{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/3875"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/3875","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Improved methodology for developing cost uncertainty models for naval vessels","abstract":"The purpose of this thesis is to analyze the probabilistic cost model currently in use by NAVSEA 05C to predict cost uncertainty in naval vessel construction and to develop a method that better predicts the ultimate cost risk. The data used to develop the improved approach is collected from analysis of the CG(X) class ship by NAVSEA 05C. The NAVSEA 05C cost risk factors are reviewed and analyzed to determine if different factors are better cost predictors. The impact of data elicitation, the Money Allocated Is Money Spent (MAIMS) principle, and correlation effects are incorporated into the research and analysis of this thesis. Data quality is directly affected by data elicitation methods and influences the choice of probability distribution used to give the best predictor of cost risk. MAIMS and correlation effects are shown to make a significant impact to the overall cost model. Program managers and analysts can readily implement the enhanced models using commercial Excel add-ins, such as Crystal Ball or @Risk, and integrate them into their current cost risk analysis and management practices to better mitigate risk and control project cost.","abstract_html":"The purpose of this thesis is to analyze the probabilistic cost model currently in use by NAVSEA 05C to predict cost uncertainty in naval vessel construction and to develop a method that better predicts the ultimate cost risk. The data used to develop the improved approach is collected from analysis of the CG(X) class ship by NAVSEA 05C. The NAVSEA 05C cost risk factors are reviewed and analyzed to determine if different factors are better cost predictors. The impact of data elicitation, the Money Allocated Is Money Spent (MAIMS) principle, and correlation effects are incorporated into the research and analysis of this thesis. Data quality is directly affected by data elicitation methods and influences the choice of probability distribution used to give the best predictor of cost risk. MAIMS and correlation effects are shown to make a significant impact to the overall cost model. Program managers and analysts can readily implement the enhanced models using commercial Excel add-ins, such as Crystal Ball or @Risk, and integrate them into their current cost risk analysis and management practices to better mitigate risk and control project cost.","abstract_has_math":false,"creators":["Brown, Cinda L."],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"Master of Science in Systems Engineering","degree_level":"Masters","degree_discipline":"Systems Engineering","degree_department":"Systems Engineering (SE)","school":null,"contributors":[],"advisors":["Kujawski, Edouard."],"committee_chairs":[],"committee_members":["Angelis, Diana"],"year":2008,"date_issued":"2008-09","date_published":"2008-09","updated_at":"2026-11-19T06:34:01Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier.oclc","label":"OCLC","values":["268693859"],"render_values":[{"text":"268693859","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/3875","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/3875","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F3875","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F3875","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Kujawski, Edouard."]},{"key":"dc:contributor.committeemember","label":"Committee Member","values":["Angelis, Diana"]},{"key":"dc:contributor.department","label":"Department","values":["Systems Engineering (SE)"]},{"key":"dc:creator","label":"Author","values":["Brown, Cinda L."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-03-14T17:39:38Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-03-14T17:39:38Z"]},{"key":"dc:date.issued","label":"Date","values":["2008-09"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["73c095de-fa3b-4d63-8300-9b6aee5b4d62"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Systems Engineering"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science in Systems Engineering"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["Cost Uncertainty","Cost model","Surface Ship","Estimation","Naval Vessel"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.oclc","label":"OCLC","values":["268693859"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/3875"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["The purpose of this thesis is to analyze the probabilistic cost model currently in use by NAVSEA 05C to predict cost uncertainty in naval vessel construction and to develop a method that better predicts the ultimate cost risk. The data used to develop the improved approach is collected from analysis of the CG(X) class ship by NAVSEA 05C. The NAVSEA 05C cost risk factors are reviewed and analyzed to determine if different factors are better cost predictors. The impact of data elicitation, the Money Allocated Is Money Spent (MAIMS) principle, and correlation effects are incorporated into the research and analysis of this thesis. Data quality is directly affected by data elicitation methods and influences the choice of probability distribution used to give the best predictor of cost risk. MAIMS and correlation effects are shown to make a significant impact to the overall cost model. Program managers and analysts can readily implement the enhanced models using commercial Excel add-ins, such as Crystal Ball or @Risk, and integrate them into their current cost risk analysis and management practices to better mitigate risk and control project cost."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/improvedmethodol109453875"]},{"key":"dc:title","label":"Title","values":["Improved methodology for developing cost uncertainty models for naval vessels"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Lieutenant Commander, United States Navy"]}]}],"canonical_facts":{"dc:contributor.advisor":["Kujawski, Edouard."],"dc:contributor.committeemember":["Angelis, Diana"],"dc:contributor.department":["Systems Engineering (SE)"],"dc:creator":["Brown, Cinda L."],"dc:date.accessioned":["2012-03-14T17:39:38Z"],"dc:date.available":["2012-03-14T17:39:38Z"],"dc:date.issued":["2008-09"],"dc:description.abstract":["The purpose of this thesis is to analyze the probabilistic cost model currently in use by NAVSEA 05C to predict cost uncertainty in naval vessel construction and to develop a method that better predicts the ultimate cost risk. The data used to develop the improved approach is collected from analysis of the CG(X) class ship by NAVSEA 05C. The NAVSEA 05C cost risk factors are reviewed and analyzed to determine if different factors are better cost predictors. The impact of data elicitation, the Money Allocated Is Money Spent (MAIMS) principle, and correlation effects are incorporated into the research and analysis of this thesis. Data quality is directly affected by data elicitation methods and influences the choice of probability distribution used to give the best predictor of cost risk. MAIMS and correlation effects are shown to make a significant impact to the overall cost model. Program managers and analysts can readily implement the enhanced models using commercial Excel add-ins, such as Crystal Ball or @Risk, and integrate them into their current cost risk analysis and management practices to better mitigate risk and control project cost."],"dc:description.uri":["http://archive.org/details/improvedmethodol109453875"],"dc:identifier.oclc":["268693859"],"dc:identifier.uri":["https://hdl.handle.net/10945/3875"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:relation.orgunit":["73c095de-fa3b-4d63-8300-9b6aee5b4d62"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"dc:subject.keyword":["Cost Uncertainty","Cost model","Surface Ship","Estimation","Naval Vessel"],"dc:title":["Improved methodology for developing cost uncertainty models for naval vessels"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Lieutenant Commander, United States Navy"],"thesis:degree_discipline":["Systems Engineering"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Master of Science in Systems Engineering"],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-19T06:34:01Z"}