{"id":{"repo_id":"njit","oai_identifier":"oai:digitalcommons.njit.edu:theses-4126"},"canonical_url":"https://search.ndltd.org/etd/njit/oai:digitalcommons.njit.edu:theses-4126","repository":{"repo_id":"njit","name":"NJIT","base_url":"https://digitalcommons.njit.edu/do/oai/"},"display":{"title":"Determination of project duration for resource constrained projects without using resource scheduling procedure","abstract":"<p>The problem addressed in this thesis is that of determining the practicability of equating measures of network and resource characteristics to the early finish date of a project which is constrained by resources. The output of standard critical path calculations along with information on resource profiles that are easy to calculate can be of use in estimating resource constrained project duration.</p><p>Twenty two different equations ( developed by Hall) were used to find the estimated project finish dates. These results were compared to the schedule resulting from the application of the heuristic rule of minimum activity float. It is shown that the calculations may be used as a substitute to resource leveling procedure.</p>","abstract_html":"&lt;p&gt;The problem addressed in this thesis is that of determining the practicability of equating measures of network and resource characteristics to the early finish date of a project which is constrained by resources. The output of standard critical path calculations along with information on resource profiles that are easy to calculate can be of use in estimating resource constrained project duration.&lt;/p&gt;&lt;p&gt;Twenty two different equations ( developed by Hall) were used to find the estimated project finish dates. These results were compared to the schedule resulting from the application of the heuristic rule of minimum activity float. It is shown that the calculations may be used as a substitute to resource leveling procedure.&lt;/p&gt;","abstract_has_math":false,"creators":["Karmakar, Rabindra Nath"],"institution":null,"degree_name":"Master of Science in Civil Engineering - (M.S.)","degree_level":null,"degree_discipline":"Civil and Environmental Engineering","degree_department":null,"school":null,"contributors":["Edward G. Dauenheimer","Walter Konon","John R. Schuring"],"advisors":[],"committee_chairs":[],"committee_members":[],"year":null,"date_issued":"","date_published":null,"updated_at":"2026-11-19T08:43:09Z","subjects":["Industrial project management","Scheduling (Management)","Civil Engineering"],"languages":[],"rights":[],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://digitalcommons.njit.edu/theses/3112","outbound_label":"Repository record","outbound_source":"dc:identifier","record_url":"https://digitalcommons.njit.edu/theses/3112","record_label":"Repository record","record_kind":"record","record_source":"dc:identifier","download_url":null,"download_label":null,"download_source":null,"access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"https://digitalcommons.njit.edu/do/oai/?verb=GetRecord&metadataPrefix=oai_etdms&identifier=oai%3Adigitalcommons.njit.edu%3Atheses-4126","prefix":"oai_etdms"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor","label":"Contributor","values":["Edward G. Dauenheimer","Walter Konon","John R. Schuring"]},{"key":"dc:creator","label":"Author","values":["Karmakar, Rabindra Nath"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.created","label":"Dc Date Created","values":["1988-05-31T07:00:00Z"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Civil and Environmental Engineering"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science in Civil Engineering - (M.S.)"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject","label":"Dc Subject","values":["Industrial project management","Scheduling (Management)","Civil Engineering"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier","label":"Identifier","values":["https://digitalcommons.njit.edu/theses/3112"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["<p>The problem addressed in this thesis is that of determining the practicability of equating measures of network and resource characteristics to the early finish date of a project which is constrained by resources. The output of standard critical path calculations along with information on resource profiles that are easy to calculate can be of use in estimating resource constrained project duration.</p><p>Twenty two different equations ( developed by Hall) were used to find the estimated project finish dates. These results were compared to the schedule resulting from the application of the heuristic rule of minimum activity float. It is shown that the calculations may be used as a substitute to resource leveling procedure.</p>"]},{"key":"dc:title","label":"Title","values":["Determination of project duration for resource constrained projects without using resource scheduling procedure"]}]}],"canonical_facts":{"dc:contributor":["Edward G. Dauenheimer","Walter Konon","John R. Schuring"],"dc:creator":["Karmakar, Rabindra Nath"],"dc:date.created":["1988-05-31T07:00:00Z"],"dc:description.abstract":["<p>The problem addressed in this thesis is that of determining the practicability of equating measures of network and resource characteristics to the early finish date of a project which is constrained by resources. The output of standard critical path calculations along with information on resource profiles that are easy to calculate can be of use in estimating resource constrained project duration.</p><p>Twenty two different equations ( developed by Hall) were used to find the estimated project finish dates. These results were compared to the schedule resulting from the application of the heuristic rule of minimum activity float. It is shown that the calculations may be used as a substitute to resource leveling procedure.</p>"],"dc:identifier":["https://digitalcommons.njit.edu/theses/3112"],"dc:subject":["Industrial project management","Scheduling (Management)","Civil Engineering"],"dc:title":["Determination of project duration for resource constrained projects without using resource scheduling procedure"],"dc:type":["Thesis"],"thesis:degree_discipline":["Civil and Environmental Engineering"],"thesis:degree_name":["Master of Science in Civil Engineering - (M.S.)"]},"updated_at":"2026-11-19T08:43:09Z"}