracting, construction of the business, how it works on the construction volume control and risk assessment for the implementation of pricing, cost control and budget management and control period is important
This research is to explore the needs of the contract in the face of manufacturers offer period, as the owners provide only the basic conceptual design, a rough layout of the plant and its construction area roughly quantity, material requirements specification, and so on. Due to the preliminary information is not sufficient, and the limited time quotes, made of paint works efficiently and accurately estimate the number of methods are not solid.
Comprehensive results of this study to estimate the best practice method but use their theory and statistics paint the actual construction of the comparative analysis and judgment to assess interference factors that can quickly and efficiently according to different types of paint specification and construction of parts or regions with different construction methods calculate the amount of construction and provide different categories to be engineers estimate the total cost of construction, carried out quickly and efficiently to achieve the correct valuation of the paint works.
This research clear judgment different risk factor, and obtains following result:
(1) Causes the estimate work to compare tradition estimate method correct &; to be fast.
(2) Wins a bidding sends the package of datum quantity according to its estimate quantity as the budget establishment and the project to carry on the cost management to be more accurate than the traditional estimate method.
(3) Correct rationale can push fast estimates the correct quantity to do for the time limit for a project appraisal and the time interval management.
Thus from this obtains the best construction quality and the benefit.
Identifer | oai:union.ndltd.org:TW/102NTOU5728013 |
Date | January 2014 |
Creators | JENG,REN-JYE, 鄭仁傑 |
Contributors | Chang,Ki-Yin, 張啓隱 |
Source Sets | National Digital Library of Theses and Dissertations in Taiwan |
Language | zh-TW |
Detected Language | English |
Type | 學位論文 ; thesis |
Format | 103 |
Page generated in 0.0057 seconds