{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/1253"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/1253","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Analysis of deferred work for San Diego Based DDGS","abstract":"The Continuous Maintenance Program is designed to maintain ships at the highest level of material condition while keeping the ships at the optimum operational readiness. In this thesis the deferred maintenance records of seven DDG's were examined during the period FY 1999 to 2000 to determine if trends existed in the types of work being deferred. First, the deferred data were grouped into categories using the System Work List Item Number from data collected in the Maintenance Support Tool. Second, compilations of the grouped data (estimated total mandays and total costs) were divided into FYs 99 and 00. Third, trends were established and then compared to FY 99 and 00 to determine consistencies. The results showed that over 60% of deferred jobs and estimated total mandays occurred in the categories of hull structure (decks), auxiliary equipment (air conditioning) and outfit/furnishing (habitability). Nearly 50% of the estimated total costs, however, occurred within the hull structure and ship support services (shipyard services) categories. Trends were also established to determine the Port Engineer's accuracy in job estimates. In FY 00, estimated deferred data were compared to FY 00 actual deferred data. The results concluded that the Port Engineers overestimated total mandays by 9% and total costs by 10%. A determination of the effectiveness of the Continuous Maintenance Program could not be reached due to the classification required to make the analysis.","abstract_html":"The Continuous Maintenance Program is designed to maintain ships at the highest level of material condition while keeping the ships at the optimum operational readiness. In this thesis the deferred maintenance records of seven DDG&#x27;s were examined during the period FY 1999 to 2000 to determine if trends existed in the types of work being deferred. First, the deferred data were grouped into categories using the System Work List Item Number from data collected in the Maintenance Support Tool. Second, compilations of the grouped data (estimated total mandays and total costs) were divided into FYs 99 and 00. Third, trends were established and then compared to FY 99 and 00 to determine consistencies. The results showed that over 60% of deferred jobs and estimated total mandays occurred in the categories of hull structure (decks), auxiliary equipment (air conditioning) and outfit/furnishing (habitability). Nearly 50% of the estimated total costs, however, occurred within the hull structure and ship support services (shipyard services) categories. Trends were also established to determine the Port Engineer&#x27;s accuracy in job estimates. In FY 00, estimated deferred data were compared to FY 00 actual deferred data. The results concluded that the Port Engineers overestimated total mandays by 9% and total costs by 10%. A determination of the effectiveness of the Continuous Maintenance Program could not be reached due to the classification required to make the analysis.","abstract_has_math":false,"creators":["Koprowski, Neil A."],"institution":"Monterey, California. Naval Postgraduate School","degree_name":"M.S.","degree_level":"Masters","degree_discipline":"Electrical Engineering","degree_department":"Electrical Engineering","school":null,"contributors":[],"advisors":["McCaffery, Jerry","Mutty, John"],"committee_chairs":[],"committee_members":[],"year":2001,"date_issued":"2001-06","date_published":"2001-06","updated_at":"2026-11-19T06:03:38Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States."],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier.oclc","label":"OCLC","values":["266405"],"render_values":[{"text":"266405","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/1253","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/1253","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F1253","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F1253","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["McCaffery, Jerry","Mutty, John"]},{"key":"dc:contributor.department","label":"Department","values":["Electrical Engineering"]},{"key":"dc:creator","label":"Author","values":["Koprowski, Neil A."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-03-14T17:31:04Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-03-14T17:31:04Z"]},{"key":"dc:date.issued","label":"Date","values":["2001-06"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, California. Naval Postgraduate School"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Electrical Engineering"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["M.S.","Master of Sciences"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.oclc","label":"OCLC","values":["266405"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/1253"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["The Continuous Maintenance Program is designed to maintain ships at the highest level of material condition while keeping the ships at the optimum operational readiness. In this thesis the deferred maintenance records of seven DDG's were examined during the period FY 1999 to 2000 to determine if trends existed in the types of work being deferred. First, the deferred data were grouped into categories using the System Work List Item Number from data collected in the Maintenance Support Tool. Second, compilations of the grouped data (estimated total mandays and total costs) were divided into FYs 99 and 00. Third, trends were established and then compared to FY 99 and 00 to determine consistencies. The results showed that over 60% of deferred jobs and estimated total mandays occurred in the categories of hull structure (decks), auxiliary equipment (air conditioning) and outfit/furnishing (habitability). Nearly 50% of the estimated total costs, however, occurred within the hull structure and ship support services (shipyard services) categories. Trends were also established to determine the Port Engineer's accuracy in job estimates. In FY 00, estimated deferred data were compared to FY 00 actual deferred data. The results concluded that the Port Engineers overestimated total mandays by 9% and total costs by 10%. A determination of the effectiveness of the Continuous Maintenance Program could not be reached due to the classification required to make the analysis."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/analysisofdeferr109451253"]},{"key":"dc:format.extent","label":"Dc Format Extent","values":["xii, 59 p. ;"]},{"key":"dc:title","label":"Title","values":["Analysis of deferred work for San Diego Based DDGS"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:etd.verified","label":"Local Etd Verified","values":["no"]}]}],"canonical_facts":{"dc:contributor.advisor":["McCaffery, Jerry","Mutty, John"],"dc:contributor.department":["Electrical Engineering"],"dc:creator":["Koprowski, Neil A."],"dc:date.accessioned":["2012-03-14T17:31:04Z"],"dc:date.available":["2012-03-14T17:31:04Z"],"dc:date.issued":["2001-06"],"dc:description.abstract":["The Continuous Maintenance Program is designed to maintain ships at the highest level of material condition while keeping the ships at the optimum operational readiness. In this thesis the deferred maintenance records of seven DDG's were examined during the period FY 1999 to 2000 to determine if trends existed in the types of work being deferred. First, the deferred data were grouped into categories using the System Work List Item Number from data collected in the Maintenance Support Tool. Second, compilations of the grouped data (estimated total mandays and total costs) were divided into FYs 99 and 00. Third, trends were established and then compared to FY 99 and 00 to determine consistencies. The results showed that over 60% of deferred jobs and estimated total mandays occurred in the categories of hull structure (decks), auxiliary equipment (air conditioning) and outfit/furnishing (habitability). Nearly 50% of the estimated total costs, however, occurred within the hull structure and ship support services (shipyard services) categories. Trends were also established to determine the Port Engineer's accuracy in job estimates. In FY 00, estimated deferred data were compared to FY 00 actual deferred data. The results concluded that the Port Engineers overestimated total mandays by 9% and total costs by 10%. A determination of the effectiveness of the Continuous Maintenance Program could not be reached due to the classification required to make the analysis."],"dc:description.uri":["http://archive.org/details/analysisofdeferr109451253"],"dc:format.extent":["xii, 59 p. ;"],"dc:identifier.oclc":["266405"],"dc:identifier.uri":["https://hdl.handle.net/10945/1253"],"dc:publisher":["Monterey, California. Naval Postgraduate School"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States."],"dc:title":["Analysis of deferred work for San Diego Based DDGS"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:etd.verified":["no"],"thesis:degree_discipline":["Electrical Engineering"],"thesis:degree_level":["Masters"],"thesis:degree_name":["M.S.","Master of Sciences"],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-19T06:03:38Z"}