{"id":{"repo_id":"greece","oai_identifier":"oai:10442/8879"},"canonical_url":"https://search.ndltd.org/etd/greece/oai:10442/8879","repository":{"repo_id":"greece","name":"Greek National Archive of PhD Theses","base_url":"https://phdtheses.ekt.gr/eadd_oai/request"},"display":{"title":"TIME - LOCATION DIAGRAM SCHEDULING MODEL FOR LINEAR CONSTRUCTION PROJECTS","abstract":"THIS RESEARCH DEALS WITH THE PLANING, SCHEDULING AND CONTROLLING ALL KINDS OF LINEAR CONSTRUCTION PROJECTS. THESE ARE PROJECTS CHARACTERIZED BY; CONTINUES ACTIVITIES HAVE DIRECT CONNECTIONS OF DISTANCE AND TIME, AND PROJECTS WHICH HAVE LINEAR DISTANCES, START FROM ONE POINT DISTANCE, AND PROCEED UNTIL THE OTHER END DISTANCE OR PROJECT FINISH POINT. THESE LINEAR PROJECTS INCLUDE THE FOLLOWING: - HIGHWAY PROJECTS, TUNNEL PROJECTS, LONG BRIDGES PROJECTS, PIPELINE PROJECTS, AND RAILROAD CONSTRUCTION PROJECTS. THE RESEARCH INVESTIGATED SEVERAL ISSUES RELATED TO THE LINEAR CONSTRUCTION PROJECTS. IT POINTED OUT SOME FACTORS THAT AFFECT LINEAR CONSTRUCTION PROJECTS, WHILE IMPLEMENTING THE \"CONVENTIONAL\" METHODS. SOME OF THESE FACTORS ARE AS FOLLOWS: A.- THE EFFECT (INTERACTION) OF THE STATIONARY ACTIVITIES ON THE LINEAR ACTIVITIES. B.- THE LEAD OR THE LAG TIME SHOULD BE CONSIDERED DUE TO TECHNICAL REQUIREMENTS, RATHER THAN FRAGMENTATION REQUIREMENT TO GUARANTEE THE CONTINUITY OF THE ACTIVITIES. THIS WILL RESULT IN AN UNREASONABLE EXPANSION OF THE DURATION OF THE PROJECT. C.- THE ACTIVITY FRAGMENTATION REQUIREMENTS IN ORDER TO PLAN, AND TO SCHEDULE THE LINEAR CONSTRUCTION PROJECTS, WHERE IT DIVIDES THE PROJECT INTO STAGES OR PARTS, EACH STAGE BEING CONSIDERED AS A NEW ACTIVITY, WITH OCCASIONAL DIFFERENT PRODUCTION RATE IN THE ACTIVITY STAGES. THIS MAY RESULT IN DIFFERENT PRODUCTION RATES FOR SIMILAR ACTIVITIES AT DIFFERENT STAGES (ABSTRACT TRUNCATED)","abstract_html":"THIS RESEARCH DEALS WITH THE PLANING, SCHEDULING AND CONTROLLING ALL KINDS OF LINEAR CONSTRUCTION