{"id":{"repo_id":"iastate","oai_identifier":"oai:dr.lib.iastate.edu:20.500.12876/64271"},"canonical_url":"https://search.ndltd.org/etd/iastate/oai:dr.lib.iastate.edu:20.500.12876/64271","repository":{"repo_id":"iastate","name":"Iowa State University","base_url":"https://dr.lib.iastate.edu/server/oai/request"},"display":{"title":"Linear scheduling model: the development of a linear scheduling model with micro computer applications for highway construction project control","abstract":"<p>This thesis describes a new approach to the problem of scheduling highway construction type projects. The technique can accurately model linear activities and identify the controlling activity path on a linear schedule. Current scheduling practices, are unable to accomplish these two tasks with any accuracy for linear activities, leaving planners and managers suspicious of the information they provide. Basic linear scheduling is not a new technique, and many attempts have been made to apply it to various types of work in the past. The technique has never been widely used however, because of the lack of an analytical approach to activity relationships and development of an analytical approach to determining controlling activities. The Linear Scheduling Model (LSM) developed in this thesis, completes the linear scheduling technique by adding to linear scheduling, all of the analytical capabilities, including computer applications, present in CPM scheduling today. The Linear Scheduling Model has tremendous potential and will likely have a significant impact on the way linear construction is scheduled in the future.</p>","abstract_html":"&lt;p&gt;This thesis describes a new approach to the problem of scheduling highway construction type projects. The technique can accurately model linear activities and identify the controlling activity path on a linear schedule. Current scheduling practices, are unable to accomplish these two tasks with any accuracy for linear activities, leaving planners and managers suspicious of the information they provide. Basic linear scheduling is not a new technique, and many attempts have been made to apply it to various types of work in the past. The technique has never been widely used however, because of the lack of an analytical approach to activity relationships and development of an analytical approach to determining controlling activities. The Linear Scheduling Model (LSM) developed in this thesis, completes the linear scheduling technique by adding to linear scheduling, all of the analytical capabilities, including computer applications, present in CPM scheduling today. The Linear Scheduling Model has tremendous potential and will likely have a significant impact on the way linear construction is scheduled in the future.&lt;/p&gt;","abstract_has_math":false,"creators":["Harmelink, David"],"institution":null,"degree_name":"Doctor of Philosophy","degree_level":"dissertation","degree_discipline":null,"degree_department":"Department of Civil, Construction and Environmental Engineering","school":null,"contributors":[],"advisors":["James E. Rowings"],"committee_chairs":[],"committee_members":[],"year":1995,"date_issued":"1995","date_published":"1995","updated_at":"2026-11-19T04:37:40Z","subjects":[],"languages":["en"],"rights":[],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://dr.lib.iastate.edu/handle/20.500.12876/64271"],"render_values":[{"text":"https://dr.lib.iastate.edu/handle/20.500.12876/64271","href":"https://dr.lib.iastate.edu/handle/20.500.12876/64271","code":true}]},{"key":"dc:identifier","label":"Identifier","values":["archive/lib.dr.iastate.edu/rtd/11056/"],"render_values":[{"text":"archive/lib.dr.iastate.edu/rtd/11056/","href":null,"code":true}]},{"key":"dc:identifier.other","label":"Dc Identifier Other","values":["12055","6430609"],"render_values":[{"text":"12055","href":null,"code":true},{"text":"6430609","href":null,"code":true}]},{"key":"mods:identifier.filename","label":"Mods Identifier Filename","values":["archive/lib.dr.iastate.edu/rtd/11056/r_9610957.pdf|||Fri Jan 14 18:41:17 UTC 2022"],"render_values":[{"text":"archive/lib.dr.iastate.edu/rtd/11056/r_9610957.pdf|||Fri Jan 14 18:41:17 UTC 2022","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://doi.org/10.31274/rtd-180813-10183","outbound_label":"DOI","outbound_source":"dc:identifier.doi","record_url":"https://doi.org/10.31274/rtd-180813-10183","record_label":"Repository record","record_kind":"doi","record_source":"dc:identifier.doi","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Aiastate%3Aoai%3Adr.lib.iastate.edu%3A20.500.12876%2F64271","prefix":"oai_dc"},"source_record":{"url":"https://dr.lib.iastate.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Adr.lib.iastate.edu%3A20.500.12876%2F64271","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["James E. Rowings"]},{"key":"dc:contributor.department","label":"Department","values":["Department of Civil, Construction and Environmental Engineering"]},{"key":"dc:creator","label":"Author","values":["Harmelink, David"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["2018-08-23T08:09:24.000"]},{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2020-06-30T07:09:49Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2020-06-30T07:09:49Z"]},{"key":"dc:date.copyright","label":"Dc Date Copyright","values":["Sun Jan 01 00:00:00 UTC 1995"]},{"key":"dc:date.issued","label":"Date","values":["1995"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["933e9c94-323c-4da9-9e8e-861692825f91"]},{"key":"dc:type","label":"Dc