{"id":{"repo_id":"alberta","oai_identifier":"oai:ualberta.scholaris.ca:123456789/86802"},"canonical_url":"https://search.ndltd.org/etd/alberta/oai:ualberta.scholaris.ca:123456789/86802","repository":{"repo_id":"alberta","name":"University of Alberta","base_url":"https://era.library.ualberta.ca/oai"},"display":{"title":"Project Controls for Engineering Work in Practice","abstract":"Engineering work can account for 10% to 20% of capital project costs, and up to 50% of a project’s schedule. The construction industry rigorously implements control techniques to minimize cost and schedule overruns; however, the same cannot be said for controlling engineering work. Over the years, engineering work has proven its susceptibility to cost and schedule overrun, yet controls have not been implemented to the same level of rigor. In practice, engineering work is controlled through techniques such as schedule and accounting summaries and neglects the relationship between cost, schedule and progress. This research aims to improve project control of engineering work in practice by adapting Earned Value Management (EVM) techniques used in construction to the requirements of engineering work. Techniques for EVM baseline development and maintenance, progress measurement, performance analysis, forecasting, and corrective action are customized to the engineering effort and successfully applied on two major engineering projects.","abstract_html":"Engineering work can account for 10% to 20% of capital project costs, and up to 50% of a project’s schedule. The construction industry rigorously implements control techniques to minimize cost and schedule overruns; however, the same cannot be said for controlling engineering work. Over the years, engineering work has proven its susceptibility to cost and schedule overrun, yet controls have not been implemented to the same level of rigor. In practice, engineering work is controlled through techniques such as schedule and accounting summaries and neglects the relationship between cost, schedule and progress. This research aims to improve project control of engineering work in practice by adapting Earned Value Management (EVM) techniques used in construction to the requirements of engineering work. Techniques for EVM baseline development and maintenance, progress measurement, performance analysis, forecasting, and corrective action are customized to the engineering effort and successfully applied on two major engineering projects.","abstract_has_math":false,"creators":["Kostelyk, Jesse D."],"institution":"University of Alberta","degree_name":"Master of Science","degree_level":"Master's","degree_discipline":"Construction Engineering and Management","degree_department":null,"school":null,"contributors":[],"advisors":["AbouRizk, Simaan (Civil and Environmental Engineering)"],"committee_chairs":[],"committee_members":[],"year":2012,"date_issued":"2012-06","date_published":"2012-06","updated_at":"2026-11-26T21:57:48Z","subjects":["Earned Value Management","Forecasting","EVA","Engineering Work","Project Controls","Baseline Development","Progress Measurement","Baseline Maintenance"],"languages":["en"],"rights":["This thesis is made available by the University of Alberta Libraries with permission of the copyright owner solely for non-commercial purposes. This thesis, or any portion thereof, may not otherwise be copied or reproduced without the written consent of the copyright owner, except to the extent permitted by Canadian copyright law."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://doi.org/10.7939/R3XM73","outbound_label":"DOI","outbound_source":"dc:identifier.doi","record_url":"https://doi.org/10.7939/R3XM73","record_label":"Repository record","record_kind":"doi","record_source":"dc:identifier.doi","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Aalberta%3Aoai%3Aualberta.scholaris.ca%3A123456789%2F86802","prefix":"oai_dc"},"source_record":{"url":"https://era.library.ualberta.ca/oai?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Aualberta.scholaris.ca%3A123456789%2F86802","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["AbouRizk, Simaan (Civil and Environmental Engineering)"]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Kumar, Amit (Mechanical Engineering)","AbouRizk, Simaan (Civil and Environmental Engineering)","Mohammed, Yasser (Civil and Environmental Engineering)"]},{"key":"dc:creator","label":"Author","values":["Kostelyk, Jesse D."