PROJECTS. THESE ARE PROJECTS CHARACTERIZED BY; CONTINUES ACTIVITIES HAVE DIRECT CONNECTIONS OF DISTANCE AND TIME, AND PROJECTS WHICH HAVE LINEAR DISTANCES, START FROM ONE POINT DISTANCE, AND PROCEED UNTIL THE OTHER END DISTANCE OR PROJECT FINISH POINT. THESE LINEAR PROJECTS INCLUDE THE FOLLOWING: - HIGHWAY PROJECTS, TUNNEL PROJECTS, LONG BRIDGES PROJECTS, PIPELINE PROJECTS, AND RAILROAD CONSTRUCTION PROJECTS. THE RESEARCH INVESTIGATED SEVERAL ISSUES RELATED TO THE LINEAR CONSTRUCTION PROJECTS. IT POINTED OUT SOME FACTORS THAT AFFECT LINEAR CONSTRUCTION PROJECTS, WHILE IMPLEMENTING THE &quot;CONVENTIONAL&quot; METHODS. SOME OF THESE FACTORS ARE AS FOLLOWS: A.- THE EFFECT (INTERACTION) OF THE STATIONARY ACTIVITIES ON THE LINEAR ACTIVITIES. B.- THE LEAD OR THE LAG TIME SHOULD BE CONSIDERED DUE TO TECHNICAL REQUIREMENTS, RATHER THAN FRAGMENTATION REQUIREMENT TO GUARANTEE THE CONTINUITY OF THE ACTIVITIES. THIS WILL RESULT IN AN UNREASONABLE EXPANSION OF THE DURATION OF THE PROJECT. C.- THE ACTIVITY FRAGMENTATION REQUIREMENTS IN ORDER TO PLAN, AND TO SCHEDULE THE LINEAR CONSTRUCTION PROJECTS, WHERE IT DIVIDES THE PROJECT INTO STAGES OR PARTS, EACH STAGE BEING CONSIDERED AS A NEW ACTIVITY, WITH OCCASIONAL DIFFERENT PRODUCTION RATE IN THE ACTIVITY STAGES. THIS MAY RESULT IN DIFFERENT PRODUCTION RATES FOR SIMILAR ACTIVITIES AT DIFFERENT STAGES (ABSTRACT TRUNCATED)","abstract_has_math":false,"creators":["El Okaili, Ziad"],"institution":"National Technical University of Athens (NTUA)","degree_name":null,"degree_level":null,"degree_discipline":null,"degree_department":null,"school":null,"contributors":[],"advisors":[],"committee_chairs":[],"committee_members":[],"year":1996,"date_issued":"1996","date_published":"1996","updated_at":"2026-11-18T20:26:33Z","subjects":["LINEAR CONSTRUCTION PROJECT","Software implementation","TIME - LOCATION DIAGRAM SCHEDULING MODEL","Ηλεκτρονικοί υπολογιστές","ΠΡΟΓΡΑΜΜΑΤΙΣΜΟΣ ΓΡΑΜΜΙΚΩΝ ΕΡΓΩΝ","ΣΤΟΧΑΣΤΙΚΗ ΘΕΩΡΗΣΗ","Επιστήμες Μηχανικού και Τεχνολογία","Επιστήμη Πολιτικού Μηχανικού","Engineering and Technology","Civil Engineering"],"languages":["eng"],"rights":[],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier","label":"Identifier","values":["10.12681/eadd/8879"],"render_values":[{"text":"10.12681/eadd/8879","href":"https://doi.org/10.12681/eadd/8879","code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"http://hdl.handle.net/10442/hedi/8879","outbound_label":"Handle","outbound_source":"dc:identifier","record_url":"http://hdl.handle.net/10442/hedi/8879","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier","download_url":null,"download_label":null,"download_source":null,"access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"https://phdtheses.ekt.gr/eadd_oai/request?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3A10442%2F8879","prefix":"oai_dc"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:creator","label":"Author","values":["El Okaili, Ziad"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["1996"]},{"key":"dc:publisher","label":"Institution","values":["National Technical University of Athens (NTUA)","Εθνικό Μετσόβιο Πολυτεχνείο (ΕΜΠ)"]},{"key":"dc:type","label":"Dc Type","values":["PhD Thesis"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject","label":"Dc Subject","values":["LINEAR CONSTRUCTION PROJECT","Software implementation","TIME - LOCATION DIAGRAM SCHEDULING MODEL","Ηλεκτρονικοί υπολογιστές","ΠΡΟΓΡΑΜΜΑΤΙΣΜΟΣ ΓΡΑΜΜΙΚΩΝ ΕΡΓΩΝ","ΣΤΟΧΑΣΤΙΚΗ ΘΕΩΡΗΣΗ","Επιστήμες Μηχανικού και Τεχνολογία","Επιστήμη Πολιτικού Μηχανικού","Engineering and Technology","Civil Engineering"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language","label":"Dc Language","values":["eng"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier","label":"Identifier","values":["10.12681/eadd/8879","http://hdl.handle.net/10442/hedi/8879"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description","label":"Description","values":["THIS