{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/60405"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/60405","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"A SYSTEMS APPROACH TO MANAGING LOW-SCOPE GROWTH-WORK IN NEW CONSTRUCTION SHIPBUILDING","abstract":"The goal of this study is to determine if a set of heuristics can be used as a decision-making tool to effectively determine what low-scope growth-work needs to be targeted for execution early in the construction cycle of a new naval ship. This study analyzes growth-work that is not incorporated into the base contract with a formal engineering change proposal, but rather a less-formal waterfront change process where the logistics and engineering products are updated after the delivery of the ship. This study shows why some growth-work is significantly more expensive or disruptive to the crew if completed after delivery of the ship. Growth-work is realized during the long construction cycle due to technology changes, lessons learned from previous hulls, fleet requirement changes, and contract requirement gaps. Since not all of the growth-work can be incorporated during the period of performance of the base contract, this study lays out a heuristics-based systems approach to managing low-scope growth-work in new construction shipbuilding. This study shows which heuristics are effective to target growth-work that will drive cost and crew disruption if executed after the delivery of the ship. Finally, this study models this approach using cam DEFinition for Function Modeling (IDEF0) diagrams. These models provide a framework for use by other program offices.","abstract_html":"The goal of this study is to determine if a set of heuristics can be used as a decision-making tool to effectively determine what low-scope growth-work needs to be targeted for execution early in the construction cycle of a new naval ship. This study analyzes growth-work that is not incorporated into the base contract with a formal engineering change proposal, but rather a less-formal waterfront change process where the logistics and engineering products are updated after the delivery of the ship. This study shows why some growth-work is significantly more expensive or disruptive to the crew if completed after delivery of the ship. Growth-work is realized during the long construction cycle due to technology changes, lessons learned from previous hulls, fleet requirement changes, and contract requirement gaps. Since not all of the growth-work can be incorporated during the period of performance of the base contract, this study lays out a heuristics-based systems approach to managing low-scope growth-work in new construction shipbuilding. This study shows which heuristics are effective to target growth-work that will drive cost and crew disruption if executed after the delivery of the ship. Finally, this study models this approach using cam DEFinition for Function Modeling (IDEF0) diagrams. These models provide a framework for use by other program offices.","abstract_has_math":false,"creators":["Glass, Mark R."],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"Master of Science in Systems Engineering Management","degree_level":"Masters","degree_discipline":"Systems Engineering Management","degree_department":"Systems Engineering (SE)","school":null,"contributors":[],"advisors":["Pickar, Charles K."],"committee_chairs":[],"committee_members":["Owen, Walter E."],"year":2018,"date_issued":"2018-09","date_published":"2018-09","updated_at":"2026-11-19T06:38:38Z","subjects":[],"languages":[],"rights":["Copyright is reserved by the copyright owner.","Approved for public release; distribution is unlimited."],"rights_urls":[],"identifier_entries":[{"key":"thesis:thesis_identifier","label":"Thesis Thesis Identifier","values":["31684"],"render_values":[{"text":"31684","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/60405","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/60405","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F60405","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F60405","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Pickar, Charles K."]},{"key":"dc:contributor.committeemember","label":"Committee Member","values":["Owen, Walter E."]},{"key":"dc:contributor.department","label":"Department","values":["Systems Engineering (SE)"]},{"key":"dc:creator","label":"Author","values":["Glass, Mark R."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2018-10-26T19:21:32Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2018-10-26T19:21:32Z"]},{"key":"dc:date.issued","label":"Date","values":["2018-09"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Systems Engineering Management"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science in Systems Engineering Management"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]},{"key":"thesis:thesis_identifier","label":"Thesis Thesis Identifier","values":["31684"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["shipbuilding","change","growth-work","new construction","IDEF0"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["Copyright is reserved by the copyright owner.","Approved for public release; distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/60405"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["The goal of this study is to determine if a set of heuristics can be used as a decision-making tool to effectively determine what low-scope growth-work needs to be targeted for execution early in the construction cycle of a new naval ship. This study analyzes growth-work that is not incorporated into the base contract with a formal engineering change proposal, but rather a less-formal waterfront change process where the logistics and engineering products are updated after the delivery of the ship. This study shows why some growth-work is significantly more expensive or disruptive to the crew if completed after delivery of the ship. Growth-work is realized during the long construction cycle due to technology changes, lessons learned from previous hulls, fleet requirement changes, and contract requirement gaps. Since not all of the growth-work can be incorporated during the period of performance of the base contract, this study lays out a heuristics-based systems approach to managing low-scope growth-work in new construction shipbuilding. This study shows which heuristics are effective to target growth-work that will drive cost and crew disruption if executed after the delivery of the ship. Finally, this study models this approach using cam DEFinition for Function Modeling (IDEF0) diagrams. These models provide a framework for use by other program offices."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/asystemsapproach1094560405"]},{"key":"dc:title","label":"Title","values":["A SYSTEMS APPROACH TO MANAGING LOW-SCOPE GROWTH-WORK IN NEW CONSTRUCTION SHIPBUILDING"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Civilian, Department of the Navy"]}]}],"canonical_facts":{"dc:contributor.advisor":["Pickar, Charles K."],"dc:contributor.committeemember":["Owen, Walter E."],"dc:contributor.department":["Systems Engineering (SE)"],"dc:creator":["Glass, Mark R."],"dc:date.accessioned":["2018-10-26T19:21:32Z"],"dc:date.available":["2018-10-26T19:21:32Z"],"dc:date.issued":["2018-09"],"dc:description.abstract":["The goal of this study is to determine if a set of heuristics can be used as a decision-making tool to effectively determine what low-scope growth-work needs to be targeted for execution early in the construction cycle of a new naval ship. This study analyzes growth-work that is not incorporated into the base contract with a formal engineering change proposal, but rather a less-formal waterfront change process where the logistics and engineering products are updated after the delivery of the ship. This study shows why some growth-work is significantly more expensive or disruptive to the crew if completed after delivery of the ship. Growth-work is realized during the long construction cycle due to technology changes, lessons learned from previous hulls, fleet requirement changes, and contract requirement gaps. Since not all of the growth-work can be incorporated during the period of performance of the base contract, this study lays out a heuristics-based systems approach to managing low-scope growth-work in new construction shipbuilding. This study shows which heuristics are effective to target growth-work that will drive cost and crew disruption if executed after the delivery of the ship. Finally, this study models this approach using cam DEFinition for Function Modeling (IDEF0) diagrams. These models provide a framework for use by other program offices."],"dc:description.uri":["http://archive.org/details/asystemsapproach1094560405"],"dc:identifier.uri":["https://hdl.handle.net/10945/60405"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:rights":["Copyright is reserved by the copyright owner.","Approved for public release; distribution is unlimited."],"dc:subject.keyword":["shipbuilding","change","growth-work","new construction","IDEF0"],"dc:title":["A SYSTEMS APPROACH TO MANAGING LOW-SCOPE GROWTH-WORK IN NEW CONSTRUCTION SHIPBUILDING"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Civilian, Department of the Navy"],"thesis:degree_discipline":["Systems Engineering Management"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Master of Science in Systems Engineering Management"],"thesis:institution_name":["Naval Postgraduate School"],"thesis:thesis_identifier":["31684"]},"updated_at":"2026-11-19T06:38:38Z"}