{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/7315"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/7315","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"A Preliminary Investigation into CNO Availability Schedule Overruns","abstract":"A naval vessels availability is a scheduled period of time, normally conducted in a shipyard, to perform maintenance on and modernization of the vessel and its systems. The four public naval shipyards are continually challenged to complete depot-level, CNO availabilities on schedule. A naval vessels late return to the fleet results in the decrease in operational readiness due to the reduced number of operational days available for these vessels. Subject-matter experts hypothesize that factors such as inadequate planning for resources, quantity of overtime, and quantity of work stoppages experienced contribute to availability lateness. Data collected by the shipyards are analyzed to investigate factors influencing late completion of availabilities. The analysis suggests that carrier availabilities tend to finish on schedule more often than submarine availabilities, timely availabilities tend to have a higher cost performance ratio than late availabilities, late availabilities tend to charge less for work per month in man-days than the budgeted amount of planned work, and availabilities that finish on schedule tend to have fewer work stoppages prior to start of the availability than the later completing ones.","abstract_html":"A naval vessels availability is a scheduled period of time, normally conducted in a shipyard, to perform maintenance on and modernization of the vessel and its systems. The four public naval shipyards are continually challenged to complete depot-level, CNO availabilities on schedule. A naval vessels late return to the fleet results in the decrease in operational readiness due to the reduced number of operational days available for these vessels. Subject-matter experts hypothesize that factors such as inadequate planning for resources, quantity of overtime, and quantity of work stoppages experienced contribute to availability lateness. Data collected by the shipyards are analyzed to investigate factors influencing late completion of availabilities. The analysis suggests that carrier availabilities tend to finish on schedule more often than submarine availabilities, timely availabilities tend to have a higher cost performance ratio than late availabilities, late availabilities tend to charge less for work per month in man-days than the budgeted amount of planned work, and availabilities that finish on schedule tend to have fewer work stoppages prior to start of the availability than the later completing ones.","abstract_has_math":false,"creators":["Caprio, Joseph L.","Leszczynski, Daniel"],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"Master of Science In Systems Engineering","degree_level":"Masters","degree_discipline":"Systems Engineering","degree_department":"Systems Engineering (SE)","school":null,"contributors":[],"advisors":["Whitcomb, Clifford","Jacobs, Patricia"],"committee_chairs":[],"committee_members":[],"year":2012,"date_issued":"2012-06","date_published":"2012-06","updated_at":"2026-11-19T06:42:35Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Distribution Statement A. Approved for public release: Distribution is unlimited."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/7315","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/7315","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","download_url":null,"download_label":null,"download_source":null,"access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F7315","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Whitcomb, Clifford","Jacobs, Patricia"]},{"key":"dc:contributor.department","label":"Department","values":["Systems Engineering (SE)"]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Graduate School of Engineering and Applied Science (GSEAS)"]},{"key":"dc:creator","label":"Author","values":["Caprio, Joseph L.","Leszczynski, Daniel"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-07-30T23:15:44Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-07-30T23:15:44Z"]},{"key":"dc:date.issued","label":"Date","values":["2012-06"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:relation.ispartofseries","label":"Dc Relation Ispartofseries","values":["NPS Outstanding Theses and Dissertations"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["54cbc27e-a8d1-42ce-b932-4ae5aa4d2386","73c095de-fa3b-4d63-8300-9b6aee5b4d62"]},{"key":"dc:relation.seriesentity","label":"Dc Relation Seriesentity","values":["c5e66392-520c-4aaf-9b4f-370ce82b601f"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Systems Engineering"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science In Systems Engineering"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["CNO Availability","Naval Shipyards","Schedule Overrun","Availability Lateness","Cost Performance","Budgeted