{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/43868"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/43868","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Optimization of Continuous Maintenance Availability Scheduling","abstract":"Every few months each United States submarine must return to a port to undergo major maintenance that cannot be conducted at sea. These maintenance periods are called Continuous Maintenance Availability (CMAV) periods. All CMAV scheduling aboard the two remaining submarine tenders in the United States fleet, the USS Emory S. Land (AS 39) and the USS Frank Cable (AS 40), is currently done manually. The schedulers rely on their experience and sound judgment with the goal of successfully completing the most maintenance as quickly and efficiently as possible for approximately 200 jobs, 50 maintenance shops and a host of other considerations. In this thesis, we develop a job-shop scheduling model, the CMAV Scheduler (CMAV-S). This is a large-scale, mixed-integer, linear program that accounts for a variety of scheduling inputs commonly used by planners: job priority, duration, allowed window of execution, prerequisites, mandatory character, workforce used and available (by shop), and special submarine conditions (active or inactive) needed to perform a job. CMAV-S produces near-optimal schedules that achieve maximum value for all scheduled jobs in about one minute. When compared to our own manual scheduling, we observe CMAV-S improves up to 25% the required CMAV length to schedule all maintenance.","abstract_html":"Every few months each United States submarine must return to a port to undergo major maintenance that cannot be conducted at sea. These maintenance periods are called Continuous Maintenance Availability (CMAV) periods. All CMAV scheduling aboard the two remaining submarine tenders in the United States fleet, the USS Emory S. Land (AS 39) and the USS Frank Cable (AS 40), is currently done manually. The schedulers rely on their experience and sound judgment with the goal of successfully completing the most maintenance as quickly and efficiently as possible for approximately 200 jobs, 50 maintenance shops and a host of other considerations. In this thesis, we develop a job-shop scheduling model, the CMAV Scheduler (CMAV-S). This is a large-scale, mixed-integer, linear program that accounts for a variety of scheduling inputs commonly used by planners: job priority, duration, allowed window of execution, prerequisites, mandatory character, workforce used and available (by shop), and special submarine conditions (active or inactive) needed to perform a job. CMAV-S produces near-optimal schedules that achieve maximum value for all scheduled jobs in about one minute. When compared to our own manual scheduling, we observe CMAV-S improves up to 25% the required CMAV length to schedule all maintenance.","abstract_has_math":false,"creators":["Anderson, Cyrus K."],"institution":"Monterey, California: Naval Postgraduate School","degree_name":"Master of Science in Operations Research","degree_level":"Masters","degree_discipline":"Operations Research","degree_department":"Operations Research","school":null,"contributors":[],"advisors":["Salmeron, Javier"],"committee_chairs":[],"committee_members":["Dufek, Michael"],"year":2014,"date_issued":"2014-09","date_published":"2014-09","updated_at":"2026-11-19T06:35:21Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/43868","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/43868","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F43868","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F43868","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Salmeron, Javier"]},{"key":"dc:contributor.committeemember","label":"Committee Member","values":["Dufek, Michael"]},{"key":"dc:contributor.department","label":"Department","values":["Operations Research"]},{"key":"dc:creator","label":"Author","values":["Anderson, Cyrus K."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["Sep-14"]},{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2014-12-05T20:09:47Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2014-12-05T20:09:47Z"]},{"key":"dc:date.issued","label":"Date","values":["2014-09"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, California: Naval Postgraduate School"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Operations Research"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science in Operations Research"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["Optimization","Submarine Maintenance","Job-shop Scheduling","Continuous Maintenance Availability"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/43868"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["Every few months each United States submarine must return to a port to undergo major maintenance that cannot be conducted at sea. These maintenance periods are called Continuous Maintenance Availability (CMAV) periods. All CMAV scheduling aboard the two remaining submarine tenders in the United States fleet, the USS Emory S. Land (AS 39) and the USS Frank Cable (AS 40), is currently done manually. The schedulers rely on their experience and sound judgment with the goal of successfully completing the most maintenance as quickly and efficiently as possible for approximately 200 jobs, 50 maintenance shops and a host of other considerations. In this thesis, we develop a job-shop scheduling model, the CMAV Scheduler (CMAV-S). This is a large-scale, mixed-integer, linear program that accounts for a variety of scheduling inputs commonly used by planners: job priority, duration, allowed window of execution, prerequisites, mandatory character, workforce used and available (by shop), and special submarine conditions (active or inactive) needed to perform a job. CMAV-S produces near-optimal schedules that achieve maximum value for all scheduled jobs in about one minute. When compared to our own manual scheduling, we observe CMAV-S improves up to 25% the required CMAV length to schedule all maintenance."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/optimizationofco1094543868"]},{"key":"dc:title","label":"Title","values":["Optimization of Continuous Maintenance Availability Scheduling"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Lieutenant, United States Navy"]}]}],"canonical_facts":{"dc:contributor.advisor":["Salmeron, Javier"],"dc:contributor.committeemember":["Dufek, Michael"],"dc:contributor.department":["Operations Research"],"dc:creator":["Anderson, Cyrus K."],"dc:date":["Sep-14"],"dc:date.accessioned":["2014-12-05T20:09:47Z"],"dc:date.available":["2014-12-05T20:09:47Z"],"dc:date.issued":["2014-09"],"dc:description.abstract":["Every few months each United States submarine must return to a port to undergo major maintenance that cannot be conducted at sea. These maintenance periods are called Continuous Maintenance Availability (CMAV) periods. All CMAV scheduling aboard the two remaining submarine tenders in the United States fleet, the USS Emory S. Land (AS 39) and the USS Frank Cable (AS 40), is currently done manually. The schedulers rely on their experience and sound judgment with the goal of successfully completing the most maintenance as quickly and efficiently as possible for approximately 200 jobs, 50 maintenance shops and a host of other considerations. In this thesis, we develop a job-shop scheduling model, the CMAV Scheduler (CMAV-S). This is a large-scale, mixed-integer, linear program that accounts for a variety of scheduling inputs commonly used by planners: job priority, duration, allowed window of execution, prerequisites, mandatory character, workforce used and available (by shop), and special submarine conditions (active or inactive) needed to perform a job. CMAV-S produces near-optimal schedules that achieve maximum value for all scheduled jobs in about one minute. When compared to our own manual scheduling, we observe CMAV-S improves up to 25% the required CMAV length to schedule all maintenance."],"dc:description.uri":["http://archive.org/details/optimizationofco1094543868"],"dc:identifier.uri":["https://hdl.handle.net/10945/43868"],"dc:publisher":["Monterey, California: Naval Postgraduate School"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"dc:subject.keyword":["Optimization","Submarine Maintenance","Job-shop Scheduling","Continuous Maintenance Availability"],"dc:title":["Optimization of Continuous Maintenance Availability Scheduling"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Lieutenant, United States Navy"],"thesis:degree_discipline":["Operations Research"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Master of Science in Operations Research"],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-19T06:35:21Z"}