{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/72594"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/72594","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"SYSTEMIC DELAY IN DEFENSE CONTRACTING: A CASE STUDY OF THE DEFENSE CONTRACT MANAGEMENT AGENCY’S CONTRACT CLOSEOUT BACKLOG FROM FY2015 TO FY2020","abstract":"In this study, we analyze the Defense Contract Management Agency’s (DCMA) actions, from FY2015 to FY2020, to reduce a backlog of more than 72,000 overage flexibly priced contracts (FPC) that awaited administrative closeout. By working directly with the Defense Contract Audit Agency (DCAA) to align organizational priorities and deconflict internal procedures, the DCMA identified systemic delays in its closeout process and reduced the FPC backlog. Using historical data generated during the DCMA’s Material Weakness Initiative (MWI), our analysis focuses on the DCMA’s overall effectiveness in closing FPCs. The goal of our research is to provide defense contracting activities a roadmap to prevent future backlogs and reduce current backlogs. One main takeaway is the importance of aligning organizational priorities and deconflicting internal procedures between interconnected contract administration participants to close FPCs on time and efficiently. Three primary recommendations that stem from our findings are that defense contracting organizations should: (1) set organizational FPC closeout goals and use metrics to track closeout progress, (2) when multiple entities are involved, establish a process to track queued FPCs awaiting administrative action by all organizations, and (3) consider adding contract clauses that enable administrative contracting officers to efficiently close FPCs during the post-award phase. Additional recommendations for further research are also provided.","abstract_html":"In this study, we analyze the Defense Contract Management Agency’s (DCMA) actions, from FY2015 to FY2020, to reduce a backlog of more than 72,000 overage flexibly priced contracts (FPC) that awaited administrative closeout. By working directly with the Defense Contract Audit Agency (DCAA) to align organizational priorities and deconflict internal procedures, the DCMA identified systemic delays in its closeout process and reduced the FPC backlog. Using historical data generated during the DCMA’s Material Weakness Initiative (MWI), our analysis focuses on the DCMA’s overall effectiveness in closing FPCs. The goal of our research is to provide defense contracting activities a roadmap to prevent future backlogs and reduce current backlogs. One main takeaway is the importance of aligning organizational priorities and deconflicting internal procedures between interconnected contract administration participants to close FPCs on time and efficiently. Three primary recommendations that stem from our findings are that defense contracting organizations should: (1) set organizational FPC closeout goals and use metrics to track closeout progress, (2) when multiple entities are involved, establish a process to track queued FPCs awaiting administrative action by all organizations, and (3) consider adding contract clauses that enable administrative contracting officers to efficiently close FPCs during the post-award phase. Additional recommendations for further research are also provided.","abstract_has_math":false,"creators":["Rawls, Darius D.","Stone, Arthur L., Jr.","Woods, Justin B."],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"Master of Business Administration","degree_level":"Masters","degree_discipline":"Master of Business Administration","degree_department":"Department of Defense Management (DDM)","school":null,"contributors":[],"advisors":["Schwartz, Brett M.","Tick, Simona L."],"committee_chairs":[],"committee_members":[],"year":2023,"date_issued":"2023-12","date_published":"2023-12","updated_at":"2026-11-26T00:14:38Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release. Distribution is unlimited."],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier.programcode","label":"Dc Identifier Programcode","values":["815, Defense Contract Management"],"render_values":[{"text":"815, Defense Contract Management","href":null,"code":true}]},{"key":"thesis:thesis_identifier","label":"Thesis Thesis Identifier","values":["39674"],"render_values":[{"text":"39674","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/72594","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/72594","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F72594","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F72594","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Schwartz, Brett M.","Tick, Simona L."]},{"key":"dc:contributor.department","label":"Department","values":["Department of Defense Management (DDM)"]},{"key":"dc:creator","label":"Author","values":["Rawls, Darius D.","Stone, Arthur L., Jr.","Woods, Justin B."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2024-02-19T22:57:00Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2024-02-19T22:57:00Z"]},{"key":"dc:date.issued","label":"Date","values":["2023-12"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:relation.ispartofseries","label":"Dc Relation Ispartofseries","values":["Master of Business Administration (MBA) Professional Reports"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["b8b0094c-45b5-4a6a-8813-f61a5dec4f2a"]},{"key":"dc:relation.seriesentity","label":"Dc Relation Seriesentity","values":["e0c365f0-ed04-4d27-bded-11759168d050"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Master of Business Administration"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Business Administration"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]},{"key":"thesis:thesis_identifier","label":"Thesis Thesis Identifier","values":["39674"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["audit backlog","class deviation","closeout backlog","contract closeout","Defense Contract Audit Agency","Defense Contract Management Agency","flexibly priced contract","incurred cost proposal","internal procedures","National Defense Authorization Act","organizational priorities","quick closeout procedures","systemic delay."]