{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/23491"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/23491","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"An analysis of the use of Linear Scheduling Techniques in the construction industry.","abstract":"A construction scheduling technique is presented which is, in many cases, more advantageous, to both the contractor & the owner, than bar charts typically provided by contractors, particularly for projects that are linear in nature or have repetitive activities scheduled in phases (e.g. roads, piping systems, bridge spans, and high rise buildings). The technique is labeled the linear scheduling method because it is most useful in the construction industry for projects that are linear in nature. The technique maps planned or actual works along the length, or stations, of a project versus time. The basic application of this method is described. Examples of practical application are provided, including a comparative analysis based on an actual Florida Department of Transportation construction project. The technique is compared to the more prevalent bar chart technique utilized in such software applications as Primavera Project Planner","abstract_html":"A construction scheduling technique is presented which is, in many cases, more advantageous, to both the contractor &amp; the owner, than bar charts typically provided by contractors, particularly for projects that are linear in nature or have repetitive activities scheduled in phases (e.g. roads, piping systems, bridge spans, and high rise buildings). The technique is labeled the linear scheduling method because it is most useful in the construction industry for projects that are linear in nature. The technique maps planned or actual works along the length, or stations, of a project versus time. The basic application of this method is described. Examples of practical application are provided, including a comparative analysis based on an actual Florida Department of Transportation construction project. The technique is compared to the more prevalent bar chart technique utilized in such software applications as Primavera Project Planner","abstract_has_math":false,"creators":["Sims, Steven L."],"institution":"University of Florida","degree_name":"Masters of Engineering","degree_level":"Masters","degree_discipline":"Engineering","degree_department":null,"school":null,"contributors":[],"advisors":[],"committee_chairs":[],"committee_members":[],"year":1998,"date_issued":"1998","date_published":"1998","updated_at":"2026-11-19T06:24:59Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States."],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier.oclc","label":"OCLC","values":["ocn640504037"],"render_values":[{"text":"ocn640504037","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/23491","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/23491","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F23491","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F23491","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["CIVINS (Civilian Institutions)"]},{"key":"dc:creator","label":"Author","values":["Sims, Steven L."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-11-29T16:12:24Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-11-29T16:12:24Z"]},{"key":"dc:date.issued","label":"Date","values":["1998"]},{"key":"dc:publisher","label":"Institution","values":["University of Florida"]},{"key":"dc:relation.ispartofseries","label":"Dc Relation Ispartofseries","values":["CIVINS (Civilian Institutions) Theses and Dissertations"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["c6eb8929-c883-4d31-84f5-166ce3ae8c52"]},{"key":"dc:relation.seriesentity","label":"Dc Relation Seriesentity","values":["0855bc76-cf0d-4c5f-84ba-3b1c54b01904"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Engineering"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Masters of Engineering"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["University of Florida"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.oclc","label":"OCLC","values":["ocn640504037"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/23491"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description","label":"Description","values":["CIVINS (Civilian Institutions) Thesis document"]},{"key":"dc:description.abstract","label":"Abstract","values":["A construction scheduling technique is presented which is, in many cases, more advantageous, to both the contractor & the owner, than bar charts typically provided by contractors, particularly for projects that are linear in nature or have repetitive activities scheduled in phases (e.g. roads, piping systems, bridge spans, and high rise buildings). The technique is labeled the linear scheduling method because it is most useful in the construction industry for projects that are linear in nature. The technique maps planned or actual works along the length, or stations, of a project versus time. The basic application of this method is described. Examples of practical application are provided, including a comparative analysis based on an actual Florida Department of Transportation construction project. The technique is compared to the more prevalent bar chart technique utilized in such software applications as Primavera Project Planner"]},{"key":"dc:description.sponsorship","label":"Dc Description Sponsorship","values":["CIVINS"]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/annalysisofuseof1094523491"]},{"key":"dc:format.extent","label":"Dc Format Extent","values":["iv, 1 v. (various leaves);28 cm."]},{"key":"dc:title","label":"Title","values":["An analysis of the use of Linear Scheduling Techniques in the construction industry."]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]}]}],"canonical_facts":{"dc:contributor.other":["CIVINS (Civilian Institutions)"],"dc:creator":["Sims, Steven L."],"dc:date.accessioned":["2012-11-29T16:12:24Z"],"dc:date.available":["2012-11-29T16:12:24Z"],"dc:date.issued":["1998"],"dc:description":["CIVINS (Civilian Institutions) Thesis document"],"dc:description.abstract":["A construction scheduling technique is presented which is, in many cases, more advantageous, to both the contractor & the owner, than bar charts typically provided by contractors, particularly for projects that are linear in nature or have repetitive activities scheduled in phases (e.g. roads, piping systems, bridge spans, and high rise buildings). The technique is labeled the linear scheduling method because it is most useful in the construction industry for projects that are linear in nature. The technique maps planned or actual works along the length, or stations, of a project versus time. The basic application of this method is described. Examples of practical application are provided, including a comparative analysis based on an actual Florida Department of Transportation construction project. The technique is compared to the more prevalent bar chart technique utilized in such software applications as Primavera Project Planner"],"dc:description.sponsorship":["CIVINS"],"dc:description.uri":["http://archive.org/details/annalysisofuseof1094523491"],"dc:format.extent":["iv, 1 v. (various leaves);28 cm."],"dc:identifier.oclc":["ocn640504037"],"dc:identifier.uri":["https://hdl.handle.net/10945/23491"],"dc:publisher":["University of Florida"],"dc:relation.ispartofseries":["CIVINS (Civilian Institutions) Theses and Dissertations"],"dc:relation.orgunit":["c6eb8929-c883-4d31-84f5-166ce3ae8c52"],"dc:relation.seriesentity":["0855bc76-cf0d-4c5f-84ba-3b1c54b01904"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States."],"dc:title":["An analysis of the use of Linear Scheduling Techniques in the construction industry."],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"thesis:degree_discipline":["Engineering"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Masters of Engineering"],"thesis:institution_name":["University of Florida"]},"updated_at":"2026-11-19T06:24:59Z"}