{"id":{"repo_id":"iastate","oai_identifier":"oai:dr.lib.iastate.edu:20.500.12876/26701"},"canonical_url":"https://search.ndltd.org/etd/iastate/oai:dr.lib.iastate.edu:20.500.12876/26701","repository":{"repo_id":"iastate","name":"Iowa State University","base_url":"https://dr.lib.iastate.edu/server/oai/request"},"display":{"title":"Evaluating the value of contractor involvement in the design phase","abstract":"<p>The use of alternative project delivery methods for transportation projects has grown in the in the U.S. out of a necessity to upgrade a rapidly deteriorating transportation infrastructure. As a result, contracting methods including design-build (DB), construction manager/general contractor (CMGC), early contractor involvement (ECI), public private partnership (P3), and alliancing have all been implemented in an effort to accelerate project schedules, manage risk and achieve enhanced project quality. The distinguishing feature of alternative project delivery methods is the ability to involve the construction contractor in the preconstruction phase of a project, providing input to the planning and design processes. Furthermore, the quality of a constructed project is a function of the quality of its design. Therefore, this research evaluates the value added to a project by involving the contractor in the preconstruction phase.</p> <p>Three research objectives are developed to address contractor added value. First, understand the factors that go into maximizing the benefit possible from cooperation during the design phase. Secondly, investigate the relationship between construction document quality, preconstruction costs, and early contractor involvement. Then finally, validate the major benefits of contractor preconstruction involvement given in literature.</p> <p>Research instruments including literature reviews, content analyses, case studies, and cost data analyses form the methodology for this thesis in order to evaluate data from 404 transportation projects, 44 case studies, and sufficient literature.</p> <p>This thesis finds that involving the contractor in the preconstruction phase increases cost certainty, produces cost and time savings, and inherently enhances project quality by contributing to the development of effective construction documents.</p>","abstract_html":"&lt;p&gt;The use of alternative project delivery methods for transportation projects has grown in the in the U.S. out of a necessity to upgrade a rapidly deteriorating transportation infrastructure. As a result, contracting methods including design-build (DB), construction manager/general contractor (CMGC), early contractor involvement (ECI), public private partnership (P3), and alliancing have all been implemented in an effort to accelerate project schedules, manage risk and achieve enhanced project quality. The distinguishing feature of alternative project delivery methods is the ability to involve the construction contractor in the preconstruction phase of a project, providing input to the planning and design processes. Furthermore, the quality of a constructed project is a function of the quality of its design. Therefore, this research evaluates the value added to a project by involving the contractor in the preconstruction phase.&lt;/p&gt; &lt;p&gt;Three research objectives are developed to address contractor added value. First, understand the factors that go into maximizing the benefit possible from cooperation during the design phase. Secondly, investigate the relationship between construction document quality, preconstruction costs, and early contractor involvement. Then finally, validate the major benefits of contractor preconstruction involvement given in literature.&lt;/p&gt; &lt;p&gt;Research instruments including literature reviews, content analyses, case studies, and cost data analyses form the methodology for this thesis in order to evaluate data from 404 transportation projects, 44 case studies, and sufficient literature.&lt;/p&gt; &lt;p&gt;This thesis finds that involving the contractor in the preconstruction phase increases cost certainty, produces cost and time savings, and inherently enhances project quality by contributing to the development of effective construction documents.