Quantity Work Performed","Actual Quantity Work Performed","Availability Delay","Work Stoppages"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Distribution Statement A. Approved for public release: Distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/7315"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["A naval vessels availability is a scheduled period of time, normally conducted in a shipyard, to perform maintenance on and modernization of the vessel and its systems. The four public naval shipyards are continually challenged to complete depot-level, CNO availabilities on schedule. A naval vessels late return to the fleet results in the decrease in operational readiness due to the reduced number of operational days available for these vessels. Subject-matter experts hypothesize that factors such as inadequate planning for resources, quantity of overtime, and quantity of work stoppages experienced contribute to availability lateness. Data collected by the shipyards are analyzed to investigate factors influencing late completion of availabilities. The analysis suggests that carrier availabilities tend to finish on schedule more often than submarine availabilities, timely availabilities tend to have a higher cost performance ratio than late availabilities, late availabilities tend to charge less for work per month in man-days than the budgeted amount of planned work, and availabilities that finish on schedule tend to have fewer work stoppages prior to start of the availability than the later completing ones."]},{"key":"dc:description.award","label":"Dc Description Award","values":["Outstanding Thesis"]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/apreliminaryinve109457315"]},{"key":"dc:format.extent","label":"Dc Format Extent","values":["141 p."]},{"key":"dc:title","label":"Title","values":["A Preliminary Investigation into CNO Availability Schedule Overruns"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Lieutenant, United States Navy","Lieutenant Junior Grade, United States Navy"]}]}],"canonical_facts":{"dc:contributor.advisor":["Whitcomb, Clifford","Jacobs, Patricia"],"dc:contributor.department":["Systems Engineering (SE)"],"dc:contributor.other":["Graduate School of Engineering and Applied Science (GSEAS)"],"dc:creator":["Caprio, Joseph L.","Leszczynski, Daniel"],"dc:date.accessioned":["2012-07-30T23:15:44Z"],"dc:date.available":["2012-07-30T23:15:44Z"],"dc:date.issued":["2012-06"],"dc:description.abstract":["A naval vessels availability is a scheduled period of time, normally conducted in a shipyard, to perform maintenance on and modernization of the vessel and its systems. The four public naval shipyards are continually challenged to complete depot-level, CNO availabilities on schedule. A naval vessels late return to the fleet results in the decrease in operational readiness due to the reduced number of operational days available for these vessels. Subject-matter experts hypothesize that factors such as inadequate planning for resources, quantity of overtime, and quantity of work stoppages experienced contribute to availability lateness. Data collected by the shipyards are analyzed to investigate factors influencing late completion of availabilities. The analysis suggests that carrier availabilities tend to finish on schedule more often than submarine availabilities, timely availabilities tend to have a higher cost performance ratio than late availabilities, late availabilities tend to charge less for work per month in man-days than the budgeted amount of planned work, and availabilities that finish on schedule tend to have fewer work stoppages prior to start of the availability than the later completing ones."],"dc:description.award":["Outstanding Thesis"],"dc:description.uri":["http://archive.org/details/apreliminaryinve109457315"],"dc:format.extent":["141 p."],"dc:identifier.uri":["https://hdl.handle.net/10945/7315"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:relation.ispartofseries":["NPS Outstanding Theses and Dissertations"],"dc:relation.orgunit":["54cbc27e-a8d1-42ce-b932-4ae5aa4d2386","73c095de-fa3b-4d63-8300-9b6aee5b4d62"],"dc:relation.seriesentity":["c5e66392-520c-4aaf-9b4f-370ce82b601f"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Distribution Statement A. Approved for public release: Distribution is unlimited."],"dc:subject.keyword":["CNO Availability","Naval Shipyards","Schedule Overrun","Availability Lateness","Cost Performance","Budgeted Quantity Work Performed","Actual Quantity Work Performed","Availability Delay","Work Stoppages"],"dc:title":["A Preliminary Investigation into CNO Availability Schedule Overruns"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Lieutenant, United States Navy","Lieutenant Junior Grade, United States Navy"],"thesis:degree_discipline":["Systems Engineering"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Master of Science In Systems Engineering"],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-19T06:42:35Z"}