{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/26075"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/26075","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Minimizing and analyzing construction delay and its impacts: case studies and knowledge-based systems.","abstract":"This report will examine the fundamental principles associated with construction delay and recovering from the delay through actual acceleration. Methods for minimizing or eliminating construction delay and analyzing its impact on cost, quality, and timely completion of construction projects will be presented. A prototype expert system will be developed to assist the public and private owner in minimizing the possibility of construction delay. Additionally, two methods of schedule compression will be examined. A case study of the acceleration which occurred during construction of the Air Force One Maintenance and Support complex will be presented","abstract_html":"This report will examine the fundamental principles associated with construction delay and recovering from the delay through actual acceleration. Methods for minimizing or eliminating construction delay and analyzing its impact on cost, quality, and timely completion of construction projects will be presented. A prototype expert system will be developed to assist the public and private owner in minimizing the possibility of construction delay. Additionally, two methods of schedule compression will be examined. A case study of the acceleration which occurred during construction of the Air Force One Maintenance and Support complex will be presented","abstract_has_math":false,"creators":["Bertolaccini, Steven G."],"institution":"Monterey, California. Naval Postgraduate School","degree_name":"M.S. in Civil Engineering","degree_level":"Masters","degree_discipline":"Civil Engineering","degree_department":"Civil Engineering","school":"NA","contributors":[],"advisors":[],"committee_chairs":[],"committee_members":[],"year":1989,"date_issued":"1989","date_published":"1989","updated_at":"2026-11-19T21:59:36Z","subjects":[],"languages":[],"rights":[],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier.oclc","label":"OCLC","values":["ocm77992185"],"render_values":[{"text":"ocm77992185","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/26075","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/26075","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F26075","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F26075","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.department","label":"Department","values":["Civil Engineering"]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["NA"]},{"key":"dc:contributor.school","label":"School","values":["NA"]},{"key":"dc:creator","label":"Author","values":["Bertolaccini, Steven G."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2013-01-23T21:55:56Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2013-01-23T21:55:56Z"]},{"key":"dc:date.issued","label":"Date","values":["1989"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, California. Naval Postgraduate School"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Civil Engineering"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["M.S. in Civil Engineering"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Georgia Institute of Technology"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.oclc","label":"OCLC","values":["ocm77992185"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/26075"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description","label":"Description","values":["Two maps on folded leaves in pockets"]},{"key":"dc:description.abstract","label":"Abstract","values":["This report will examine the fundamental principles associated with construction delay and recovering from the delay through actual acceleration. Methods for minimizing or eliminating construction delay and analyzing its impact on cost, quality, and timely completion of construction projects will be presented. A prototype expert system will be developed to assist the public and private owner in minimizing the possibility of construction delay. Additionally, two methods of schedule compression will be examined. A case study of the acceleration which occurred during construction of the Air Force One Maintenance and Support complex will be presented"]},{"key":"dc:description.award","label":"Dc Description Award","values":["NA"]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/minimizingndnaly1094526075"]},{"key":"dc:format.extent","label":"Dc Format Extent","values":["132 leaves: ill."]},{"key":"dc:title","label":"Title","values":["Minimizing and analyzing construction delay and its impacts: case studies and knowledge-based systems."]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]}]}],"canonical_facts":{"dc:contributor.department":["Civil Engineering"],"dc:contributor.other":["NA"],"dc:contributor.school":["NA"],"dc:creator":["Bertolaccini, Steven G."],"dc:date.accessioned":["2013-01-23T21:55:56Z"],"dc:date.available":["2013-01-23T21:55:56Z"],"dc:date.issued":["1989"],"dc:description":["Two maps on folded leaves in pockets"],"dc:description.abstract":["This report will examine the fundamental principles associated with construction delay and recovering from the delay through actual acceleration. Methods for minimizing or eliminating construction delay and analyzing its impact on cost, quality, and timely completion of construction projects will be presented. A prototype expert system will be developed to assist the public and private owner in minimizing the possibility of construction delay. Additionally, two methods of schedule compression will be examined. A case study of the acceleration which occurred during construction of the Air Force One Maintenance and Support complex will be presented"],"dc:description.award":["NA"],"dc:description.uri":["http://archive.org/details/minimizingndnaly1094526075"],"dc:format.extent":["132 leaves: ill."],"dc:identifier.oclc":["ocm77992185"],"dc:identifier.uri":["https://hdl.handle.net/10945/26075"],"dc:publisher":["Monterey, California. Naval Postgraduate School"],"dc:title":["Minimizing and analyzing construction delay and its impacts: case studies and knowledge-based systems."],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"thesis:degree_discipline":["Civil Engineering"],"thesis:degree_level":["Masters"],"thesis:degree_name":["M.S. in Civil Engineering"],"thesis:institution_name":["Georgia Institute of Technology"]},"updated_at":"2026-11-19T21:59:36Z"}