{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/74704"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/74704","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"OPTIMIZING ROCKET MOTOR SCHEDULES","abstract":"This research develops the rocket inspection scheduling optimization model (RISOM), a new approach to scheduling rocket motors for low-temperature conditioning and x-ray inspection at Naval Surface Warfare Center Indian Head Division. RISOM seeks to maximize the value of motors that complete inspection, while also minimizing their lateness. RISOM is tested using simulated data based on realistic demand projections. Results show that current facility and labor capacity can meet 90% of the simulated demand, but the range of lateness is undesirable. Increasing the x-ray facilities by 50% allows all motors to be scheduled and reduces lateness to a few days. Adding one eight-hour shift reduces lateness to within a month. Combining other labor and facility additions, we reduce lateness to about one day for 90% of the motors.","abstract_html":"This research develops the rocket inspection scheduling optimization model (RISOM), a new approach to scheduling rocket motors for low-temperature conditioning and x-ray inspection at Naval Surface Warfare Center Indian Head Division. RISOM seeks to maximize the value of motors that complete inspection, while also minimizing their lateness. RISOM is tested using simulated data based on realistic demand projections. Results show that current facility and labor capacity can meet 90% of the simulated demand, but the range of lateness is undesirable. Increasing the x-ray facilities by 50% allows all motors to be scheduled and reduces lateness to a few days. Adding one eight-hour shift reduces lateness to within a month. Combining other labor and facility additions, we reduce lateness to about one day for 90% of the motors.","abstract_has_math":false,"creators":["Lancaster, Ezekiel B."],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"Master of Science in Systems Engineering Management","degree_level":"Masters","degree_discipline":"Systems Engineering Management","degree_department":"Systems Engineering (SE)","school":null,"contributors":[],"advisors":["Salmeron-Medrano, Javier"],"committee_chairs":[],"committee_members":["Emmons, Nelson L."],"year":2025,"date_issued":"2025-09","date_published":"2025-09","updated_at":"2026-11-19T06:43:09Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Distribution Statement A. Approved for public release: Distribution is unlimited."],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier.programcode","label":"Dc Identifier Programcode","values":["721, Systems Engineering Management-PD21 (DL)"],"render_values":[{"text":"721, Systems Engineering Management-PD21 (DL)","href":null,"code":true}]},{"key":"thesis:thesis_identifier","label":"Thesis Thesis Identifier","values":["40977"],"render_values":[{"text":"40977","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/74704","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/74704","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F74704","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Salmeron-Medrano, Javier"]},{"key":"dc:contributor.committeemember","label":"Committee Member","values":["Emmons, Nelson L."]},{"key":"dc:contributor.department","label":"Department","values":["Systems Engineering (SE)"]},{"key":"dc:creator","label":"Author","values":["Lancaster, Ezekiel B."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2026-03-05T17:49:55Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2026-03-05T17:49:55Z"]},{"key":"dc:date.issued","label":"Date","values":["2025-09"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["73c095de-fa3b-4d63-8300-9b6aee5b4d62"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Systems Engineering Management"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science in Systems Engineering Management"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]},{"key":"thesis:thesis_identifier","label":"Thesis Thesis Identifier","values":["40977"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["optimization","manufacturing","inspection","x-ray","mixed integer program","job-shop problem","scheduling","low-temperature conditioning","lateness","capacity","job shop","rocket inspection scheduling optimization model","RISOM"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Distribution Statement A. Approved for public release: Distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.programcode","label":"Dc Identifier Programcode","values":["721, Systems Engineering Management-PD21 (DL)"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/74704"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["This research develops the rocket inspection scheduling optimization model (RISOM), a new approach to scheduling rocket motors for low-temperature conditioning and x-ray inspection at Naval Surface Warfare Center Indian Head Division. RISOM seeks to maximize the value of motors that complete inspection, while also minimizing their lateness. RISOM is tested using simulated data based on realistic demand projections. Results show that current facility and labor capacity can meet 90% of the simulated demand, but the range of lateness is undesirable. Increasing the x-ray facilities by 50% allows all motors to be scheduled and reduces lateness to a few days. Adding one eight-hour shift reduces lateness to within a month. Combining other labor and facility additions, we reduce lateness to about one day for 90% of the motors."]},{"key":"dc:description.sponsorship","label":"Dc Description Sponsorship","values":["NSWC Indian Head Division"]},{"key":"dc:title","label":"Title","values":["OPTIMIZING ROCKET MOTOR SCHEDULES"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Civilian, Department of the Navy"]}]}],"canonical_facts":{"dc:contributor.advisor":["Salmeron-Medrano, Javier"],"dc:contributor.committeemember":["Emmons, Nelson L."],"dc:contributor.department":["Systems Engineering (SE)"],"dc:creator":["Lancaster, Ezekiel B."],"dc:date.accessioned":["2026-03-05T17:49:55Z"],"dc:date.available":["2026-03-05T17:49:55Z"],"dc:date.issued":["2025-09"],"dc:description.abstract":["This research develops the rocket inspection scheduling optimization model (RISOM), a new approach to scheduling rocket motors for low-temperature conditioning and x-ray inspection at Naval Surface Warfare Center Indian Head Division. RISOM seeks to maximize the value of motors that complete inspection, while also minimizing their lateness. RISOM is tested using simulated data based on realistic demand projections. Results show that current facility and labor capacity can meet 90% of the simulated demand, but the range of lateness is undesirable. Increasing the x-ray facilities by 50% allows all motors to be scheduled and reduces lateness to a few days. Adding one eight-hour shift reduces lateness to within a month. Combining other labor and facility additions, we reduce lateness to about one day for 90% of the motors."],"dc:description.sponsorship":["NSWC Indian Head Division"],"dc:identifier.programcode":["721, Systems Engineering Management-PD21 (DL)"],"dc:identifier.uri":["https://hdl.handle.net/10945/74704"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:relation.orgunit":["73c095de-fa3b-4d63-8300-9b6aee5b4d62"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Distribution Statement A. Approved for public release: Distribution is unlimited."],"dc:subject.keyword":["optimization","manufacturing","inspection","x-ray","mixed integer program","job-shop problem","scheduling","low-temperature conditioning","lateness","capacity","job shop","rocket inspection scheduling optimization model","RISOM"],"dc:title":["OPTIMIZING ROCKET MOTOR SCHEDULES"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Civilian, Department of the Navy"],"thesis:degree_discipline":["Systems Engineering Management"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Master of Science in Systems Engineering Management"],"thesis:institution_name":["Naval Postgraduate School"],"thesis:thesis_identifier":["40977"]},"updated_at":"2026-11-19T06:43:09Z"}