&lt;/p&gt;","abstract_has_math":false,"creators":["West, Nicola"],"institution":null,"degree_name":"Master of Science","degree_level":"thesis","degree_discipline":null,"degree_department":"Department of Civil, Construction and Environmental Engineering","school":null,"contributors":[],"advisors":["Douglas D Gransberg"],"committee_chairs":[],"committee_members":[],"year":2012,"date_issued":"2012-01-01","date_published":"2012-01-01","updated_at":"2026-11-19T04:32:52Z","subjects":[],"languages":["en"],"rights":[],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://dr.lib.iastate.edu/handle/20.500.12876/26701"],"render_values":[{"text":"https://dr.lib.iastate.edu/handle/20.500.12876/26701","href":"https://dr.lib.iastate.edu/handle/20.500.12876/26701","code":true}]},{"key":"dc:identifier","label":"Identifier","values":["archive/lib.dr.iastate.edu/etd/12512/"],"render_values":[{"text":"archive/lib.dr.iastate.edu/etd/12512/","href":null,"code":true}]},{"key":"dc:identifier.other","label":"Dc Identifier Other","values":["3519","3437881"],"render_values":[{"text":"3519","href":null,"code":true},{"text":"3437881","href":null,"code":true}]},{"key":"mods:identifier.filename","label":"Mods Identifier Filename","values":["archive/lib.dr.iastate.edu/etd/12512/West_iastate_0097M_12639.pdf|||Fri Jan 14 19:23:37 UTC 2022"],"render_values":[{"text":"archive/lib.dr.iastate.edu/etd/12512/West_iastate_0097M_12639.pdf|||Fri Jan 14 19:23:37 UTC 2022","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://doi.org/10.31274/etd-180810-982","outbound_label":"DOI","outbound_source":"dc:identifier.doi","record_url":"https://doi.org/10.31274/etd-180810-982","record_label":"Repository record","record_kind":"doi","record_source":"dc:identifier.doi","access_status":"embargoed","embargo_until":"2013-06-05","access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Aiastate%3Aoai%3Adr.lib.iastate.edu%3A20.500.12876%2F26701","prefix":"oai_dc"},"source_record":{"url":"https://dr.lib.iastate.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Adr.lib.iastate.edu%3A20.500.12876%2F26701","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Douglas D Gransberg"]},{"key":"dc:contributor.department","label":"Department","values":["Department of Civil, Construction and Environmental Engineering"]},{"key":"dc:creator","label":"Author","values":["West, Nicola"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["2018-08-11T18:14:20.000"]},{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2020-06-30T02:43:12Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2020-06-30T02:43:12Z"]},{"key":"dc:date.copyright","label":"Dc Date Copyright","values":["Sun Jan 01 00:00:00 UTC 2012"]},{"key":"dc:date.embargo","label":"Dc Date Embargo","values":["2013-06-05"]},{"key":"dc:date.issued","label":"Date","values":["2012-01-01"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["933e9c94-323c-4da9-9e8e-861692825f91"]},{"key":"dc:type","label":"Dc Type","values":["thesis"]},{"key":"thesis:degree_level","label":"Degree Level","values":["thesis"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.discipline","label":"Dc Subject Discipline","values":["Civil Engineering"]},{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["Alternative project delivery methods","Construction manager/general contractor","Design-bid-build","Design-build","Design fee","Preconstruction"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language.iso","label":"Language (ISO)","values":["en"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier","label":"Identifier","values":["archive/lib.dr.iastate.edu/etd/12512/"]},{"key":"dc:identifier.doi","label":"DOI","values":["https://doi.org/10.31274/etd-180810-982"]},{"key":"dc:identifier.other","label":"Dc Identifier Other","values":["3519","3437881"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://dr.lib.iastate.edu/handle/20.500.12876/26701"]},{"key":"mods:identifier.filename","label":"Mods Identifier Filename","values":["archive/lib.dr.iastate.edu/etd/12512/West_iastate_0097M_12639.pdf|||Fri Jan 14 19:23:37 UTC 2022"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["<p>The use of alternative project delivery methods for transportation projects has grown in the in the U.S. out of a necessity to upgrade a rapidly deteriorating transportation infrastructure. As a result, contracting methods including design-build (DB), construction manager/general contractor (CMGC), early contractor involvement (ECI), public private partnership (P3), and alliancing have all been implemented in an effort to accelerate project schedules, manage risk and achieve enhanced project quality. The distinguishing feature of alternative project delivery methods is the ability to involve the construction contractor in the preconstruction phase of a project, providing input to the planning and design processes. Furthermore, the quality of a constructed project is a function of the quality of its design. Therefore, this research evaluates the value added to a project by involving the contractor in the preconstruction phase.