{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/3627"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/3627","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Prioritization of capital projects","abstract":"Public works capital projects in the U.S. naval forces are not prioritized and funded in a way that best uses limited operations resources and maintenance dollars. This thesis develops a linear model for public works commands to effectively prioritize and fund capital projects. This model allows each command to set its own criteria and weightings which are then used to score and rank capital projects. Using objective criteria, it seamlessly integrates new projects with existing projects into a command's Integrated Project List. The time formerly needed to manually rank each new project against all other projects is saved. Moreover, a command is able to keep a complete and comprehensive list of all unfunded capital projects. The subjectivity inherent in manual project priority decisions is removed. Ways to use existing computer systems in public works commands through Annual Inspection Summary reports are explored. The project decision process was studied through interviews conducted in commands at varying levels of the public works hierarchy. The linear model for project prioritization was developed in Excel. A spreadsheet sample of the linear model and detailed step-by-step instructions for its construction are available upon request from the author. Suggestions are made for further development of the project prioritization process.","abstract_html":"Public works capital projects in the U.S. naval forces are not prioritized and funded in a way that best uses limited operations resources and maintenance dollars. This thesis develops a linear model for public works commands to effectively prioritize and fund capital projects. This model allows each command to set its own criteria and weightings which are then used to score and rank capital projects. Using objective criteria, it seamlessly integrates new projects with existing projects into a command&#x27;s Integrated Project List. The time formerly needed to manually rank each new project against all other projects is saved. Moreover, a command is able to keep a complete and comprehensive list of all unfunded capital projects. The subjectivity inherent in manual project priority decisions is removed. Ways to use existing computer systems in public works commands through Annual Inspection Summary reports are explored. The project decision process was studied through interviews conducted in commands at varying levels of the public works hierarchy. The linear model for project prioritization was developed in Excel. A spreadsheet sample of the linear model and detailed step-by-step instructions for its construction are available upon request from the author. Suggestions are made for further development of the project prioritization process.","abstract_has_math":false,"creators":["LaVielle, Michael S."],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"M.S. in Management","degree_level":"Masters","degree_discipline":"Management","degree_department":null,"school":"Graduate School of Business and Public Policy","contributors":[],"advisors":["Haga, William J.","Manago, Saverio M."],"committee_chairs":[],"committee_members":[],"year":2002,"date_issued":"2002-12","date_published":"2002-12","updated_at":"2026-11-26T00:16:25Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/3627","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/3627","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F3627","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F3627","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Haga, William J.","Manago, Saverio M."]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Naval Postgraduate School"]},{"key":"dc:contributor.school","label":"School","values":["Graduate School of Business and Public Policy"]},{"key":"dc:creator","label":"Author","values":["LaVielle, Michael S."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["December 2002"]},{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-03-14T17:38:55Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-03-14T17:38:55Z"]},{"key":"dc:date.issued","label":"Date","values":["2002-12"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Management"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["M.S. in Management"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["Public works","Prioritization","Capital projects","Annual Inspection Summary","Integrated priority list","Linear model"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/3627"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["Public works capital projects in the U.S. naval forces are not prioritized and funded in a way that best uses limited operations resources and maintenance dollars. This thesis develops a linear model for public works commands to effectively prioritize and fund capital projects. This model allows each command to set its own criteria and weightings which are then used to score and rank capital projects. Using objective criteria, it seamlessly integrates new projects with existing projects into a command's Integrated Project List. The time formerly needed to manually rank each new project against all other projects is saved. Moreover, a command is able to keep a complete and comprehensive list of all unfunded capital projects. The subjectivity inherent in manual project priority decisions is removed. Ways to use existing computer systems in public works commands through Annual Inspection Summary reports are explored. The project decision process was studied through interviews conducted in commands at varying levels of the public works hierarchy. The linear model for project prioritization was developed in Excel. A spreadsheet sample of the linear model and detailed step-by-step instructions for its construction are available upon request from the author. Suggestions are made for further development of the project prioritization process."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/prioritizationof109453627"]},{"key":"dc:format.extent","label":"Dc Format Extent","values":["xiv, 55 p. : col. ill."]},{"key":"dc:title","label":"Title","values":["Prioritization of capital projects"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Lieutenant, United States Navy"]},{"key":"local:etd.verified","label":"Local Etd Verified","values":["no"]}]}],"canonical_facts":{"dc:contributor.advisor":["Haga, William J.","Manago, Saverio M."],"dc:contributor.other":["Naval Postgraduate School"],"dc:contributor.school":["Graduate School of Business and Public Policy"],"dc:creator":["LaVielle, Michael S."],"dc:date":["December 2002"],"dc:date.accessioned":["2012-03-14T17:38:55Z"],"dc:date.available":["2012-03-14T17:38:55Z"],"dc:date.issued":["2002-12"],"dc:description.abstract":["Public works capital projects in the U.S. naval forces are not prioritized and funded in a way that best uses limited operations resources and maintenance dollars. This thesis develops a linear model for public works commands to effectively prioritize and fund capital projects. This model allows each command to set its own criteria and weightings which are then used to score and rank capital projects. Using objective criteria, it seamlessly integrates new projects with existing projects into a command's Integrated Project List. The time formerly needed to manually rank each new project against all other projects is saved. Moreover, a command is able to keep a complete and comprehensive list of all unfunded capital projects. The subjectivity inherent in manual project priority decisions is removed. Ways to use existing computer systems in public works commands through Annual Inspection Summary reports are explored. The project decision process was studied through interviews conducted in commands at varying levels of the public works hierarchy. The linear model for project prioritization was developed in Excel. A spreadsheet sample of the linear model and detailed step-by-step instructions for its construction are available upon request from the author. Suggestions are made for further development of the project prioritization process."],"dc:description.uri":["http://archive.org/details/prioritizationof109453627"],"dc:format.extent":["xiv, 55 p. : col. ill."],"dc:identifier.uri":["https://hdl.handle.net/10945/3627"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"dc:subject.keyword":["Public works","Prioritization","Capital projects","Annual Inspection Summary","Integrated priority list","Linear model"],"dc:title":["Prioritization of capital projects"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Lieutenant, United States Navy"],"local:etd.verified":["no"],"thesis:degree_discipline":["Management"],"thesis:degree_level":["Masters"],"thesis:degree_name":["M.S. in Management"],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-26T00:16:25Z"}