RESEARCH DEALS WITH THE PLANING, SCHEDULING AND CONTROLLING ALL KINDS OF LINEAR CONSTRUCTION PROJECTS. THESE ARE PROJECTS CHARACTERIZED BY; CONTINUES ACTIVITIES HAVE DIRECT CONNECTIONS OF DISTANCE AND TIME, AND PROJECTS WHICH HAVE LINEAR DISTANCES, START FROM ONE POINT DISTANCE, AND PROCEED UNTIL THE OTHER END DISTANCE OR PROJECT FINISH POINT. THESE LINEAR PROJECTS INCLUDE THE FOLLOWING: - HIGHWAY PROJECTS, TUNNEL PROJECTS, LONG BRIDGES PROJECTS, PIPELINE PROJECTS, AND RAILROAD CONSTRUCTION PROJECTS. THE RESEARCH INVESTIGATED SEVERAL ISSUES RELATED TO THE LINEAR CONSTRUCTION PROJECTS. IT POINTED OUT SOME FACTORS THAT AFFECT LINEAR CONSTRUCTION PROJECTS, WHILE IMPLEMENTING THE \"CONVENTIONAL\" METHODS. SOME OF THESE FACTORS ARE AS FOLLOWS: A.- THE EFFECT (INTERACTION) OF THE STATIONARY ACTIVITIES ON THE LINEAR ACTIVITIES. B.- THE LEAD OR THE LAG TIME SHOULD BE CONSIDERED DUE TO TECHNICAL REQUIREMENTS, RATHER THAN FRAGMENTATION REQUIREMENT TO GUARANTEE THE CONTINUITY OF THE ACTIVITIES. THIS WILL RESULT IN AN UNREASONABLE EXPANSION OF THE DURATION OF THE PROJECT. C.- THE ACTIVITY FRAGMENTATION REQUIREMENTS IN ORDER TO PLAN, AND TO SCHEDULE THE LINEAR CONSTRUCTION PROJECTS, WHERE IT DIVIDES THE PROJECT INTO STAGES OR PARTS, EACH STAGE BEING CONSIDERED AS A NEW ACTIVITY, WITH OCCASIONAL DIFFERENT PRODUCTION RATE IN THE ACTIVITY STAGES. THIS MAY RESULT IN DIFFERENT PRODUCTION RATES FOR SIMILAR ACTIVITIES AT DIFFERENT STAGES (ABSTRACT TRUNCATED)","ΑΝΤΙΚΕΙΜΕΝΟ ΤΗΣ ΔΙΑΤΡΙΒΗΣ ΕΙΝΑΙ Η ΕΡΕΥΝΑ ΤΩΝ ΕΡΓΩΝ ΓΡΑΜΜΙΚΩΝ ΚΑΤΑΣΚΕΥΩΝ, ΟΠΩΣ Π.Χ. ΕΙΝΑΙ ΤΑ ΕΡΓΑ ΟΔΟΠΟΙΙΑΣ, ΔΙΩΡΥΓΩΝ, ΣΙΔΗΡΟΔΡΟΜΙΚΩΝ ΓΡΑΜΜΩΝ, ΣΗΡΑΓΓΩΝ, ΣΩΛΗΝΩΣΕΩΝ ΗΛΕΚΤΡΙΚΩΝ ΓΡΑΜΜΩΝ Κ.Λ.