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2025-05-29T06:52:02Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2025-05-29T06:52:02Z"]},{"key":"dc:date.issued","label":"Date","values":["2012-06"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Construction Engineering and Management"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Master's"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["University of Alberta"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject","label":"Dc Subject","values":["Earned Value Management","Forecasting","EVA","Engineering Work","Project Controls","Baseline Development","Progress Measurement","Baseline Maintenance"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language.iso","label":"Language (ISO)","values":["en"]},{"key":"dc:rights","label":"Dc Rights","values":["This thesis is made available by the University of Alberta Libraries with permission of the copyright owner solely for non-commercial purposes. This thesis, or any portion thereof, may not otherwise be copied or reproduced without the written consent of the copyright owner, except to the extent permitted by Canadian copyright law."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.doi","label":"DOI","values":["https://doi.org/10.7939/R3XM73"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["Engineering work can account for 10% to 20% of capital project costs, and up to 50% of a project’s schedule. The construction industry rigorously implements control techniques to minimize cost and schedule overruns; however, the same cannot be said for controlling engineering work. Over the years, engineering work has proven its susceptibility to cost and schedule overrun, yet controls have not been implemented to the same level of rigor. In practice, engineering work is controlled through techniques such as schedule and accounting summaries and neglects the relationship between cost, schedule and progress. This research aims to improve project control of engineering work in practice by adapting Earned Value Management (EVM) techniques used in construction to the requirements of engineering work. Techniques for EVM baseline development and maintenance, progress measurement, performance analysis, forecasting, and corrective action are customized to the engineering effort and successfully applied on two major engineering projects."]},{"key":"dc:title","label":"Title","values":["Project Controls for Engineering Work in Practice"]},{"key":"others:access_status","label":"Others Access Status","values":["open.access"]}]}],"canonical_facts":{"dc:contributor.advisor":["AbouRizk, Simaan (Civil and Environmental Engineering)"],"dc:contributor.other":["Kumar, Amit (Mechanical Engineering)","AbouRizk, Simaan (Civil and Environmental Engineering)","Mohammed, Yasser (Civil and Environmental Engineering)"],"dc:creator":["Kostelyk, Jesse D."],"dc:date.accessioned":["2025-05-29T06:52:02Z"],"dc:date.available":["2025-05-29T06:52:02Z"],"dc:date.issued":["2012-06"],"dc:description.abstract":["Engineering work can account for 10% to 20% of capital project costs, and up to 50% of a project’s schedule. The construction industry rigorously implements control techniques to minimize cost and schedule overruns; however, the same cannot be said for controlling engineering work. Over the years, engineering work has proven its susceptibility to cost and schedule overrun, yet controls have not been implemented to the same level of rigor. In practice, engineering work is controlled through techniques such as schedule and accounting summaries and neglects the relationship between cost, schedule and progress. This research aims to improve project control of engineering work in practice by adapting Earned Value Management (EVM) techniques used in construction to the requirements of engineering work. Techniques for EVM baseline development and maintenance, progress measurement, performance analysis, forecasting, and corrective action are customized to the engineering effort and successfully applied on two major engineering projects."],"dc:identifier.doi":["https://doi.org/10.7939/R3XM73"],"dc:language.iso":["en"],"dc:rights":["This thesis is made available by the University of Alberta Libraries with permission of the copyright owner solely for non-commercial purposes. This thesis, or any portion thereof, may not otherwise be copied or reproduced without the written consent of the copyright owner, except to the extent permitted by Canadian copyright law."],"dc:subject":["Earned Value Management","Forecasting","EVA","Engineering Work","Project Controls","Baseline Development","Progress Measurement","Baseline Maintenance"],"dc:title":["Project Controls for Engineering Work in Practice"],"dc:type":["Thesis"],"others:access_status":["open.access"],"thesis:degree_discipline":["Construction Engineering and Management"],"thesis:degree_level":["Master's"],"thesis:degree_name":["Master of Science"],"thesis:institution_name":["University of Alberta"]},"updated_at":"2026-11-26T21:57:48Z"}