{"id":{"repo_id":"ndsu","oai_identifier":"oai:library.ndsu.edu:10365/26538"},"canonical_url":"https://search.ndltd.org/etd/ndsu/oai:library.ndsu.edu:10365/26538","repository":{"repo_id":"ndsu","name":"North Dakota State University","base_url":"https://library.ndsu.edu/server/oai/request"},"display":{"title":"Project Time and Cost Control Using Building Information Modeling","abstract":"Although the construction industry has been evolving for centuries and researchers have been seeking innovative solutions for decades, diverse challenges still exist in making the construction process faster, safer, cheaper and more accurate. It is believed that Building Information Modeling (BIM) can lead to greater efficiency through the incremental collaboration. The data in BIM system is extremely useful and can be generated to optimize the project delivery processes. However, since BIM increases the project design cost and requires a big learning curve, project participants are concerned about the cost of project, which has hindered the adoption of BIM for the project delivery. This paper, using a case study, describes how BIM functions to help cut down costs, optimize schedule, and benefit the project participants. The analysis of project cost and time control focuses on life cycle. The recommendations for the future use of BIM are made generally.","abstract_html":"Although the construction industry has been evolving for centuries and researchers have been seeking innovative solutions for decades, diverse challenges still exist in making the construction process faster, safer, cheaper and more accurate. It is believed that Building Information Modeling (BIM) can lead to greater efficiency through the incremental collaboration. The data in BIM system is extremely useful and can be generated to optimize the project delivery processes. However, since BIM increases the project design cost and requires a big learning curve, project participants are concerned about the cost of project, which has hindered the adoption of BIM for the project delivery. This paper, using a case study, describes how BIM functions to help cut down costs, optimize schedule, and benefit the project participants. The analysis of project cost and time control focuses on life cycle. The recommendations for the future use of BIM are made generally.","abstract_has_math":false,"creators":["Zhang, Dalu"],"institution":"North Dakota State University","degree_name":null,"degree_level":null,"degree_discipline":null,"degree_department":null,"school":null,"contributors":[],"advisors":[],"committee_chairs":[],"committee_members":[],"year":2013,"date_issued":"2013","date_published":"2013","updated_at":"2026-11-19T13:51:44Z","subjects":["Building information modeling","Project management","Scheduling"],"languages":[],"rights":["NDSU Policy 190.6.2"],"rights_urls":["https://www.ndsu.edu/fileadmin/policy/190.pdf"],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10365/26538","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10365/26538","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","download_url":null,"download_label":null,"download_source":null,"access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"https://library.ndsu.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Alibrary.ndsu.edu%3A10365%2F26538","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:creator","label":"Author","values":["Zhang, Dalu"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2017-10-06T21:33:25Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2017-10-06T21:33:25Z"]},{"key":"dc:date.issued","label":"Date","values":["2013"]},{"key":"dc:publisher","label":"Institution","values":["North Dakota State University"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.lcsh","label":"Dc Subject Lcsh","values":["Building information modeling","Project management","Scheduling"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["NDSU Policy 190.6.2"]},{"key":"dc:rights.uri","label":"Rights URI","values":["https://www.ndsu.edu/fileadmin/policy/190.pdf"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10365/26538"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["Although the construction industry has been evolving for centuries and researchers have been seeking innovative solutions for decades, diverse challenges still exist in making the construction process faster, safer, cheaper and more accurate. It is believed that Building Information Modeling (BIM) can lead to greater efficiency through the incremental collaboration. The data in BIM system is extremely useful and can be generated to optimize the project delivery processes. However, since BIM increases the project design cost and requires a big learning curve, project participants are concerned about the cost of project, which has hindered the adoption of BIM for the project delivery. This paper, using a case study, describes how BIM functions to help cut down costs, optimize schedule, and benefit the project participants. The analysis of project cost and time control focuses on life cycle. The recommendations for the future use of BIM are made generally."]},{"key":"dc:title","label":"Title","values":["Project Time and Cost Control Using Building Information Modeling"]}]}],"canonical_facts":{"dc:creator":["Zhang, Dalu"],"dc:date.accessioned":["2017-10-06T21:33:25Z"],"dc:date.available":["2017-10-06T21:33:25Z"],"dc:date.issued":["2013"],"dc:description.abstract":["Although the construction industry has been evolving for centuries and researchers have been seeking innovative solutions for decades, diverse challenges still exist in making the construction process faster, safer, cheaper and more accurate. It is believed that Building Information Modeling (BIM) can lead to greater efficiency through the incremental collaboration. The data in BIM system is extremely useful and can be generated to optimize the project delivery processes. However, since BIM increases the project design cost and requires a big learning curve, project participants are concerned about the cost of project, which has hindered the adoption of BIM for the project delivery. This paper, using a case study, describes how BIM functions to help cut down costs, optimize schedule, and benefit the project participants. The analysis of project cost and time control focuses on life cycle. The recommendations for the future use of BIM are made generally."],"dc:identifier.uri":["https://hdl.handle.net/10365/26538"],"dc:publisher":["North Dakota State University"],"dc:rights":["NDSU Policy 190.6.2"],"dc:rights.uri":["https://www.ndsu.edu/fileadmin/policy/190.pdf"],"dc:subject.lcsh":["Building information modeling","Project management","Scheduling"],"dc:title":["Project Time and Cost Control Using Building Information Modeling"],"dc:type":["Thesis"]},"updated_at":"2026-11-19T13:51:44Z"}