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release. Distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.programcode","label":"Dc Identifier Programcode","values":["815, Defense Contract Management"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/72594"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["In this study, we analyze the Defense Contract Management Agency’s (DCMA) actions, from FY2015 to FY2020, to reduce a backlog of more than 72,000 overage flexibly priced contracts (FPC) that awaited administrative closeout. By working directly with the Defense Contract Audit Agency (DCAA) to align organizational priorities and deconflict internal procedures, the DCMA identified systemic delays in its closeout process and reduced the FPC backlog. Using historical data generated during the DCMA’s Material Weakness Initiative (MWI), our analysis focuses on the DCMA’s overall effectiveness in closing FPCs. The goal of our research is to provide defense contracting activities a roadmap to prevent future backlogs and reduce current backlogs. One main takeaway is the importance of aligning organizational priorities and deconflicting internal procedures between interconnected contract administration participants to close FPCs on time and efficiently. Three primary recommendations that stem from our findings are that defense contracting organizations should: (1) set organizational FPC closeout goals and use metrics to track closeout progress, (2) when multiple entities are involved, establish a process to track queued FPCs awaiting administrative action by all organizations, and (3) consider adding contract clauses that enable administrative contracting officers to efficiently close FPCs during the post-award phase. Additional recommendations for further research are also provided."]},{"key":"dc:title","label":"Title","values":["SYSTEMIC DELAY IN DEFENSE CONTRACTING: A CASE STUDY OF THE DEFENSE CONTRACT MANAGEMENT AGENCY’S CONTRACT CLOSEOUT BACKLOG FROM FY2015 TO FY2020"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Lieutenant Commander, United States Navy"]}]}],"canonical_facts":{"dc:contributor.advisor":["Schwartz, Brett M.","Tick, Simona L."],"dc:contributor.department":["Department of Defense Management (DDM)"],"dc:creator":["Rawls, Darius D.","Stone, Arthur L., Jr.","Woods, Justin B."],"dc:date.accessioned":["2024-02-19T22:57:00Z"],"dc:date.available":["2024-02-19T22:57:00Z"],"dc:date.issued":["2023-12"],"dc:description.abstract":["In this study, we analyze the Defense Contract Management Agency’s (DCMA) actions, from FY2015 to FY2020, to reduce a backlog of more than 72,000 overage flexibly priced contracts (FPC) that awaited administrative closeout. By working directly with the Defense Contract Audit Agency (DCAA) to align organizational priorities and deconflict internal procedures, the DCMA identified systemic delays in its closeout process and reduced the FPC backlog. Using historical data generated during the DCMA’s Material Weakness Initiative (MWI), our analysis focuses on the DCMA’s overall effectiveness in closing FPCs. The goal of our research is to provide defense contracting activities a roadmap to prevent future backlogs and reduce current backlogs. One main takeaway is the importance of aligning organizational priorities and deconflicting internal procedures between interconnected contract administration participants to close FPCs on time and efficiently. Three primary recommendations that stem from our findings are that defense contracting organizations should: (1) set organizational FPC closeout goals and use metrics to track closeout progress, (2) when multiple entities are involved, establish a process to track queued FPCs awaiting administrative action by all organizations, and (3) consider adding contract clauses that enable administrative contracting officers to efficiently close FPCs during the post-award phase. Additional recommendations for further research are also provided."],"dc:identifier.programcode":["815, Defense Contract Management"],"dc:identifier.uri":["https://hdl.handle.net/10945/72594"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:relation.ispartofseries":["Master of Business Administration (MBA) Professional Reports"],"dc:relation.orgunit":["b8b0094c-45b5-4a6a-8813-f61a5dec4f2a"],"dc:relation.seriesentity":["e0c365f0-ed04-4d27-bded-11759168d050"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release. Distribution is unlimited."],"dc:subject.keyword":["audit backlog","class deviation","closeout backlog","contract closeout","Defense Contract Audit Agency","Defense Contract Management Agency","flexibly priced contract","incurred cost proposal","internal procedures","National Defense Authorization Act","organizational priorities","quick closeout procedures","systemic delay."],"dc:title":["SYSTEMIC DELAY IN DEFENSE CONTRACTING: A CASE STUDY OF THE DEFENSE CONTRACT MANAGEMENT AGENCY’S CONTRACT CLOSEOUT BACKLOG FROM FY2015 TO FY2020"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Lieutenant Commander, United States Navy"],"thesis:degree_discipline":["Master of Business Administration"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Master of Business Administration"],"thesis:institution_name":["Naval Postgraduate School"],"thesis:thesis_identifier":["39674"]},"updated_at":"2026-11-26T00:14:38Z"}