</p> <p>Three research objectives are developed to address contractor added value. First, understand the factors that go into maximizing the benefit possible from cooperation during the design phase. Secondly, investigate the relationship between construction document quality, preconstruction costs, and early contractor involvement. Then finally, validate the major benefits of contractor preconstruction involvement given in literature.</p> <p>Research instruments including literature reviews, content analyses, case studies, and cost data analyses form the methodology for this thesis in order to evaluate data from 404 transportation projects, 44 case studies, and sufficient literature.</p> <p>This thesis finds that involving the contractor in the preconstruction phase increases cost certainty, produces cost and time savings, and inherently enhances project quality by contributing to the development of effective construction documents.</p>"]},{"key":"dc:format.mimetype","label":"Dc Format Mimetype","values":["application/pdf"]},{"key":"dc:title","label":"Title","values":["Evaluating the value of contractor involvement in the design phase"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:admin","label":"Local Admin","values":["isulib-bepress-aws-west","etd/12512"]}]}],"canonical_facts":{"dc:contributor.advisor":["Douglas D Gransberg"],"dc:contributor.department":["Department of Civil, Construction and Environmental Engineering"],"dc:creator":["West, Nicola"],"dc:date":["2018-08-11T18:14:20.000"],"dc:date.accessioned":["2020-06-30T02:43:12Z"],"dc:date.available":["2020-06-30T02:43:12Z"],"dc:date.copyright":["Sun Jan 01 00:00:00 UTC 2012"],"dc:date.embargo":["2013-06-05"],"dc:date.issued":["2012-01-01"],"dc:description.abstract":["<p>The use of alternative project delivery methods for transportation projects has grown in the in the U.S. out of a necessity to upgrade a rapidly deteriorating transportation infrastructure. As a result, contracting methods including design-build (DB), construction manager/general contractor (CMGC), early contractor involvement (ECI), public private partnership (P3), and alliancing have all been implemented in an effort to accelerate project schedules, manage risk and achieve enhanced project quality. The distinguishing feature of alternative project delivery methods is the ability to involve the construction contractor in the preconstruction phase of a project, providing input to the planning and design processes. Furthermore, the quality of a constructed project is a function of the quality of its design. Therefore, this research evaluates the value added to a project by involving the contractor in the preconstruction phase.</p> <p>Three research objectives are developed to address contractor added value. First, understand the factors that go into maximizing the benefit possible from cooperation during the design phase. Secondly, investigate the relationship between construction document quality, preconstruction costs, and early contractor involvement. Then finally, validate the major benefits of contractor preconstruction involvement given in literature.</p> <p>Research instruments including literature reviews, content analyses, case studies, and cost data analyses form the methodology for this thesis in order to evaluate data from 404 transportation projects, 44 case studies, and sufficient literature.</p> <p>This thesis finds that involving the contractor in the preconstruction phase increases cost certainty, produces cost and time savings, and inherently enhances project quality by contributing to the development of effective construction documents.</p>"],"dc:format.mimetype":["application/pdf"],"dc:identifier":["archive/lib.dr.iastate.edu/etd/12512/"],"dc:identifier.doi":["https://doi.org/10.31274/etd-180810-982"],"dc:identifier.other":["3519","3437881"],"dc:identifier.uri":["https://dr.lib.iastate.edu/handle/20.500.12876/26701"],"dc:language.iso":["en"],"dc:relation.orgunit":["933e9c94-323c-4da9-9e8e-861692825f91"],"dc:subject.discipline":["Civil Engineering"],"dc:subject.keyword":["Alternative project delivery methods","Construction manager/general contractor","Design-bid-build","Design-build","Design fee","Preconstruction"],"dc:title":["Evaluating the value of contractor involvement in the design phase"],"dc:type":["thesis"],"dspace:entity.type":["Publication"],"local:admin":["isulib-bepress-aws-west","etd/12512"],"mods:identifier.filename":["archive/lib.dr.iastate.edu/etd/12512/West_iastate_0097M_12639.pdf|||Fri Jan 14 19:23:37 UTC 2022"],"thesis:degree_level":["thesis"],"thesis:degree_name":["Master of Science"]},"updated_at":"2026-11-19T04:32:52Z"}