{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/4364"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/4364","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Application of adaptive CERs to the Korea Helicopter Project","abstract":"This thesis develops new models to estimate the cost for a defense acquisition project, namely the Korean Helicopter Program (KHP). The thesis constructs various cost estimating models based on the traditional Ordinary Least Square (OLS) method and the Adaptive Cost Estimating Relationships (CER), which was introduced in June 2008. This new methodology is used to improve the uncertainty of OLS as shown in the differences between actual data and predicted values. In particular, the new (Adaptive) CER method uses three ways of estimation to diminish the errors; a priori, piece-wise, and X-distance methods. Among these three approaches, this thesis deals with the priori method, which assigns weights to individual data points. By comparing the OLS and the weighted methods, improvements in the cost estimates can be achieved. In addition, this thesis provided robust cost estimates for the KHP.","abstract_html":"This thesis develops new models to estimate the cost for a defense acquisition project, namely the Korean Helicopter Program (KHP). The thesis constructs various cost estimating models based on the traditional Ordinary Least Square (OLS) method and the Adaptive Cost Estimating Relationships (CER), which was introduced in June 2008. This new methodology is used to improve the uncertainty of OLS as shown in the differences between actual data and predicted values. In particular, the new (Adaptive) CER method uses three ways of estimation to diminish the errors; a priori, piece-wise, and X-distance methods. Among these three approaches, this thesis deals with the priori method, which assigns weights to individual data points. By comparing the OLS and the weighted methods, improvements in the cost estimates can be achieved. In addition, this thesis provided robust cost estimates for the KHP.","abstract_has_math":false,"creators":["Oh, Jaecheon"],"institution":"Monterey, California. Naval Postgraduate School","degree_name":"M.S.","degree_level":"Masters","degree_discipline":"Operations Research","degree_department":null,"school":null,"contributors":[],"advisors":["Nussbaum, Daniel"],"committee_chairs":[],"committee_members":["Kang, Sung Jin"],"year":2009,"date_issued":"2009-12","date_published":"2009-12","updated_at":"2026-11-19T06:35:21Z","subjects":["Operations research"],"languages":[],"rights":["Approved for public release; distribution is unlimited."],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier.oclc","label":"OCLC","values":["503147730"],"render_values":[{"text":"503147730","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/4364","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/4364","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F4364","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Nussbaum, Daniel"]},{"key":"dc:contributor.committeemember","label":"Committee Member","values":["Kang, Sung Jin"]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Naval Postgraduate School (U.S.)"]},{"key":"dc:creator","label":"Author","values":["Oh, Jaecheon"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-03-14T17:41:40Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-03-14T17:41:40Z"]},{"key":"dc:date.issued","label":"Date","values":["2009-12"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, California. Naval Postgraduate School"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Operations Research"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["M.S."]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.lcsh","label":"Dc Subject Lcsh","values":["Operations research"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["Approved for public release; distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.oclc","label":"OCLC","values":["503147730"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/4364"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["This thesis develops new models to estimate the cost for a defense acquisition project, namely the Korean Helicopter Program (KHP). The thesis constructs various cost estimating models based on the traditional Ordinary Least Square (OLS) method and the Adaptive Cost Estimating Relationships (CER), which was introduced in June 2008. This new methodology is used to improve the uncertainty of OLS as shown in the differences between actual data and predicted values. In particular, the new (Adaptive) CER method uses three ways of estimation to diminish the errors; a priori, piece-wise, and X-distance methods. Among these three approaches, this thesis deals with the priori method, which assigns weights to individual data points. By comparing the OLS and the weighted methods, improvements in the cost estimates can be achieved. In addition, this thesis provided robust cost estimates for the KHP."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/applicationofdap109454364"]},{"key":"dc:format.extent","label":"Dc Format Extent","values":["xvi, 81 p. :"]},{"key":"dc:title","label":"Title","values":["Application of adaptive CERs to the Korea Helicopter Project"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Republic of Korea Army author."]},{"key":"local:etd.verified","label":"Local Etd Verified","values":["no"]}]}],"canonical_facts":{"dc:contributor.advisor":["Nussbaum, Daniel"],"dc:contributor.committeemember":["Kang, Sung Jin"],"dc:contributor.other":["Naval Postgraduate School (U.S.)"],"dc:creator":["Oh, Jaecheon"],"dc:date.accessioned":["2012-03-14T17:41:40Z"],"dc:date.available":["2012-03-14T17:41:40Z"],"dc:date.issued":["2009-12"],"dc:description.abstract":["This thesis develops new models to estimate the cost for a defense acquisition project, namely the Korean Helicopter Program (KHP). The thesis constructs various cost estimating models based on the traditional Ordinary Least Square (OLS) method and the Adaptive Cost Estimating Relationships (CER), which was introduced in June 2008. This new methodology is used to improve the uncertainty of OLS as shown in the differences between actual data and predicted values. In particular, the new (Adaptive) CER method uses three ways of estimation to diminish the errors; a priori, piece-wise, and X-distance methods. Among these three approaches, this thesis deals with the priori method, which assigns weights to individual data points. By comparing the OLS and the weighted methods, improvements in the cost estimates can be achieved. In addition, this thesis provided robust cost estimates for the KHP."],"dc:description.uri":["http://archive.org/details/applicationofdap109454364"],"dc:format.extent":["xvi, 81 p. :"],"dc:identifier.oclc":["503147730"],"dc:identifier.uri":["https://hdl.handle.net/10945/4364"],"dc:publisher":["Monterey, California. Naval Postgraduate School"],"dc:rights":["Approved for public release; distribution is unlimited."],"dc:subject.lcsh":["Operations research"],"dc:title":["Application of adaptive CERs to the Korea Helicopter Project"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Republic of Korea Army author."],"local:etd.verified":["no"],"thesis:degree_discipline":["Operations Research"],"thesis:degree_level":["Masters"],"thesis:degree_name":["M.S."],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-19T06:35:21Z"}