{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/47326"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/47326","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Planning to execution earned value risk management tool","abstract":"This study presents a proof-of-concept software application capable of producing risk-based estimates for project costs and schedules, tracking project performance against baseline plans, and providing real-time updates for cost and schedule at completion. Current budget and schedule estimation practices within the Department of Defense (DOD) are often performed by different personnel across several software tools. Market research of existing commercial off-the-shelf (COTS) project planning and tracking software shows that tools commonly used by many industries require additional software packages and user training to perform uncertainty analyses. A modeling and simulation experiment demonstrates how using minimum and maximum duration estimates can result in baseline project plans that greatly underestimate and overestimate the project schedule, respectively. The prototype software application integrates the planning and execution tracking of projects. It accounts for uncertainty within the various activities in a project, thus creating more realistic baseline plans. During project execution, the prototype software application shortens the project status feedback cycle, identifies any activities that go over cost or schedule, and guides management action by determining which activities have the greatest impact on the outcome of the project. It is easier to use when compared to current planning and execution tracking software applications.","abstract_html":"This study presents a proof-of-concept software application capable of producing risk-based estimates for project costs and schedules, tracking project performance against baseline plans, and providing real-time updates for cost and schedule at completion. Current budget and schedule estimation practices within the Department of Defense (DOD) are often performed by different personnel across several software tools. Market research of existing commercial off-the-shelf (COTS) project planning and tracking software shows that tools commonly used by many industries require additional software packages and user training to perform uncertainty analyses. A modeling and simulation experiment demonstrates how using minimum and maximum duration estimates can result in baseline project plans that greatly underestimate and overestimate the project schedule, respectively. The prototype software application integrates the planning and execution tracking of projects. It accounts for uncertainty within the various activities in a project, thus creating more realistic baseline plans. During project execution, the prototype software application shortens the project status feedback cycle, identifies any activities that go over cost or schedule, and guides management action by determining which activities have the greatest impact on the outcome of the project. It is easier to use when compared to current planning and execution tracking software applications.","abstract_has_math":false,"creators":["Baldwin, Matthew","Shultz,David","Ancheta, Jason","Aschenbrenner, Lisa","Hirth, Brian","Martin, Joseph","Moye, Devilin","Navedo, Emmanuel","Twigg, Andrew","Team MERICA","Cohort 311-141A"],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"Master of Science in Systems Engineering","degree_level":"Masters","degree_discipline":"Systems Engineering","degree_department":"Systems Engineering (SE)","school":null,"contributors":[],"advisors":["Rhoades, Mark M.","Miller, Gregory"],"committee_chairs":[],"committee_members":[],"year":2015,"date_issued":"2015-09","date_published":"2015-09","updated_at":"2026-11-19T06:35:56Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited.","Copyright is reserved by the copyright owner."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/47326","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/47326","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F47326","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F47326","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Rhoades, Mark M.","Miller, Gregory"]},{"key":"dc:contributor.department","label":"Department","values":["Systems Engineering (SE)"]},{"key":"dc:creator","label":"Author","values":["Baldwin, Matthew","Shultz,David","Ancheta, Jason","Aschenbrenner, Lisa","Hirth, Brian","Martin, Joseph","Moye, Devilin","Navedo, Emmanuel","Twigg, Andrew","Team MERICA","Cohort 311-141A"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2015-11-06T18:22:45Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2015-11-06T18:22:45Z"]},{"key":"dc:date.issued","label":"Date","values":["2015-09"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["73c095de-fa3b-4d63-8300-9b6aee5b4d62"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Systems Engineering","Engineering Systems"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science in Systems Engineering","Master of Science in Engineering Systems"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["budget","schedule","cost","duration","uncertainty","estimates","earned-value management","risk-based scheduling","risk-based budgeting"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited.","Copyright is reserved by the copyright owner."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/47326"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["This study presents a proof-of-concept software application capable of producing risk-based estimates for project costs and schedules, tracking project performance against baseline plans, and providing real-time updates for cost and schedule at completion. Current budget and schedule estimation practices within the Department of Defense (DOD) are often performed by different personnel across several software tools. Market research of existing commercial off-the-shelf (COTS) project planning and tracking software shows that tools commonly used by many industries require additional software packages and user training to perform uncertainty analyses. A modeling and simulation experiment demonstrates how using minimum and maximum duration estimates can result in baseline project plans that greatly underestimate and overestimate the project schedule, respectively. The prototype software application integrates the planning and execution tracking of projects. It accounts for uncertainty within the various activities in a project, thus creating more realistic baseline plans. During project execution, the prototype software application shortens the project status feedback cycle, identifies any activities that go over cost or schedule, and guides management action by determining which activities have the greatest impact on the outcome of the project. It is easier to use when compared to current planning and execution tracking software applications."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/planningtoexecut1094547326"]},{"key":"dc:title","label":"Title","values":["Planning to execution earned value risk management tool"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]}]}],"canonical_facts":{"dc:contributor.advisor":["Rhoades, Mark M.","Miller, Gregory"],"dc:contributor.department":["Systems Engineering (SE)"],"dc:creator":["Baldwin, Matthew","Shultz,David","Ancheta, Jason","Aschenbrenner, Lisa","Hirth, Brian","Martin, Joseph","Moye, Devilin","Navedo, Emmanuel","Twigg, Andrew","Team MERICA","Cohort 311-141A"],"dc:date.accessioned":["2015-11-06T18:22:45Z"],"dc:date.available":["2015-11-06T18:22:45Z"],"dc:date.issued":["2015-09"],"dc:description.abstract":["This study presents a proof-of-concept software application capable of producing risk-based estimates for project costs and schedules, tracking project performance against baseline plans, and providing real-time updates for cost and schedule at completion. Current budget and schedule estimation practices within the Department of Defense (DOD) are often performed by different personnel across several software tools. Market research of existing commercial off-the-shelf (COTS) project planning and tracking software shows that tools commonly used by many industries require additional software packages and user training to perform uncertainty analyses. A modeling and simulation experiment demonstrates how using minimum and maximum duration estimates can result in baseline project plans that greatly underestimate and overestimate the project schedule, respectively. The prototype software application integrates the planning and execution tracking of projects. It accounts for uncertainty within the various activities in a project, thus creating more realistic baseline plans. During project execution, the prototype software application shortens the project status feedback cycle, identifies any activities that go over cost or schedule, and guides management action by determining which activities have the greatest impact on the outcome of the project. It is easier to use when compared to current planning and execution tracking software applications."],"dc:description.uri":["http://archive.org/details/planningtoexecut1094547326"],"dc:identifier.uri":["https://hdl.handle.net/10945/47326"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:relation.orgunit":["73c095de-fa3b-4d63-8300-9b6aee5b4d62"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited.","Copyright is reserved by the copyright owner."],"dc:subject.keyword":["budget","schedule","cost","duration","uncertainty","estimates","earned-value management","risk-based scheduling","risk-based budgeting"],"dc:title":["Planning to execution earned value risk management tool"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"thesis:degree_discipline":["Systems Engineering","Engineering Systems"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Master of Science in Systems Engineering","Master of Science in Engineering Systems"],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-19T06:35:56Z"}