{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/17329"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/17329","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"A Comparison of Earned Value and Earned Schedule Duration Forecast Methods on Department of Defense Major Defense Acquisition Programs","abstract":"Earned value management is a project management tool that integrates project scope with cost, schedule, and performance elements for optimum project planning and control. Earned value management is required by the Department of Defense for cost and incentive type contracts equal or greater than $20 million as part of a comprehensive approach to improving critical acquisitions. It is used to forecast the programs schedule performance using cost-based indicators but not time-based indicators. Earned value management has been used since the early 1960s as a program management tool, but is viewed by some professionals as incomplete when predicting schedule performance values. An extension of earned value management, called earned schedule, was introduced in 2003 as a tool to more accurately estimate schedule performance using time indicators that is lacking in traditional earned value management estimates. Earned schedule uses standard earned value management performance indicator values and time-based equations to depict the schedule performance. This research project measured the accuracy of earned value and earned schedule final duration forecast methods by analyzing four U.S. Army Chemical Materials Agency programs.","abstract_html":"Earned value management is a project management tool that integrates project scope with cost, schedule, and performance elements for optimum project planning and control. Earned value management is required by the Department of Defense for cost and incentive type contracts equal or greater than $20 million as part of a comprehensive approach to improving critical acquisitions. It is used to forecast the programs schedule performance using cost-based indicators but not time-based indicators. Earned value management has been used since the early 1960s as a program management tool, but is viewed by some professionals as incomplete when predicting schedule performance values. An extension of earned value management, called earned schedule, was introduced in 2003 as a tool to more accurately estimate schedule performance using time indicators that is lacking in traditional earned value management estimates. Earned schedule uses standard earned value management performance indicator values and time-based equations to depict the schedule performance. This research project measured the accuracy of earned value and earned schedule final duration forecast methods by analyzing four U.S. Army Chemical Materials Agency programs.","abstract_has_math":false,"creators":["Bruchey, William J."],"institution":"Monterey, California. Naval Postgraduate School","degree_name":"Master of Program Management","degree_level":"Masters","degree_discipline":"Program Management","degree_department":"Program Management","school":null,"contributors":[],"advisors":["Pickar, Charles","Fast, William"],"committee_chairs":[],"committee_members":[],"year":2012,"date_issued":"2012-09","date_published":"2012-09","updated_at":"2026-11-19T06:06:58Z","subjects":[],"languages":[],"rights":["Approved for public release; distribution is unlimited."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/17329","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/17329","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F17329","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F17329","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Pickar, Charles","Fast, William"]},{"key":"dc:contributor.department","label":"Department","values":["Program Management"]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Human Systems Integration (HSI) Certificate Program"]},{"key":"dc:creator","label":"Author","values":["Bruchey, William J."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["Sep-12"]},{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-11-14T00:02:16Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-11-14T00:02:16Z"]},{"key":"dc:date.issued","label":"Date","values":["2012-09"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, California. Naval Postgraduate School"]},{"key":"dc:relation.ispartofseries","label":"Dc Relation Ispartofseries","values":["Joint Applied Projects"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["b1db68f8-fa8c-4d10-b118-8166cdacdb4c"]},{"key":"dc:relation.seriesentity","label":"Dc Relation Seriesentity","values":["5e5d89a9-08b3-46c1-9247-fc96704340b4"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Program Management"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Program Management"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["Earned Value","Earned Schedule","Schedule Performance","Final Duration Forecast"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["Approved for public release; distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/17329"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["Earned value management is a project management tool that integrates project scope with cost, schedule, and performance elements for optimum project planning and control. Earned value management is required by the Department of Defense for cost and incentive type contracts equal or greater than $20 million as part of a comprehensive approach to improving critical acquisitions. It is used to forecast the programs schedule performance using cost-based indicators but not time-based indicators. Earned value management has been used since the early 1960s as a program management tool, but is viewed by some professionals as incomplete when predicting schedule performance values. An extension of earned value management, called earned schedule, was introduced in 2003 as a tool to more accurately estimate schedule performance using time indicators that is lacking in traditional earned value management estimates. Earned schedule uses standard earned value management performance indicator values and time-based equations to depict the schedule performance. This research project measured the accuracy of earned value and earned schedule final duration forecast methods by analyzing four U.S. Army Chemical Materials Agency programs."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/acomparisonofear1094517329"]},{"key":"dc:title","label":"Title","values":["A Comparison of Earned Value and Earned Schedule Duration Forecast Methods on Department of Defense Major Defense Acquisition Programs"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Civilian, United States Army"]}]}],"canonical_facts":{"dc:contributor.advisor":["Pickar, Charles","Fast, William"],"dc:contributor.department":["Program Management"],"dc:contributor.other":["Human Systems Integration (HSI) Certificate Program"],"dc:creator":["Bruchey, William J."],"dc:date":["Sep-12"],"dc:date.accessioned":["2012-11-14T00:02:16Z"],"dc:date.available":["2012-11-14T00:02:16Z"],"dc:date.issued":["2012-09"],"dc:description.abstract":["Earned value management is a project management tool that integrates project scope with cost, schedule, and performance elements for optimum project planning and control. Earned value management is required by the Department of Defense for cost and incentive type contracts equal or greater than $20 million as part of a comprehensive approach to improving critical acquisitions. It is used to forecast the programs schedule performance using cost-based indicators but not time-based indicators. Earned value management has been used since the early 1960s as a program management tool, but is viewed by some professionals as incomplete when predicting schedule performance values. An extension of earned value management, called earned schedule, was introduced in 2003 as a tool to more accurately estimate schedule performance using time indicators that is lacking in traditional earned value management estimates. Earned schedule uses standard earned value management performance indicator values and time-based equations to depict the schedule performance. This research project measured the accuracy of earned value and earned schedule final duration forecast methods by analyzing four U.S. Army Chemical Materials Agency programs."],"dc:description.uri":["http://archive.org/details/acomparisonofear1094517329"],"dc:identifier.uri":["https://hdl.handle.net/10945/17329"],"dc:publisher":["Monterey, California. Naval Postgraduate School"],"dc:relation.ispartofseries":["Joint Applied Projects"],"dc:relation.orgunit":["b1db68f8-fa8c-4d10-b118-8166cdacdb4c"],"dc:relation.seriesentity":["5e5d89a9-08b3-46c1-9247-fc96704340b4"],"dc:rights":["Approved for public release; distribution is unlimited."],"dc:subject.keyword":["Earned Value","Earned Schedule","Schedule Performance","Final Duration Forecast"],"dc:title":["A Comparison of Earned Value and Earned Schedule Duration Forecast Methods on Department of Defense Major Defense Acquisition Programs"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Civilian, United States Army"],"thesis:degree_discipline":["Program Management"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Master of Program Management"]},"updated_at":"2026-11-19T06:06:58Z"}