{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/7052"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/7052","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Manpower Costs of the Training Wing Five T-6B Transition Plan","abstract":"EXECUTIVE SUMMARY: This project was undertaken at the request of the Deputy Commodore, Training Wing FIVE. In light of the coming transition from the T-34 to T-6 aircraft, the manpower cost from initial preparation through final execution remained uncertain. While most consultation projects involve an analysis and selection of a course of action, this unique project began with a course already determined and attempted only to determine the cost of that course. In order to determine this cost in terms of Instructor Pilots (IPs) lost from production during the transition, an interactive spreadsheet model was constructed and several pools of data were analyzed. A timeline for Instructor Pilot training was constructed based on the planned time to train, then a second timeline was constructed for the training of the Flight Instructor Training Unit (FITU) Instructor Pilots (FIPs) to ensure they would be prepared to qualify new Instructor Pilots in time for the arrival of the first T-6 Student Military Aviators (SMAs). Once this framework was constructed, numerous data values such as aircraft capacity and SMA-to-IP ratios were applied to ensure the answer was both accurate and comprehensive. The findings of this project reveal that, based on the currently planned T-6 training schedule for both SMAs and IPs, Training Wing FIVE will experience a deficit of T-34 Instructor Pilots commencing APR 2008 and concluding APR 2012, reaching a peak deficit of 36 Instructor Pilots at numerous points during that time period.","abstract_html":"EXECUTIVE SUMMARY: This project was undertaken at the request of the Deputy Commodore, Training Wing FIVE. In light of the coming transition from the T-34 to T-6 aircraft, the manpower cost from initial preparation through final execution remained uncertain. While most consultation projects involve an analysis and selection of a course of action, this unique project began with a course already determined and attempted only to determine the cost of that course. In order to determine this cost in terms of Instructor Pilots (IPs) lost from production during the transition, an interactive spreadsheet model was constructed and several pools of data were analyzed. A timeline for Instructor Pilot training was constructed based on the planned time to train, then a second timeline was constructed for the training of the Flight Instructor Training Unit (FITU) Instructor Pilots (FIPs) to ensure they would be prepared to qualify new Instructor Pilots in time for the arrival of the first T-6 Student Military Aviators (SMAs). Once this framework was constructed, numerous data values such as aircraft capacity and SMA-to-IP ratios were applied to ensure the answer was both accurate and comprehensive. The findings of this project reveal that, based on the currently planned T-6 training schedule for both SMAs and IPs, Training Wing FIVE will experience a deficit of T-34 Instructor Pilots commencing APR 2008 and concluding APR 2012, reaching a peak deficit of 36 Instructor Pilots at numerous points during that time period.","abstract_has_math":false,"creators":["Orgain, Marc","Chastain, Marshall","Patterson, Luke"],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"Executive Master of Business Administration","degree_level":"Masters","degree_discipline":"Executive Master of Business Administration","degree_department":null,"school":null,"contributors":[],"advisors":["Crawford, Alice"],"committee_chairs":[],"committee_members":[],"year":2008,"date_issued":"2008-03-12","date_published":"2008-03-12","updated_at":"2026-11-19T06:41:15Z","subjects":[],"languages":[],"rights":[],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/7052","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/7052","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F7052","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Crawford, Alice"]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Graduate School of Business & Public Policy (GSBPP)"]},{"key":"dc:creator","label":"Author","values":["Orgain, Marc","Chastain, Marshall","Patterson, Luke"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-06-27T15:04:07Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-06-27T15:04:07Z"]},{"key":"dc:date.issued","label":"Date","values":["2008-03-12"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:relation.ispartofseries","label":"Dc Relation Ispartofseries","values":["Executive Master of Business Administration (EMBA) Project Final Reports"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["689b9e9a-8dae-40b6-b61b-bc2662e12411"]},{"key":"dc:relation.seriesentity","label":"Dc Relation