{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/17935"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/17935","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Schedule adherence in a naval shipyard : a case study","abstract":"In this research, the author documents the process of production management employed in a naval shipyard in seeking adherence to schedules during the non-nuclear portion of the overhaul of nuclear submarines. In addition to recording the process details for those who may learn from them in the future, the -author also demonstrates some of the problems confronting managers in all naval shipyards. The author first profiles the history, mission, and organization of the activity chosen for the research, Mare Island Naval Shipyard, then develops the process constraints of estimated cost, schedule, personnel resources, and authorized work packages for an individual ship. The discussion then shifts to a detailed description of the management aids used to monitor and assess overhaul progress and of the techniques employed, using these aids, to seek schedule adherence on several ships simultaneously. The research concludes with a summary of the total process and suggestions for further research.","abstract_html":"In this research, the author documents the process of production management employed in a naval shipyard in seeking adherence to schedules during the non-nuclear portion of the overhaul of nuclear submarines. In addition to recording the process details for those who may learn from them in the future, the -author also demonstrates some of the problems confronting managers in all naval shipyards. The author first profiles the history, mission, and organization of the activity chosen for the research, Mare Island Naval Shipyard, then develops the process constraints of estimated cost, schedule, personnel resources, and authorized work packages for an individual ship. The discussion then shifts to a detailed description of the management aids used to monitor and assess overhaul progress and of the techniques employed, using these aids, to seek schedule adherence on several ships simultaneously. The research concludes with a summary of the total process and suggestions for further research.","abstract_has_math":false,"creators":["Eckstein, Eric Rockhill"],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"M.S. in Management","degree_level":"Masters","degree_discipline":"Management","degree_department":"Department of Administrative Sciences","school":null,"contributors":[],"advisors":["McMasters, A.W."],"committee_chairs":[],"committee_members":["Eckstein, E.R."],"year":1976,"date_issued":"1976","date_published":"1976","updated_at":"2026-11-26T00:17:57Z","subjects":["Management"],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/17935","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/17935","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F17935","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F17935","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["McMasters, A.W."]},{"key":"dc:contributor.committeemember","label":"Committee Member","values":["Eckstein, E.R."]},{"key":"dc:contributor.department","label":"Department","values":["Department of Administrative Sciences"]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Naval Postgraduate School (U.S.)"]},{"key":"dc:creator","label":"Author","values":["Eckstein, Eric Rockhill"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["September 1976"]},{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-11-16T18:48:54Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-11-16T18:48:54Z"]},{"key":"dc:date.issued","label":"Date","values":["1976"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Management"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["M.S. in Management"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["Shipyard Management control","Shipyard Production conditions","Shipyard scheduling","Schedule Maintenance"]},{"key":"dc:subject.lcsh","label":"Dc Subject Lcsh","values":["Management"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/17935"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["In this research, the author documents the process of production management employed in a naval shipyard in seeking adherence to schedules during the non-nuclear portion of the overhaul of nuclear submarines. In addition to recording the process details for those who may learn from them in the future, the -author also demonstrates some of the problems confronting managers in all naval shipyards. The author first profiles the history, mission, and organization of the activity chosen for the research, Mare Island Naval Shipyard, then develops the process constraints of estimated cost, schedule, personnel resources, and authorized work packages for an individual ship. The discussion then shifts to a detailed description of the management aids used to monitor and assess overhaul progress and of the techniques employed, using these aids, to seek schedule adherence on several ships simultaneously. The research concludes with a summary of the total process and suggestions for further research."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/scheduledherence1094517935"]},{"key":"dc:title","label":"Title","values":["Schedule adherence in a naval shipyard : a case study"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Lieutenant Commander, United States Navy"]}]}],"canonical_facts":{"dc:contributor.advisor":["McMasters, A.W."],"dc:contributor.committeemember":["Eckstein, E.R."],"dc:contributor.department":["Department of Administrative Sciences"],"dc:contributor.other":["Naval Postgraduate School (U.S.)"],"dc:creator":["Eckstein, Eric Rockhill"],"dc:date":["September 1976"],"dc:date.accessioned":["2012-11-16T18:48:54Z"],"dc:date.available":["2012-11-16T18:48:54Z"],"dc:date.issued":["1976"],"dc:description.abstract":["In this research, the author documents the process of production management employed in a naval shipyard in seeking adherence to schedules during the non-nuclear portion of the overhaul of nuclear submarines. In addition to recording the process details for those who may learn from them in the future, the -author also demonstrates some of the problems confronting managers in all naval shipyards. The author first profiles the history, mission, and organization of the activity chosen for the research, Mare Island Naval Shipyard, then develops the process constraints of estimated cost, schedule, personnel resources, and authorized work packages for an individual ship. The discussion then shifts to a detailed description of the management aids used to monitor and assess overhaul progress and of the techniques employed, using these aids, to seek schedule adherence on several ships simultaneously. The research concludes with a summary of the total process and suggestions for further research."],"dc:description.uri":["http://archive.org/details/scheduledherence1094517935"],"dc:identifier.uri":["https://hdl.handle.net/10945/17935"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"dc:subject.keyword":["Shipyard Management control","Shipyard Production conditions","Shipyard scheduling","Schedule Maintenance"],"dc:subject.lcsh":["Management"],"dc:title":["Schedule adherence in a naval shipyard : a case study"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Lieutenant Commander, United States Navy"],"thesis:degree_discipline":["Management"],"thesis:degree_level":["Masters"],"thesis:degree_name":["M.S. in Management"],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-26T00:17:57Z"}