{"id":{"repo_id":"calgary","oai_identifier":"oai:ucalgary.scholaris.ca:11023/694"},"canonical_url":"https://search.ndltd.org/etd/calgary/oai:ucalgary.scholaris.ca:11023/694","repository":{"repo_id":"calgary","name":"University of Calgary","base_url":"https://ucalgary.scholaris.ca/server/oai/request"},"display":{"title":"Optimum Degree of Activity Accelerating and Overlapping in Schedule Compression","abstract":"Today's volatile economy encourages project owners to monitor their project schedules very closely, to ensure timely completion. The first incentive for such monitoring is escalation in commodity price and labour costs that may easily become more than the estimated amount. In addition, assumptions about the price and demand for the end-products are based on information available at the time of the initial estimates, which can be years prior to production. Any changes in these assumptions due to market fluctuations may render a project which was previously feasible financially unjustifiable after several years. On the other hand, when end-product prices are much higher than assumptions made during a feasibility study, organizations may be willing to finish projects earlier than planned to take advantage of higher profit margins even with the higher cost. For such reasons, a reliable mechanism for calculating time-cost trade-offs will considerably assist project managers in deciding on the level of schedule compression in projects, to consider reducing the duration with a reasonable cost increase. There are two main techniques by which schedule compression can be accomplished: activity accelerating, and overlapping. Activity accelerating is shortening project tasks' durations by incurring more cost. Overlapping is to perform the activities in parallel where in normal execution they would be completed in sequence. The amount of overlapping between two activities is expected to shorten duration, though due to the risks of changes and necessary rework, the duration saved would not be exactly the same as the length of the overlap. The purpose of this research is to review and analyze schedule compression techniques in detail, in order to develop an optimization algorithm as a tool for determining the optimum degree of accelerating and overlapping in schedule activities. The \"optimum degree\" is the point that offers the maximum benefit from schedule compression. For this purpose, data and information have been collected through extensive literature reviews, interviews, and focus groups. The findings are analyzed and formed the basis for developing an algorithm to optimize activity accelerating and overlapping in schedule activities. The algorithm developed, and the accompanying computer tool, have been tested and validated by several experiments showing their efficiency and effectiveness.","abstract_html":"Today&#x27;s volatile economy encourages project owners to monitor their project schedules very closely, to ensure timely completion. The first incentive for such monitoring is escalation in commodity price and labour costs that may easily become more than the estimated amount. In addition, assumptions about the price and demand for the end-products are based on information available at the time of the initial estimates, which can be years prior to production. Any changes in these assumptions due to market fluctuations may render a project which was previously feasible financially unjustifiable after several years. On the other hand, when end-product prices are much higher than assumptions made during a feasibility study, organizations may be willing to finish projects earlier than planned to take advantage of higher profit margins even with the higher cost. For such reasons, a reliable mechanism for calculating time-cost trade-offs will considerably assist project managers in deciding on the level of schedule compression in projects, to consider reducing the duration with a reasonable cost increase. There are two main techniques by which schedule compression can be accomplished: activity accelerating, and overlapping. Activity accelerating is shortening project tasks&#x27; durations by incurring more cost. Overlapping is to perform the activities in parallel where in normal execution they would be completed in sequence. The amount of overlapping between two activities is expected to shorten duration, though due to the risks of changes and necessary rework, the duration saved would not be exactly the same as the length of the overlap. The purpose of this research is to review and analyze schedule compression techniques in detail, in order to develop an optimization algorithm as a tool for determining the optimum degree of accelerating and overlapping in schedule activities. The &quot;optimum degree&quot; is the point that offers the maximum benefit from schedule compression. For this purpose, data and information have been collected through extensive literature reviews, interviews, and focus groups. The findings are analyzed and formed the basis for developing an algorithm to optimize activity accelerating and overlapping in schedule activities. The algorithm developed, and the accompanying computer tool, have been tested and validated by several experiments showing their efficiency and effectiveness.","abstract_has_math":false,"creators":["Hazini Bahram Abadi, Kamran"],"institution":"Graduate Studies","degree_name":"Doctor of Philosophy (PhD)","degree_level":null,"degree_discipline":"Civil Engineering","degree_department":null,"school":null,"contributors":[],"advisors":["Ruwanpura, Janaka"],"committee_chairs":[],"committee_members":[],"year":2013,"date_issued":"2013-05-01","date_published":"2013-05-01","updated_at":"2026-11-19T07:27:44Z","subjects":["Engineering--Industrial"],"languages":["eng"],"rights":["University of Calgary graduate students retain copyright ownership and moral rights for their thesis. You may use this material in any way that is permitted by the Copyright Act or through licensing that has been assigned to the document. For uses that are not allowable under copyright legislation or licensing, you are required to seek permission."],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["http://hdl.handle.net/11023/694"],"render_values":[{"text":"http://hdl.handle.net/11023/694","href":"https://hdl.handle.net/11023/694","code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://doi.org/10.11575/PRISM/27218","outbound_label":"DOI","outbound_source":"dc:identifier.doi","record_url":"https://doi.org/10.11575/PRISM/27218","record_label":"Repository record","record_kind":"doi","record_source":"dc:identifier.doi","access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"https://ucalgary.scholaris.ca/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Aucalgary.scholaris.ca%3A11023%2F694","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Ruwanpura, Janaka"]},{"key":"dc:creator","label":"Author","values":["Hazini Bahram Abadi, Kamran"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2013-05-01T20:32:19Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2013-06-10T07:00:47Z"]},{"key":"dc:date.issued","label":"Date","values":["2013-05-01"]},{"key":"dc:date.submitted","label":"Dc Date Submitted","values":["2013"]},{"key":"dc:publisher.faculty","label":"Dc Publisher Faculty","values":["Graduate Studies"]},{"key":"dc:publisher.institution","label":"Dc Publisher Institution","values":["University of Calgary"]},{"key":"dc:publisher.place","label":"Dc Publisher Place","values":["Calgary"]},{"key":"dc:type","label":"Dc Type","values":["doctoral thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Civil Engineering"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Doctor of Philosophy (PhD)"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["University of Calgary"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject","label":"Dc Subject","values":["Engineering--Industrial"]},{"key":"dc:subject.classification","label":"Dc Subject Classification","values":["Scheduling","Accelerating","Overlapping","Optimization","Time-Cost Trade-off"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language.iso","label":"Language (ISO)","values":["eng"]},{"key":"dc:rights","label":"Dc Rights","values":["University of Calgary graduate students retain copyright ownership and moral rights for their thesis. You may use this material in any way that is permitted by the Copyright Act or through licensing that has been assigned to the document. For uses that are not allowable under copyright legislation or licensing, you are required to seek permission."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.citation","label":"Dc Identifier Citation","values":["Hazini Bahram Abadi, K. (2013). Optimum Degree of Activity Accelerating and Overlapping in Schedule Compression (Doctoral thesis, University of Calgary, Calgary, Canada). Retrieved from https://prism.ucalgary.ca. doi:10.11575/PRISM/27218"]},{"key":"dc:identifier.doi","label":"DOI","values":["http://dx.doi.org/10.11575/PRISM/27218"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["http://hdl.handle.net/11023/694"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"atmire:migration.oldid","label":"Atmire Migration Oldid","values":["876"]},{"key":"dc:description.abstract","label":"Abstract","values":["Today's volatile economy encourages project owners to monitor their project schedules very closely, to ensure timely completion. The first incentive for such monitoring is escalation in commodity price and labour costs that may easily become more than the estimated amount. In addition, assumptions about the price and demand for the end-products are based on information available at the time of the initial estimates, which can be years prior to production. Any changes in these assumptions due to market fluctuations may render a project which was previously feasible financially unjustifiable after several years. On the other hand, when end-product prices are much higher than assumptions made during a feasibility study, organizations may be willing to finish projects earlier than planned to take advantage of higher profit margins even with the higher cost. For such reasons, a reliable mechanism for calculating time-cost trade-offs will considerably assist project managers in deciding on the level of schedule compression in projects, to consider reducing the duration with a reasonable cost increase. There are two main techniques by which schedule compression can be accomplished: activity accelerating, and overlapping. Activity accelerating is shortening project tasks' durations by incurring more cost. Overlapping is to perform the activities in parallel where in normal execution they would be completed in sequence. The amount of overlapping between two activities is expected to shorten duration, though due to the risks of