{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/1415"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/1415","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"The impact of long-term aircraft carrier maintenance scheduling on the Fleet Readiness Plan","abstract":"Maintaining the Fleet Readiness Plan (FRP) construct of six aircraft carriers available within 30 days, plus two additional carriers available within 90 days is a difficult task. Maintenance requirements on carriers alone make satisfying the FRP a challenging scheduling problem. We develop a carrier maintenance scheduling model with a goal to meet, as best as possible, the FRP requirements over a ten-year period, while obeying simple maintenance facility constraints. This model allows us to anticipate gaps in coverage and also quantitatively assess the benefit, or burden, of re-sizing the fleet. We conclude that by increasing the average cycle time for a Carrier Strike Group (CSG) to 27 months we can meet the FRP requirements continuously after an initial maintenance adjustment period of 62 months.","abstract_html":"Maintaining the Fleet Readiness Plan (FRP) construct of six aircraft carriers available within 30 days, plus two additional carriers available within 90 days is a difficult task. Maintenance requirements on carriers alone make satisfying the FRP a challenging scheduling problem. We develop a carrier maintenance scheduling model with a goal to meet, as best as possible, the FRP requirements over a ten-year period, while obeying simple maintenance facility constraints. This model allows us to anticipate gaps in coverage and also quantitatively assess the benefit, or burden, of re-sizing the fleet. We conclude that by increasing the average cycle time for a Carrier Strike Group (CSG) to 27 months we can meet the FRP requirements continuously after an initial maintenance adjustment period of 62 months.","abstract_has_math":false,"creators":["Hall, Matthew H."],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"M.S. in Operations Research","degree_level":"Masters","degree_discipline":"Operations Research","degree_department":"Operations Research (OR)","school":null,"contributors":[],"advisors":["Carlyle, W. Matthew"],"committee_chairs":[],"committee_members":["Kline, Jeffrey E."],"year":2004,"date_issued":"2004-09","date_published":"2004-09","updated_at":"2026-11-26T00:10:31Z","subjects":["Aircraft carriers","United States","Operational readiness"],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/1415","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/1415","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F1415","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F1415","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Carlyle, W. Matthew"]},{"key":"dc:contributor.committeemember","label":"Committee Member","values":["Kline, Jeffrey E."]},{"key":"dc:contributor.department","label":"Department","values":["Operations Research (OR)"]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Naval Postgraduate School (U.S.)"]},{"key":"dc:creator","label":"Author","values":["Hall, Matthew H."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-03-14T17:31:43Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-03-14T17:31:43Z"]},{"key":"dc:date.issued","label":"Date","values":["2004-09"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["58745961-c46a-45ad-ae9c-d139d1ba1041"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Operations Research"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["M.S. in Operations Research"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.lcsh","label":"Dc Subject Lcsh","values":["Aircraft carriers","United States","Operational readiness"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/1415"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["Maintaining the Fleet Readiness Plan (FRP) construct of six aircraft carriers available within 30 days, plus two additional carriers available within 90 days is a difficult task. Maintenance requirements on carriers alone make satisfying the FRP a challenging scheduling problem. We develop a carrier maintenance scheduling model with a goal to meet, as best as possible, the FRP requirements over a ten-year period, while obeying simple maintenance facility constraints. This model allows us to anticipate gaps in coverage and also quantitatively assess the benefit, or burden, of re-sizing the fleet. We conclude that by increasing the average cycle time for a Carrier Strike Group (CSG) to 27 months we can meet the FRP requirements continuously after an initial maintenance adjustment period of 62 months."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/theimpactoflongt109451415"]},{"key":"dc:format.extent","label":"Dc Format Extent","values":["xvi, 69 p. : ill. (some col.), col. maps ;"]},{"key":"dc:title","label":"Title","values":["The impact of long-term aircraft carrier maintenance scheduling on the Fleet Readiness Plan"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Lieutenant, United States Navy"]},{"key":"local:etd.verified","label":"Local Etd Verified","values":["no"]}]}],"canonical_facts":{"dc:contributor.advisor":["Carlyle, W. Matthew"],"dc:contributor.committeemember":["Kline, Jeffrey E."],"dc:contributor.department":["Operations Research (OR)"],"dc:contributor.other":["Naval Postgraduate School (U.S.)"],"dc:creator":["Hall, Matthew H."],"dc:date.accessioned":["2012-03-14T17:31:43Z"],"dc:date.available":["2012-03-14T17:31:43Z"],"dc:date.issued":["2004-09"],"dc:description.abstract":["Maintaining the Fleet Readiness Plan (FRP) construct of six aircraft carriers available within 30 days, plus two additional carriers available within 90 days is a difficult task. Maintenance requirements on carriers alone make satisfying the FRP a challenging scheduling problem. We develop a carrier maintenance scheduling model with a goal to meet, as best as possible, the FRP requirements over a ten-year period, while obeying simple maintenance facility constraints. This model allows us to anticipate gaps in coverage and also quantitatively assess the benefit, or burden, of re-sizing the fleet. We conclude that by increasing the average cycle time for a Carrier Strike Group (CSG) to 27 months we can meet the FRP requirements continuously after an initial maintenance adjustment period of 62 months."],"dc:description.uri":["http://archive.org/details/theimpactoflongt109451415"],"dc:format.extent":["xvi, 69 p. : ill. (some col.), col. maps ;"],"dc:identifier.uri":["https://hdl.handle.net/10945/1415"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:relation.orgunit":["58745961-c46a-45ad-ae9c-d139d1ba1041"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"dc:subject.lcsh":["Aircraft carriers","United States","Operational readiness"],"dc:title":["The impact of long-term aircraft carrier maintenance scheduling on the Fleet Readiness Plan"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Lieutenant, United States Navy"],"local:etd.verified":["no"],"thesis:degree_discipline":["Operations Research"],"thesis:degree_level":["Masters"],"thesis:degree_name":["M.S. in Operations Research"],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-26T00:10:31Z"}