{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/34629"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/34629","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Implications of transaction costs for acquisition program cost breaches","abstract":"It is generally accepted that cost growth in federal major defense acquisition programs (MDAPs) is partially attributable to inaccurate cost estimates. Cost analysts exhaustively analyze manpower and resources to provide accurate estimates, however the influence of transaction costs is often ignored in traditional cost estimates. This thesis investigates the association between cost growth and transaction costs, the real cost of business negotiations and program management. We collect MDAP cost threshold breach data and cross reference it with a proxy for MDAP transaction costs (Systems Engineering/Program Management Costs) to determine whether a correlation exists. We use multiple logistic regression models to analyze the binary outcome of breach or no breach. The results show that for MDAPs with cost-plus contracts there is a statistically significant relation between the likelihood of a cost threshold breach occurring and the relative magnitude of the MDAPs transaction costs; no such relation exists for fixed price contracts. Although these results show an association between cost threshold breaches and transaction costs, there is no evidence of causality between these two variables and our exploration of causality is a topic for future research.","abstract_html":"It is generally accepted that cost growth in federal major defense acquisition programs (MDAPs) is partially attributable to inaccurate cost estimates. Cost analysts exhaustively analyze manpower and resources to provide accurate estimates, however the influence of transaction costs is often ignored in traditional cost estimates. This thesis investigates the association between cost growth and transaction costs, the real cost of business negotiations and program management. We collect MDAP cost threshold breach data and cross reference it with a proxy for MDAP transaction costs (Systems Engineering/Program Management Costs) to determine whether a correlation exists. We use multiple logistic regression models to analyze the binary outcome of breach or no breach. The results show that for MDAPs with cost-plus contracts there is a statistically significant relation between the likelihood of a cost threshold breach occurring and the relative magnitude of the MDAPs transaction costs; no such relation exists for fixed price contracts. Although these results show an association between cost threshold breaches and transaction costs, there is no evidence of causality between these two variables and our exploration of causality is a topic for future research.","abstract_has_math":false,"creators":["Biggs, Carl T."],"institution":"Monterey, California. Naval Postgraduate School","degree_name":"Master of Science","degree_level":"Masters","degree_discipline":"Systems Engineering","degree_department":"Systems Engineering (SE)","school":null,"contributors":[],"advisors":["Angelis, Diana","Franck, Raymond"],"committee_chairs":[],"committee_members":["Armey, Laura"],"year":2013,"date_issued":"2013-06","date_published":"2013-06","updated_at":"2026-11-19T06:33:31Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/34629","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/34629","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F34629","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F34629","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Angelis, Diana","Franck, Raymond"]},{"key":"dc:contributor.committeemember","label":"Committee Member","values":["Armey, Laura"]},{"key":"dc:contributor.department","label":"Department","values":["Systems Engineering (SE)"]},{"key":"dc:creator","label":"Author","values":["Biggs, Carl T."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["Jun-13"]},{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2013-08-01T16:51:24Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2013-08-01T16:51:24Z"]},{"key":"dc:date.issued","label":"Date","values":["2013-06"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, California. Naval Postgraduate School"]},{"key":"dc:relation.ispartofseries","label":"Dc Relation Ispartofseries","values":["NPS Outstanding Theses and Dissertations"]},{"key":"dc:relation.seriesentity","label":"Dc Relation Seriesentity","values":["c5e66392-520c-4aaf-9b4f-370ce82b601f"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Systems Engineering"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science","Master of Science in Systems Engineering"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["Transaction Costs;Costs Breaches;System Engineering/Program Management Cost.","Transaction Costs","Costs Breaches","System Engineering/Program Management Cost."]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/34629"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["It is generally accepted that cost growth in federal major defense acquisition programs (MDAPs) is partially attributable to inaccurate cost estimates. Cost analysts exhaustively analyze manpower and resources to provide accurate estimates, however the influence of transaction costs is often ignored in traditional cost estimates. This thesis investigates the association between cost growth and transaction costs, the real cost of business negotiations and program management. We collect MDAP cost threshold breach data and cross reference it with a proxy for MDAP transaction costs (Systems Engineering/Program Management Costs) to determine whether a correlation exists. We use multiple logistic regression models to analyze the binary outcome of breach or no breach. The results show that for MDAPs with cost-plus contracts there is a statistically significant relation between the likelihood of a cost threshold breach occurring and the relative magnitude of the MDAPs transaction costs; no such relation exists for fixed price contracts. Although these results show an association between cost threshold breaches and transaction costs, there is no evidence of causality between these two variables and our exploration of causality is a topic for future research."]},{"key":"dc:description.award","label":"Dc Description Award","values":["Outstanding Thesis"]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/implicationsoftr1094534629"]},{"key":"dc:title","label":"Title","values":["Implications of transaction costs for acquisition program cost breaches"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Lieutenant Commander, United States Navy"]}]}],"canonical_facts":{"dc:contributor.advisor":["Angelis, Diana","Franck, Raymond"],"dc:contributor.committeemember":["Armey, Laura"],"dc:contributor.department":["Systems Engineering (SE)"],"dc:creator":["Biggs, Carl T."],"dc:date":["Jun-13"],"dc:date.accessioned":["2013-08-01T16:51:24Z"],"dc:date.available":["2013-08-01T16:51:24Z"],"dc:date.issued":["2013-06"],"dc:description.abstract":["It is generally accepted that cost growth in federal major defense acquisition programs (MDAPs) is partially attributable to inaccurate cost estimates. Cost analysts exhaustively analyze manpower and resources to provide accurate estimates, however the influence of transaction costs is often ignored in traditional cost estimates. This thesis investigates the association between cost growth and transaction costs, the real cost of business negotiations and program management. We collect MDAP cost threshold breach data and cross reference it with a proxy for MDAP transaction costs (Systems Engineering/Program Management Costs) to determine whether a correlation exists. We use multiple logistic regression models to analyze the binary outcome of breach or no breach. The results show that for MDAPs with cost-plus contracts there is a statistically significant relation between the likelihood of a cost threshold breach occurring and the relative magnitude of the MDAPs transaction costs; no such relation exists for fixed price contracts. Although these results show an association between cost threshold breaches and transaction costs, there is no evidence of causality between these two variables and our exploration of causality is a topic for future research."],"dc:description.award":["Outstanding Thesis"],"dc:description.uri":["http://archive.org/details/implicationsoftr1094534629"],"dc:identifier.uri":["https://hdl.handle.net/10945/34629"],"dc:publisher":["Monterey, California. Naval Postgraduate School"],"dc:relation.ispartofseries":["NPS Outstanding Theses and Dissertations"],"dc:relation.seriesentity":["c5e66392-520c-4aaf-9b4f-370ce82b601f"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"dc:subject.keyword":["Transaction Costs;Costs Breaches;System Engineering/Program Management Cost.","Transaction Costs","Costs Breaches","System Engineering/Program Management Cost."],"dc:title":["Implications of transaction costs for acquisition program cost breaches"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Lieutenant Commander, United States Navy"],"thesis:degree_discipline":["Systems Engineering"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Master of Science","Master of Science in Systems Engineering"]},"updated_at":"2026-11-19T06:33:31Z"}