Type","values":["dissertation"]},{"key":"thesis:degree_level","label":"Degree Level","values":["dissertation"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Doctor of Philosophy"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.discipline","label":"Dc Subject Discipline","values":["Civil Engineering","Transportation"]},{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["Civil and construction engineering","Civil engineering (Construction engineering and management)","Construction engineering and management"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language.iso","label":"Language (ISO)","values":["en"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier","label":"Identifier","values":["archive/lib.dr.iastate.edu/rtd/11056/"]},{"key":"dc:identifier.doi","label":"DOI","values":["https://doi.org/10.31274/rtd-180813-10183"]},{"key":"dc:identifier.other","label":"Dc Identifier Other","values":["12055","6430609"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://dr.lib.iastate.edu/handle/20.500.12876/64271"]},{"key":"mods:identifier.filename","label":"Mods Identifier Filename","values":["archive/lib.dr.iastate.edu/rtd/11056/r_9610957.pdf|||Fri Jan 14 18:41:17 UTC 2022"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["<p>This thesis describes a new approach to the problem of scheduling highway construction type projects. The technique can accurately model linear activities and identify the controlling activity path on a linear schedule. Current scheduling practices, are unable to accomplish these two tasks with any accuracy for linear activities, leaving planners and managers suspicious of the information they provide. Basic linear scheduling is not a new technique, and many attempts have been made to apply it to various types of work in the past. The technique has never been widely used however, because of the lack of an analytical approach to activity relationships and development of an analytical approach to determining controlling activities. The Linear Scheduling Model (LSM) developed in this thesis, completes the linear scheduling technique by adding to linear scheduling, all of the analytical capabilities, including computer applications, present in CPM scheduling today. The Linear Scheduling Model has tremendous potential and will likely have a significant impact on the way linear construction is scheduled in the future.</p>"]},{"key":"dc:format.mimetype","label":"Dc Format Mimetype","values":["application/pdf"]},{"key":"dc:title","label":"Title","values":["Linear scheduling model: the development of a linear scheduling model with micro computer applications for highway construction project control"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:admin","label":"Local Admin","values":["isulib-bepress-aws-west","rtd/11056"]}]}],"canonical_facts":{"dc:contributor.advisor":["James E. Rowings"],"dc:contributor.department":["Department of Civil, Construction and Environmental Engineering"],"dc:creator":["Harmelink, David"],"dc:date":["2018-08-23T08:09:24.000"],"dc:date.accessioned":["2020-06-30T07:09:49Z"],"dc:date.available":["2020-06-30T07:09:49Z"],"dc:date.copyright":["Sun Jan 01 00:00:00 UTC 1995"],"dc:date.issued":["1995"],"dc:description.abstract":["<p>This thesis describes a new approach to the problem of scheduling highway construction type projects. The technique can accurately model linear activities and identify the controlling activity path on a linear schedule. Current scheduling practices, are unable to accomplish these two tasks with any accuracy for linear activities, leaving planners and managers suspicious of the information they provide. Basic linear scheduling is not a new technique, and many attempts have been made to apply it to various types of work in the past. The technique has never been widely used however, because of the lack of an analytical approach to activity relationships and development of an analytical approach to determining controlling activities. The Linear Scheduling Model (LSM) developed in this thesis, completes the linear scheduling technique by adding to linear scheduling, all of the analytical capabilities, including computer applications, present in CPM scheduling today. The Linear Scheduling Model has tremendous potential and will likely have a significant impact on the way linear construction is scheduled in the future.</p>"],"dc:format.mimetype":["application/pdf"],"dc:identifier":["archive/lib.dr.iastate.edu/rtd/11056/"],"dc:identifier.doi":["https://doi.org/10.31274/rtd-180813-10183"],"dc:identifier.other":["12055","6430609"],"dc:identifier.uri":["https://dr.lib.iastate.edu/handle/20.500.12876/64271"],"dc:language.iso":["en"],"dc:relation.orgunit":["933e9c94-323c-4da9-9e8e-861692825f91"],"dc:subject.discipline":["Civil Engineering","Transportation"],"dc:subject.keyword":["Civil and construction engineering","Civil engineering (Construction engineering and management)","Construction engineering and management"],"dc:title":["Linear scheduling model: the development of a linear scheduling model with micro computer applications for highway construction project control"],"dc:type":["dissertation"],"dspace:entity.type":["Publication"],"local:admin":["isulib-bepress-aws-west","rtd/11056"],"mods:identifier.filename":["archive/lib.dr.iastate.edu/rtd/11056/r_9610957.pdf|||Fri Jan 14 18:41:17 UTC 2022"],"thesis:degree_level":["dissertation"],"thesis:degree_name":["Doctor of Philosophy"]},"updated_at":"2026-11-19T04:37:40Z"}