{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/45846"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/45846","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Optimizing Department of Defense Acquisition Development Test and Evaluation scheduling","abstract":"Department of Defense (DOD) Development Test and Evaluation (DT&E) activities for new acquisitions account for a large portion of time and money during the Engineering and Manufacturing Development Phase. DOD Program Management Office test personnel develop test schedules manually using time estimates and heuristic subject matter expert advice for each test to forecast the overall time and costs associated with a developed course of action. These manually constructed schedules take weeks to develop via many planning iterations to construct an acceptable, but not necessarily feasible or optimal solution. Ultimately, these forecast schedules and duration estimates can be inaccurate, and may result in schedule delays and/or cost overruns. This thesis presents an optimization and simulation model as a decision support tool to improve current DT&E scheduling. We represent this resource-constrained scheduling problem as an integer linear program, and develop set enumeration reduction techniques, as well as a cascade method to reduce solve times. The proposed model, unlike current manual scheduling techniques, suggests schedules that are feasible, nearly optimal, and are produced quickly for effective analysis of alternatives.","abstract_html":"Department of Defense (DOD) Development Test and Evaluation (DT&amp;E) activities for new acquisitions account for a large portion of time and money during the Engineering and Manufacturing Development Phase. DOD Program Management Office test personnel develop test schedules manually using time estimates and heuristic subject matter expert advice for each test to forecast the overall time and costs associated with a developed course of action. These manually constructed schedules take weeks to develop via many planning iterations to construct an acceptable, but not necessarily feasible or optimal solution. Ultimately, these forecast schedules and duration estimates can be inaccurate, and may result in schedule delays and/or cost overruns. This thesis presents an optimization and simulation model as a decision support tool to improve current DT&amp;E scheduling. We represent this resource-constrained scheduling problem as an integer linear program, and develop set enumeration reduction techniques, as well as a cascade method to reduce solve times. The proposed model, unlike current manual scheduling techniques, suggests schedules that are feasible, nearly optimal, and are produced quickly for effective analysis of alternatives.","abstract_has_math":false,"creators":["Edwards, Shane A."],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"Master of Science in Operations Research","degree_level":"Masters","degree_discipline":"Operations Research","degree_department":"Operations Research (OR)","school":null,"contributors":[],"advisors":["Brown, Gerald"],"committee_chairs":[],"committee_members":["Kline, Jeffrey"],"year":2015,"date_issued":"2015-06","date_published":"2015-06","updated_at":"2026-11-19T06:35:40Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/45846","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/45846","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F45846","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Brown, Gerald"]},{"key":"dc:contributor.committeemember","label":"Committee Member","values":["Kline, Jeffrey"]},{"key":"dc:contributor.department","label":"Department","values":["Operations Research (OR)"]},{"key":"dc:creator","label":"Author","values":["Edwards, Shane A."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2015-08-05T23:05:33Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2015-08-05T23:05:33Z"]},{"key":"dc:date.issued","label":"Date","values":["2015-06"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["58745961-c46a-45ad-ae9c-d139d1ba1041"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Operations Research"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science in Operations Research"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["Optimization","test and evaluation","integer linear programming","cascade","project scheduling","project management"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/45846"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["Department of Defense (DOD) Development Test and Evaluation (DT&E) activities for new acquisitions account for a large portion of time and money during the Engineering and Manufacturing Development Phase. DOD Program Management Office test personnel develop test schedules manually using time estimates and heuristic subject matter expert advice for each test to forecast the overall time and costs associated with a developed course of action. These manually constructed schedules take weeks to develop via many planning iterations to construct an acceptable, but not necessarily feasible or optimal solution. Ultimately, these forecast schedules and duration estimates can be inaccurate, and may result in schedule delays and/or cost overruns. This thesis presents an optimization and simulation model as a decision support tool to improve current DT&E scheduling. We represent this resource-constrained scheduling problem as an integer linear program, and develop set enumeration reduction techniques, as well as a cascade method to reduce solve times. The proposed model, unlike current manual scheduling techniques, suggests schedules that are feasible, nearly optimal, and are produced quickly for effective analysis of alternatives."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/optimizingdepart1094545846"]},{"key":"dc:title","label":"Title","values":["Optimizing Department of Defense Acquisition Development Test and Evaluation scheduling"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Major, United States Marine Corps"]}]}],"canonical_facts":{"dc:contributor.advisor":["Brown, Gerald"],"dc:contributor.committeemember":["Kline, Jeffrey"],"dc:contributor.department":["Operations Research (OR)"],"dc:creator":["Edwards, Shane A."],"dc:date.accessioned":["2015-08-05T23:05:33Z"],"dc:date.available":["2015-08-05T23:05:33Z"],"dc:date.issued":["2015-06"],"dc:description.abstract":["Department of Defense (DOD) Development Test and Evaluation (DT&E) activities for new acquisitions account for a large portion of time and money during the Engineering and Manufacturing Development Phase. DOD Program Management Office test personnel develop test schedules manually using time estimates and heuristic subject matter expert advice for each test to forecast the overall time and costs associated with a developed course of action. These manually constructed schedules take weeks to develop via many planning iterations to construct an acceptable, but not necessarily feasible or optimal solution. Ultimately, these forecast schedules and duration estimates can be inaccurate, and may result in schedule delays and/or cost overruns. This thesis presents an optimization and simulation model as a decision support tool to improve current DT&E scheduling. We represent this resource-constrained scheduling problem as an integer linear program, and develop set enumeration reduction techniques, as well as a cascade method to reduce solve times. The proposed model, unlike current manual scheduling techniques, suggests schedules that are feasible, nearly optimal, and are produced quickly for effective analysis of alternatives."],"dc:description.uri":["http://archive.org/details/optimizingdepart1094545846"],"dc:identifier.uri":["https://hdl.handle.net/10945/45846"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:relation.orgunit":["58745961-c46a-45ad-ae9c-d139d1ba1041"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"dc:subject.keyword":["Optimization","test and evaluation","integer linear programming","cascade","project scheduling","project management"],"dc:title":["Optimizing Department of Defense Acquisition Development Test and Evaluation scheduling"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Major, United States Marine Corps"],"thesis:degree_discipline":["Operations Research"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Master of Science in Operations Research"],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-19T06:35:40Z"}