changes and necessary rework, the duration saved would not be exactly the same as the length of the overlap. The purpose of this research is to review and analyze schedule compression techniques in detail, in order to develop an optimization algorithm as a tool for determining the optimum degree of accelerating and overlapping in schedule activities. The \"optimum degree\" is the point that offers the maximum benefit from schedule compression. For this purpose, data and information have been collected through extensive literature reviews, interviews, and focus groups. The findings are analyzed and formed the basis for developing an algorithm to optimize activity accelerating and overlapping in schedule activities. The algorithm developed, and the accompanying computer tool, have been tested and validated by several experiments showing their efficiency and effectiveness."]},{"key":"dc:title","label":"Title","values":["Optimum Degree of Activity Accelerating and Overlapping in Schedule Compression"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:request.copy","label":"Local Request Copy","values":["true"]},{"key":"others:access_status","label":"Others Access Status","values":["open.access"]}]}],"canonical_facts":{"atmire:migration.oldid":["876"],"dc:contributor.advisor":["Ruwanpura, Janaka"],"dc:creator":["Hazini Bahram Abadi, Kamran"],"dc:date.accessioned":["2013-05-01T20:32:19Z"],"dc:date.available":["2013-06-10T07:00:47Z"],"dc:date.issued":["2013-05-01"],"dc:date.submitted":["2013"],"dc:description.abstract":["Today's volatile economy encourages project owners to monitor their project schedules very closely, to ensure timely completion. The first incentive for such monitoring is escalation in commodity price and labour costs that may easily become more than the estimated amount. In addition, assumptions about the price and demand for the end-products are based on information available at the time of the initial estimates, which can be years prior to production. Any changes in these assumptions due to market fluctuations may render a project which was previously feasible financially unjustifiable after several years. On the other hand, when end-product prices are much higher than assumptions made during a feasibility study, organizations may be willing to finish projects earlier than planned to take advantage of higher profit margins even with the higher cost. For such reasons, a reliable mechanism for calculating time-cost trade-offs will considerably assist project managers in deciding on the level of schedule compression in projects, to consider reducing the duration with a reasonable cost increase. There are two main techniques by which schedule compression can be accomplished: activity accelerating, and overlapping. Activity accelerating is shortening project tasks' durations by incurring more cost. Overlapping is to perform the activities in parallel where in normal execution they would be completed in sequence. The amount of overlapping between two activities is expected to shorten duration, though due to the risks of changes and necessary rework, the duration saved would not be exactly the same as the length of the overlap. The purpose of this research is to review and analyze schedule compression techniques in detail, in order to develop an optimization algorithm as a tool for determining the optimum degree of accelerating and overlapping in schedule activities. The \"optimum degree\" is the point that offers the maximum benefit from schedule compression. For this purpose, data and information have been collected through extensive literature reviews, interviews, and focus groups. The findings are analyzed and formed the basis for developing an algorithm to optimize activity accelerating and overlapping in schedule activities. The algorithm developed, and the accompanying computer tool, have been tested and validated by several experiments showing their efficiency and effectiveness."],"dc:identifier.citation":["Hazini Bahram Abadi, K. (2013). Optimum Degree of Activity Accelerating and Overlapping in Schedule Compression (Doctoral thesis, University of Calgary, Calgary, Canada). Retrieved from https://prism.ucalgary.ca. doi:10.11575/PRISM/27218"],"dc:identifier.doi":["http://dx.doi.org/10.11575/PRISM/27218"],"dc:identifier.uri":["http://hdl.handle.net/11023/694"],"dc:language.iso":["eng"],"dc:publisher.faculty":["Graduate Studies"],"dc:publisher.institution":["University of Calgary"],"dc:publisher.place":["Calgary"],"dc:rights":["University of Calgary graduate students retain copyright ownership and moral rights for their thesis. You may use this material in any way that is permitted by the Copyright Act or through licensing that has been assigned to the document. For uses that are not allowable under copyright legislation or licensing, you are required to seek permission."],"dc:subject":["Engineering--Industrial"],"dc:subject.classification":["Scheduling","Accelerating","Overlapping","Optimization","Time-Cost Trade-off"],"dc:title":["Optimum Degree of Activity Accelerating and Overlapping in Schedule Compression"],"dc:type":["doctoral thesis"],"dspace:entity.type":["Publication"],"local:request.copy":["true"],"others:access_status":["open.access"],"thesis:degree_discipline":["Civil Engineering"],"thesis:degree_name":["Doctor of Philosophy (PhD)"],"thesis:institution_name":["University of Calgary"]},"updated_at":"2026-11-19T07:27:44Z"}