{"id":{"repo_id":"alberta","oai_identifier":"oai:ualberta.scholaris.ca:123456789/74396"},"canonical_url":"https://search.ndltd.org/etd/alberta/oai:ualberta.scholaris.ca:123456789/74396","repository":{"repo_id":"alberta","name":"University of Alberta","base_url":"https://era.library.ualberta.ca/oai"},"display":{"title":"An Integrated Simulation-based Planning Approach for Construction Projects","abstract":"Cost and schedule integration can improve efficiencies in construction planning and control since they are key constraints in project delivery and closely related. This research provides a framework for cost and schedule integration, and transforms the model to simulation-based planning in which the uncertainties of project cost and schedule are evaluated through computer simulation. This has been achieved through explicitly incorporating risk, resource, and detailed operation into a work-packaging model. The developed framework has been implemented in the Simphony.Net modeling environment as a special purpose simulation tool called ISP (integrated simulation-based planning). The ISP’s main framework is a simulation-based network analysis based on a precedence diagram method. The ISP tool application has been demonstrated with a hypothetical road construction project. The approach is useful for considering risks in the early stages of project planning for investigating a range of possible project completion times and cost estimates in multiple scenarios.","abstract_html":"Cost and schedule integration can improve efficiencies in construction planning and control since they are key constraints in project delivery and closely related. This research provides a framework for cost and schedule integration, and transforms the model to simulation-based planning in which the uncertainties of project cost and schedule are evaluated through computer simulation. This has been achieved through explicitly incorporating risk, resource, and detailed operation into a work-packaging model. The developed framework has been implemented in the Simphony.Net modeling environment as a special purpose simulation tool called ISP (integrated simulation-based planning). The ISP’s main framework is a simulation-based network analysis based on a precedence diagram method. The ISP tool application has been demonstrated with a hypothetical road construction project. The approach is useful for considering risks in the early stages of project planning for investigating a range of possible project completion times and cost estimates in multiple scenarios.","abstract_has_math":false,"creators":["Hong, Jangmi"],"institution":"University of Alberta","degree_name":"Master of Science","degree_level":"Master's","degree_discipline":"Construction Engineering & Management","degree_department":null,"school":null,"contributors":[],"advisors":["AbouRizk, Simaan (Civil & Environmental Engineering)"],"committee_chairs":[],"committee_members":[],"year":2012,"date_issued":"2012-06","date_published":"2012-06","updated_at":"2026-11-26T20:51:43Z","subjects":["Cost and schedule integration","Construcion management","Risk breakdown structure","Simulation-based planning","Work-packaging model","Risk analysis","Work breakdown structure"],"languages":["en"],"rights":["This thesis is made available by the University of Alberta Libraries with permission of the copyright owner solely for non-commercial purposes. This thesis, or any portion thereof, may not otherwise be copied or reproduced without the written consent of the copyright owner, except to the extent permitted by Canadian copyright law."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://doi.org/10.7939/R37K7J","outbound_label":"DOI","outbound_source":"dc:identifier.doi","record_url":"https://doi.org/10.7939/R37K7J","record_label":"Repository record","record_kind":"doi","record_source":"dc:identifier.doi","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Aalberta%3Aoai%3Aualberta.scholaris.ca%3A123456789%2F74396","prefix":"oai_dc"},"source_record":{"url":"https://era.library.ualberta.ca/oai?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Aualberta.scholaris.ca%3A123456789%2F74396","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["AbouRizk, Simaan (Civil & Environmental Engineering)"]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Lu, Ming (Civil and Environmental Engineering)","Marquez, Horacio J. (Electrical and Computer Engineering)","AbouRizk, Simaan (Civil and Environmental Engineering)"]},{"key":"dc:creator","label":"Author","values":["Hong, Jangmi"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2025-05-28T19:15:10Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2025-05-28T19:15:10Z"]},{"key":"dc:date.issued","label":"Date","values":["2012-06"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Construction Engineering & Management"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Master's"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["University of Alberta"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject","label":"Dc Subject","values":["Cost and schedule integration","Construcion management","Risk breakdown structure","Simulation-based planning","Work-packaging model","Risk analysis","Work breakdown structure"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language.iso","label":"Language (ISO)","values":["en"]},{"key":"dc:rights","label":"Dc Rights","values":["This thesis is made available by the University of Alberta Libraries with permission of the copyright owner solely for non-commercial purposes. This thesis, or any portion thereof, may not otherwise be copied or reproduced without the written consent of the copyright owner, except to the extent permitted by Canadian copyright law."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.doi","label":"DOI","values":["https://doi.org/10.7939/R37K7J"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["Cost and schedule integration can improve efficiencies in construction planning and control since they are key constraints in project delivery and closely related. This research provides a framework for cost and schedule integration, and transforms the model to simulation-based planning in which the uncertainties of project cost and schedule are evaluated through computer simulation. This has been achieved through explicitly incorporating risk, resource, and detailed operation into a work-packaging model. The developed framework has been implemented in the Simphony.Net modeling environment as a special purpose simulation tool called ISP (integrated simulation-based planning). The ISP’s main framework is a simulation-based network analysis based on a precedence diagram method. The ISP tool application has been demonstrated with a hypothetical road construction project. The approach is useful for considering risks in the early stages of project planning for investigating a range of possible project completion times and cost estimates in multiple scenarios."]},{"key":"dc:title","label":"Title","values":["An Integrated Simulation-based Planning Approach for Construction Projects"]},{"key":"others:access_status","label":"Others Access Status","values":["open.access"]}]}],"canonical_facts":{"dc:contributor.advisor":["AbouRizk, Simaan (Civil & Environmental Engineering)"],"dc:contributor.other":["Lu, Ming (Civil and Environmental Engineering)","Marquez, Horacio J. (Electrical and Computer Engineering)","AbouRizk, Simaan (Civil and Environmental Engineering)"],"dc:creator":["Hong, Jangmi"],"dc:date.accessioned":["2025-05-28T19:15:10Z"],"dc:date.available":["2025-05-28T19:15:10Z"],"dc:date.issued":["2012-06"],"dc:description.abstract":["Cost and schedule integration can improve efficiencies in construction planning and control since they are key constraints in project delivery and closely related. This research provides a framework for cost and schedule integration, and transforms the model to simulation-based planning in which the uncertainties of project cost and schedule are evaluated through computer simulation. This has been achieved through explicitly incorporating risk, resource, and detailed operation into a work-packaging model. The developed framework has been implemented in the Simphony.Net modeling environment as a special purpose simulation tool called ISP (integrated simulation-based planning). The ISP’s main framework is a simulation-based network analysis based on a precedence diagram method. The ISP tool application has been demonstrated with a hypothetical road construction project. The approach is useful for considering risks in the early stages of project planning for investigating a range of possible project completion times and cost estimates in multiple scenarios."],"dc:identifier.doi":["https://doi.org/10.7939/R37K7J"],"dc:language.iso":["en"],"dc:rights":["This thesis is made available by the University of Alberta Libraries with permission of the copyright owner solely for non-commercial purposes. This thesis, or any portion thereof, may not otherwise be copied or reproduced without the written consent of the copyright owner, except to the extent permitted by Canadian copyright law."],"dc:subject":["Cost and schedule integration","Construcion management","Risk breakdown structure","Simulation-based planning","Work-packaging model","Risk analysis","Work breakdown structure"],"dc:title":["An Integrated Simulation-based Planning Approach for Construction Projects"],"dc:type":["Thesis"],"others:access_status":["open.access"],"thesis:degree_discipline":["Construction Engineering & Management"],"thesis:degree_level":["Master's"],"thesis:degree_name":["Master of Science"],"thesis:institution_name":["University of Alberta"]},"updated_at":"2026-11-26T20:51:43Z"}