Π. ΣΤΑ ΕΡΓΑ ΑΥΤΑ ΟΙ ΔΡΑΣΤΗΡΙΟΤΗΤΕΣ ΕΙΝΑΙ ΣΥΝΕΧΕΙΣ ΚΑΙ ΕΠΑΝΑΛΑΜΒΑΝΟΜΕΝΕΣ ΚΑΙ ΧΑΡΑΚΤΗΡΙΖΟΝΤΑΙ ΑΠΟ ΜΙΑ ΓΡΑΜΜΙΚΗ ΣΥΝΑΡΤΗΣΗ ΑΠΟΣΤΑΣΕΩΣ - ΧΡΟΝΟΥ. Η ΜΕΘΟΔΟΣ ΑΥΤΗ ΕΙΝΑΙ ΜΙΑ ΕΝΑΛΛΑΚΤΙΚΗ ΜΕΘΟΔΟΣ ΧΡΟΝΙΚΟΥ ΠΡΟΓΡΑΜΜΑΤΙΣΜΟΥ ΓΡΑΜΜΙΚΩΝ ΕΡΓΩΝ, ΣΤΑ ΟΠΟΙΑ ΔΕΝ ΕΙΝΑΙ ΔΥΝΑΤΗ Η ΑΜΕΣΗ (ΧΩΡΙΣ ΔΙΑΣΠΑΣΗ ΔΡΑΣΤΗΡΙΟΤΗΤΩΝ Η ΠΡΟΣΘΕΣΗ ΠΛΑΣΜΑΤΙΚΩΝ) ΕΦΑΡΜΟΓΗ ΤΩΝ ΚΛΑΣΣΙΚΩΝ ΜΕΘΟΔΩΝ ΠΡΟΓΡΑΜΜΑΤΙΣΜΟΥ ΜΕ ΔΙΚΤΥΩΤΑ ΓΡΑΦΗΜΑΤΑ. Ο ΥΠΟΨΗΦΙΟΣ ΕΡΕΥΝΑ ΤΟ ΜΗΧΑΝΙΣΜΟ ΠΡΟΓΡΑΜΜΑΤΙΣΜΟΥΓΡΑΜΜΙΚΩΝ ΕΡΓΩΝ ΚΑΙ ΑΝΑΠΤΥΣΣΕΙ ΑΛΓΟΡΙΣΜΟ, Ο ΟΠΟΙΟΣ ΜΠΟΡΕΙ ΝΑ ΕΙΣΗΓΗΘΕΙ ΜΕ ΤΟ ΧΕΡΙ Η ΣΕ ΠΟΛΥΠΛΟΚΑ ΕΡΓΑ ΜΕ ΥΠΟΣΤΗΡΙΞΗ ΠΡΟΓΡΑΜΜΑΤΟΣ ΗΛΕΚΤΡΟΝΙΚΟΥ ΥΠΟΛΟΓΙΣΤΗ ΜΕ ΔΥΝΑΤΟΤΗΤΑ, ΕΤΣΙ ΛΟΓΩ ΤΗΣ ΤΑΧΥΤΗΤΑΣ ΤΟΥ ΠΡΟΓΡΑΜΜΑΤΟΣ, ΑΝΙΧΝΕΥΣΕΩΣ ΒΕΛΤΙΣΤΩΝΛΥΣΕΩΝ. ΤΟ ΠΡΟΓΡΑΜΜΑ ΕΚΠΟΝΗΘΗΚΕ ΑΠΟ ΤΟΝ ΥΠΟΨΗΦΙΟ ΚΑΙ ΑΠΟΤΕΛΕΙ ΜΕΡΟΣ ΤΗΣ ΔΙΔΑΚΤΟΡΙΚΗΣ ΔΙΑΤΡΙΒΗΣ."]},{"key":"dc:title","label":"Title","values":["TIME - LOCATION DIAGRAM SCHEDULING MODEL FOR LINEAR CONSTRUCTION PROJECTS","ΜΑΘΗΜΑΤΙΚΗ ΑΝΑΛΥΣΗ ΤΟΥ ΥΠΟΔΕΙΓΜΑΤΟΣ ΠΡΟΓΡΑΜΜΑΤΙΣΜΟΥ ΓΡΑΜΜΙΚΩΝ ΕΡΓΩΝ"]}]}],"canonical_facts":{"dc:creator":["El Okaili, Ziad"],"dc:date":["1996"],"dc:description":["THIS RESEARCH DEALS WITH THE PLANING, SCHEDULING AND CONTROLLING ALL KINDS OF LINEAR CONSTRUCTION PROJECTS. THESE ARE PROJECTS CHARACTERIZED BY; CONTINUES ACTIVITIES HAVE DIRECT CONNECTIONS OF DISTANCE AND TIME, AND PROJECTS WHICH HAVE LINEAR DISTANCES, START FROM ONE POINT DISTANCE, AND PROCEED UNTIL THE OTHER END DISTANCE OR PROJECT FINISH POINT. THESE LINEAR PROJECTS INCLUDE THE FOLLOWING: - HIGHWAY PROJECTS, TUNNEL PROJECTS, LONG BRIDGES PROJECTS, PIPELINE PROJECTS, AND RAILROAD CONSTRUCTION PROJECTS. THE RESEARCH INVESTIGATED SEVERAL ISSUES RELATED TO THE LINEAR CONSTRUCTION PROJECTS. IT POINTED OUT SOME FACTORS THAT AFFECT LINEAR CONSTRUCTION PROJECTS, WHILE IMPLEMENTING THE \"CONVENTIONAL\" METHODS. SOME OF THESE FACTORS ARE AS FOLLOWS: A.- THE EFFECT (INTERACTION) OF THE STATIONARY ACTIVITIES ON THE LINEAR ACTIVITIES. B.- THE LEAD OR THE LAG TIME SHOULD BE CONSIDERED DUE TO TECHNICAL REQUIREMENTS, RATHER THAN FRAGMENTATION REQUIREMENT TO GUARANTEE THE CONTINUITY OF THE ACTIVITIES. THIS WILL RESULT IN AN UNREASONABLE EXPANSION OF THE DURATION OF THE PROJECT. C.