Seriesentity","values":["bcb50f2b-7b68-41f4-86fb-97ad721ed8f2"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Executive Master of Business Administration"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Executive Master of Business Administration"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/7052"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description","label":"Description","values":["EMBA Project Report"]},{"key":"dc:description.abstract","label":"Abstract","values":["EXECUTIVE SUMMARY: This project was undertaken at the request of the Deputy Commodore, Training Wing FIVE. In light of the coming transition from the T-34 to T-6 aircraft, the manpower cost from initial preparation through final execution remained uncertain. While most consultation projects involve an analysis and selection of a course of action, this unique project began with a course already determined and attempted only to determine the cost of that course. In order to determine this cost in terms of Instructor Pilots (IPs) lost from production during the transition, an interactive spreadsheet model was constructed and several pools of data were analyzed. A timeline for Instructor Pilot training was constructed based on the planned time to train, then a second timeline was constructed for the training of the Flight Instructor Training Unit (FITU) Instructor Pilots (FIPs) to ensure they would be prepared to qualify new Instructor Pilots in time for the arrival of the first T-6 Student Military Aviators (SMAs). Once this framework was constructed, numerous data values such as aircraft capacity and SMA-to-IP ratios were applied to ensure the answer was both accurate and comprehensive. The findings of this project reveal that, based on the currently planned T-6 training schedule for both SMAs and IPs, Training Wing FIVE will experience a deficit of T-34 Instructor Pilots commencing APR 2008 and concluding APR 2012, reaching a peak deficit of 36 Instructor Pilots at numerous points during that time period."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/manpowercostsoft109457052"]},{"key":"dc:title","label":"Title","values":["Manpower Costs of the Training Wing Five T-6B Transition Plan"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]}]}],"canonical_facts":{"dc:contributor.advisor":["Crawford, Alice"],"dc:contributor.other":["Graduate School of Business & Public Policy (GSBPP)"],"dc:creator":["Orgain, Marc","Chastain, Marshall","Patterson, Luke"],"dc:date.accessioned":["2012-06-27T15:04:07Z"],"dc:date.available":["2012-06-27T15:04:07Z"],"dc:date.issued":["2008-03-12"],"dc:description":["EMBA Project Report"],"dc:description.abstract":["EXECUTIVE SUMMARY: This project was undertaken at the request of the Deputy Commodore, Training Wing FIVE. In light of the coming transition from the T-34 to T-6 aircraft, the manpower cost from initial preparation through final execution remained uncertain. While most consultation projects involve an analysis and selection of a course of action, this unique project began with a course already determined and attempted only to determine the cost of that course. In order to determine this cost in terms of Instructor Pilots (IPs) lost from production during the transition, an interactive spreadsheet model was constructed and several pools of data were analyzed. A timeline for Instructor Pilot training was constructed based on the planned time to train, then a second timeline was constructed for the training of the Flight Instructor Training Unit (FITU) Instructor Pilots (FIPs) to ensure they would be prepared to qualify new Instructor Pilots in time for the arrival of the first T-6 Student Military Aviators (SMAs). Once this framework was constructed, numerous data values such as aircraft capacity and SMA-to-IP ratios were applied to ensure the answer was both accurate and comprehensive. The findings of this project reveal that, based on the currently planned T-6 training schedule for both SMAs and IPs, Training Wing FIVE will experience a deficit of T-34 Instructor Pilots commencing APR 2008 and concluding APR 2012, reaching a peak deficit of 36 Instructor Pilots at numerous points during that time period."],"dc:description.uri":["http://archive.org/details/manpowercostsoft109457052"],"dc:identifier.uri":["https://hdl.handle.net/10945/7052"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:relation.ispartofseries":["Executive Master of Business Administration (EMBA) Project Final Reports"],"dc:relation.orgunit":["689b9e9a-8dae-40b6-b61b-bc2662e12411"],"dc:relation.seriesentity":["bcb50f2b-7b68-41f4-86fb-97ad721ed8f2"],"dc:title":["Manpower Costs of the Training Wing Five T-6B Transition Plan"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"thesis:degree_discipline":["Executive Master of Business Administration"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Executive Master of Business Administration"],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-19T06:41:15Z"}