Global ETD Search

Search theses and dissertations gathered from participating repositories worldwide. Every result links back to the library that holds it. No account is needed.

Results

Showing 1 to 10 of 10 for “"closure pour"”.

  1. Corrosion Assessment for Failed Bridge Deck Closure Pour

    … deck. After 17 years in service, a 3ft x3ft closure pour section punched through. It was part of the left wheel path of the south bound right lane of the bridge deck. The bridge deck was replaced in 1992 as part of a bridge rehabilitation project, epoxy coated reinforcement were used as the …

    vt Repository record for Corrosion Assessment for Failed Bridge Deck Closure Pour (opens in a new tab)

  2. Fatigue Assessment for Failed Bridge Deck Closure Pour

    After 17 years in service, a 3 ft by 3 ft closure pour section of an Interstate 81 (I-81) bridge deck failed by punching through near Marion, Virginia. Visual inspection noted that there was considerable corrosion on some of the reinforcing bars in the vicinity of the construction joint, while …

    vt Repository record for Fatigue Assessment for Failed Bridge Deck Closure Pour (opens in a new tab)

  3. Connection of modular steel beam precast slab units with cast-in-place closure pour slabs

    … extensive in-field formwork and lengthy traffic closures. The Texas Department of Transportation proposes a new method of constructing jointless bridges using prefabricated girder-and-deck units connected on-site with cast-in-place closure pours. This new system will expedite construction and …

    tamu Repository record for Connection of modular steel beam precast slab units with cast-in-place closure pour slabs (opens in a new tab)

  4. Investigation of Longitudinal Joints Between Precast Prestressed Deck Bulb Tee Girders Using Latex Modified Concrete

    … of latex modified concrete (LMC) as a closure pour material with a U-bar connection detail in longitudinal joints between precast deck bulb tee bridge girders with integral concrete decks. The objective was to determine if the joint detail was capable of resisting service shear and …

    south-carolina Repository record for Investigation of Longitudinal Joints Between Precast Prestressed Deck Bulb Tee Girders Using Latex Modified Concrete (opens in a new tab)

  5. Exploring Fiber-Reinforced Polymer Concrete for Accelerated Bridge Construction Applications

    … polymer concrete (FRPC) was explored as a closure pour material for bridges to connect adjacent precast superstructure elements. Polymer concretes have been used successfully as a non-structural overlay material in transportation systems for many decades. With the addition of fibers, FRPC …

    washington Repository record for Exploring Fiber-Reinforced Polymer Concrete for Accelerated Bridge Construction Applications (opens in a new tab)

  6. Laboratory testing of full-depth precast, prestressed concrete deck panels used in the Boone County IBRC accelerated bridge replacement project

    … a single panel and on two panels connected by a closure pour. These tests ranged from determining physical properties of the panel (compressive strength and prestressing force), to determining the panel's response in various circumstances (moving with a crane, during field leveling, and under …

    iastate Repository record for Laboratory testing of full-depth precast, prestressed concrete deck panels used in the Boone County IBRC accelerated bridge replacement project (opens in a new tab)

  7. Durability and Fatigue Behavior of CIP Concrete Connections for Accelerated Bridge Construction

    … The procedure for selecting durable closure pour (CP) materials for the connections is discussed firstly. The accelerated construction is quantified as two categories: overnight cure and 7-day cure of CP materials. Candidate materials are selected first based on literature review as …

    utk-theses Repository record for Durability and Fatigue Behavior of CIP Concrete Connections for Accelerated Bridge Construction (opens in a new tab)

  8. Ultra-high performance concrete (UHPC) for closure pours between precast concrete deck panels

    … bridge construction, UHPC can be used as joint pour between precast structural elements such as deck panels and bulb-T girders. The usage of UHPC can significantly reduce construction time and long-term maintenance cost of bridges. However, commercially available UHPC is prohibitively expensive …

    gatech Repository record for Ultra-high performance concrete (UHPC) for closure pours between precast concrete deck panels (opens in a new tab)

  9. STRUCTURAL TESTING OF NON-PROPRIETARY UHPC FOR CLOSURE POURS BETWEEN PRECAST BRDIGE DECK PANELS

    … to the viability of the non-proprietary mix for closure pour applications. The mix proved successful in this regard, indicated by all four-large scale structural test specimens failing via crushing of the precast concrete panels rather than failure being governed by the UHPC joint. The UHPC joint …

    gatech Repository record for STRUCTURAL TESTING OF NON-PROPRIETARY UHPC FOR CLOSURE POURS BETWEEN PRECAST BRDIGE DECK PANELS (opens in a new tab)

  10. Structural Testing Of Non-Proprietary UHPC For Closure Pours Used In Standard GDOT Precast Bridge Deck Panels

    … and environmentally sustainable. The closure joint is a critical component of a bridge that accommodates the expansion and contraction of the bridge deck due to temperature changes. The UHPC mix was used to fill the closure joint between two adjacent bridge slabs. The performance of …

    gatech Repository record for Structural Testing Of Non-Proprietary UHPC For Closure Pours Used In Standard GDOT Precast Bridge Deck Panels (opens in a new tab)