- THE ACTIVITY FRAGMENTATION REQUIREMENTS IN ORDER TO PLAN, AND TO SCHEDULE THE LINEAR CONSTRUCTION PROJECTS, WHERE IT DIVIDES THE PROJECT INTO STAGES OR PARTS, EACH STAGE BEING CONSIDERED AS A NEW ACTIVITY, WITH OCCASIONAL DIFFERENT PRODUCTION RATE IN THE ACTIVITY STAGES. THIS MAY RESULT IN DIFFERENT PRODUCTION RATES FOR SIMILAR ACTIVITIES AT DIFFERENT STAGES (ABSTRACT TRUNCATED)","ΑΝΤΙΚΕΙΜΕΝΟ ΤΗΣ ΔΙΑΤΡΙΒΗΣ ΕΙΝΑΙ Η ΕΡΕΥΝΑ ΤΩΝ ΕΡΓΩΝ ΓΡΑΜΜΙΚΩΝ ΚΑΤΑΣΚΕΥΩΝ, ΟΠΩΣ Π.Χ. ΕΙΝΑΙ ΤΑ ΕΡΓΑ ΟΔΟΠΟΙΙΑΣ, ΔΙΩΡΥΓΩΝ, ΣΙΔΗΡΟΔΡΟΜΙΚΩΝ ΓΡΑΜΜΩΝ, ΣΗΡΑΓΓΩΝ, ΣΩΛΗΝΩΣΕΩΝ ΗΛΕΚΤΡΙΚΩΝ ΓΡΑΜΜΩΝ Κ.Λ.Π. ΣΤΑ ΕΡΓΑ ΑΥΤΑ ΟΙ ΔΡΑΣΤΗΡΙΟΤΗΤΕΣ ΕΙΝΑΙ ΣΥΝΕΧΕΙΣ ΚΑΙ ΕΠΑΝΑΛΑΜΒΑΝΟΜΕΝΕΣ ΚΑΙ ΧΑΡΑΚΤΗΡΙΖΟΝΤΑΙ ΑΠΟ ΜΙΑ ΓΡΑΜΜΙΚΗ ΣΥΝΑΡΤΗΣΗ ΑΠΟΣΤΑΣΕΩΣ - ΧΡΟΝΟΥ. Η ΜΕΘΟΔΟΣ ΑΥΤΗ ΕΙΝΑΙ ΜΙΑ ΕΝΑΛΛΑΚΤΙΚΗ ΜΕΘΟΔΟΣ ΧΡΟΝΙΚΟΥ ΠΡΟΓΡΑΜΜΑΤΙΣΜΟΥ ΓΡΑΜΜΙΚΩΝ ΕΡΓΩΝ, ΣΤΑ ΟΠΟΙΑ ΔΕΝ ΕΙΝΑΙ ΔΥΝΑΤΗ Η ΑΜΕΣΗ (ΧΩΡΙΣ ΔΙΑΣΠΑΣΗ ΔΡΑΣΤΗΡΙΟΤΗΤΩΝ Η ΠΡΟΣΘΕΣΗ ΠΛΑΣΜΑΤΙΚΩΝ) ΕΦΑΡΜΟΓΗ ΤΩΝ ΚΛΑΣΣΙΚΩΝ ΜΕΘΟΔΩΝ ΠΡΟΓΡΑΜΜΑΤΙΣΜΟΥ ΜΕ ΔΙΚΤΥΩΤΑ ΓΡΑΦΗΜΑΤΑ. Ο ΥΠΟΨΗΦΙΟΣ ΕΡΕΥΝΑ ΤΟ ΜΗΧΑΝΙΣΜΟ ΠΡΟΓΡΑΜΜΑΤΙΣΜΟΥΓΡΑΜΜΙΚΩΝ ΕΡΓΩΝ ΚΑΙ ΑΝΑΠΤΥΣΣΕΙ ΑΛΓΟΡΙΣΜΟ, Ο ΟΠΟΙΟΣ ΜΠΟΡΕΙ ΝΑ ΕΙΣΗΓΗΘΕΙ ΜΕ ΤΟ ΧΕΡΙ Η ΣΕ ΠΟΛΥΠΛΟΚΑ ΕΡΓΑ ΜΕ ΥΠΟΣΤΗΡΙΞΗ ΠΡΟΓΡΑΜΜΑΤΟΣ ΗΛΕΚΤΡΟΝΙΚΟΥ ΥΠΟΛΟΓΙΣΤΗ ΜΕ ΔΥΝΑΤΟΤΗΤΑ, ΕΤΣΙ ΛΟΓΩ ΤΗΣ ΤΑΧΥΤΗΤΑΣ ΤΟΥ ΠΡΟΓΡΑΜΜΑΤΟΣ, ΑΝΙΧΝΕΥΣΕΩΣ ΒΕΛΤΙΣΤΩΝΛΥΣΕΩΝ. ΤΟ ΠΡΟΓΡΑΜΜΑ ΕΚΠΟΝΗΘΗΚΕ ΑΠΟ ΤΟΝ ΥΠΟΨΗΦΙΟ ΚΑΙ ΑΠΟΤΕΛΕΙ ΜΕΡΟΣ ΤΗΣ ΔΙΔΑΚΤΟΡΙΚΗΣ ΔΙΑΤΡΙΒΗΣ."],"dc:identifier":["10.12681/eadd/8879","http://hdl.handle.net/10442/hedi/8879"],"dc:language":["eng"],"dc:publisher":["National Technical University of Athens (NTUA)","Εθνικό Μετσόβιο Πολυτεχνείο (ΕΜΠ)"],"dc:subject":["LINEAR CONSTRUCTION PROJECT","Software implementation","TIME - LOCATION DIAGRAM SCHEDULING MODEL","Ηλεκτρονικοί υπολογιστές","ΠΡΟΓΡΑΜΜΑΤΙΣΜΟΣ ΓΡΑΜΜΙΚΩΝ ΕΡΓΩΝ","ΣΤΟΧΑΣΤΙΚΗ ΘΕΩΡΗΣΗ","Επιστήμες Μηχανικού και Τεχνολογία","Επιστήμη Πολιτικού Μηχανικού","Engineering and Technology","Civil Engineering"],"dc:title":["TIME - LOCATION DIAGRAM SCHEDULING MODEL FOR LINEAR CONSTRUCTION PROJECTS","ΜΑΘΗΜΑΤΙΚΗ ΑΝΑΛΥΣΗ ΤΟΥ ΥΠΟΔΕΙΓΜΑΤΟΣ ΠΡΟΓΡΑΜΜΑΤΙΣΜΟΥ ΓΡΑΜΜΙΚΩΝ ΕΡΓΩΝ"],"dc:type":["PhD Thesis"]},"updated_at":"2026-11-18T20:26:33Z"}