{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/75651"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/75651","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"CRUISER MODERNIZATION: AN ORGANIZATIONAL KNOWLEDGE CAPTURE","abstract":"This case study examines the U.S. Navy’s cruiser modernization effort and evaluates how limited technical oversight, fragmented organizational authority, compressed planning timelines, contractor sequencing conflicts, and insufficient knowledge transfer contributed to cost growth, schedule delay, rework, and delivery of non-operational capability. The background is the Navy’s cruiser modernization effort where compressed schedules, limited shipyard capacity, firm-fixed-price contracting pressures, and fragmented authority complicated execution. Using a qualitative case study approach, the research examined planning, installation sequencing, oversight relationships, contractor interaction, technical discrepancies, and system operational verification test readiness. Results show knowledgeable personnel existed in the project team, yet organizational structures often prevented that knowledge from shaping execution. Sequencing conflicts, weak surveillance, dismissed technical guidance, poor continuity, and adversarial contractor relationships contributed to rework, schedule delay, cost growth, and non-operational capability. Findings show that modernization output quality depends on people who are trained, heard, and authorized to act. The study recommends initiating competency pathways, stronger Navy technical representative authority, lessons-learned repositories, governance, readiness reviews, quality-based contract incentives, and continuity plans.","abstract_html":"This case study examines the U.S. Navy’s cruiser modernization effort and evaluates how limited technical oversight, fragmented organizational authority, compressed planning timelines, contractor sequencing conflicts, and insufficient knowledge transfer contributed to cost growth, schedule delay, rework, and delivery of non-operational capability. The background is the Navy’s cruiser modernization effort where compressed schedules, limited shipyard capacity, firm-fixed-price contracting pressures, and fragmented authority complicated execution. Using a qualitative case study approach, the research examined planning, installation sequencing, oversight relationships, contractor interaction, technical discrepancies, and system operational verification test readiness. Results show knowledgeable personnel existed in the project team, yet organizational structures often prevented that knowledge from shaping execution. Sequencing conflicts, weak surveillance, dismissed technical guidance, poor continuity, and adversarial contractor relationships contributed to rework, schedule delay, cost growth, and non-operational capability. Findings show that modernization output quality depends on people who are trained, heard, and authorized to act. The study recommends initiating competency pathways, stronger Navy technical representative authority, lessons-learned repositories, governance, readiness reviews, quality-based contract incentives, and continuity plans.","abstract_has_math":false,"creators":["Anhold, Jay D."],"institution":"Monterey, CA; Naval Postgraduate School","degree_name":"Master of Science in Program Management","degree_level":"Masters","degree_discipline":"Program Management","degree_department":"Department of Acquisition, Finance and Manpower (DAFM)","school":null,"contributors":[],"advisors":["Mortlock, Robert F."],"committee_chairs":[],"committee_members":["Dunlap, Jeffrey R."],"year":2026,"date_issued":"2026-06","date_published":"2026-06","updated_at":"2026-11-19T06:43:32Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Distribution Statement A. Approved for public release: Distribution is unlimited."],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier.programcode","label":"Dc Identifier Programcode","values":["836, Acquisition (Program Management) (DL)"],"render_values":[{"text":"836, Acquisition (Program Management) (DL)","href":null,"code":true}]},{"key":"thesis:thesis_identifier","label":"Thesis Thesis Identifier","values":["39400"],"render_values":[{"text":"39400","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/75651","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/75651","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F75651","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F75651","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Mortlock, Robert F."]},{"key":"dc:contributor.committeemember","label":"Committee Member","values":["Dunlap, Jeffrey R."]},{"key":"dc:contributor.department","label":"Department","values":["Department of Acquisition, Finance and Manpower (DAFM)"]},{"key":"dc:creator","label":"Author","values":["Anhold, Jay D."]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2026-09-03T16:56:02Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2026-09-03T16:56:02Z"]},{"key":"dc:date.issued","label":"Date","values":["2026-06"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, CA; Naval Postgraduate School"]},{"key":"dc:relation.ispartofseries","label":"Dc Relation Ispartofseries","values":["Capstone Applied Project Reports"]},{"key":"dc:relation.orgunit","label":"Dc Relation Orgunit","values":["ff28ff54-a1d6-4c99-955a-999e99bd8f6d"]},{"key":"dc:relation.seriesentity","label":"Dc Relation Seriesentity","values":["409d700c-a0df-4ded-8bb7-9da7660ceddb"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Program Management"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science in Program Management"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]},{"key":"thesis:thesis_identifier","label":"Thesis Thesis Identifier","values":["39400"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["knowledge management","continuous learning","knowledge mapping","Aegis Combat System","alteration installation team","anti-submarine warfare","ASW","Aegis Weapon System","guided-missile cruiser","Contract Management Body of Knowledge","combat systems","Defense Acquisition Workforce Improvement Act","Federal Acquisition Regulation","Government Accountability Office","integrated master schedule","incremental selected restricted availability","integrated warfare systems","lead maintenance activity"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Distribution Statement A. Approved for public release: Distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.programcode","label":"Dc Identifier Programcode","values":["836, Acquisition (Program Management) (DL)"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/75651"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["This case study examines the U.S. Navy’s cruiser modernization effort and evaluates how limited technical oversight, fragmented organizational authority, compressed planning timelines, contractor sequencing conflicts, and insufficient knowledge transfer contributed to cost growth, schedule delay, rework, and delivery of non-operational capability. The background is the Navy’s cruiser modernization effort where compressed schedules, limited shipyard capacity, firm-fixed-price contracting pressures, and fragmented authority complicated execution. Using a qualitative case study approach, the research examined planning, installation sequencing, oversight relationships, contractor interaction, technical discrepancies, and system operational verification test readiness. Results show knowledgeable personnel existed in the project team, yet organizational structures often prevented that knowledge from shaping execution. Sequencing conflicts, weak surveillance, dismissed technical guidance, poor continuity, and adversarial contractor relationships contributed to rework, schedule delay, cost growth, and non-operational capability. Findings show that modernization output quality depends on people who are trained, heard, and authorized to act. The study recommends initiating competency pathways, stronger Navy technical representative authority, lessons-learned repositories, governance, readiness reviews, quality-based contract incentives, and continuity plans."]},{"key":"dc:title","label":"Title","values":["CRUISER MODERNIZATION: AN ORGANIZATIONAL KNOWLEDGE CAPTURE"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Civilian, Department of the Navy"]}]}],"canonical_facts":{"dc:contributor.advisor":["Mortlock, Robert F."],"dc:contributor.committeemember":["Dunlap, Jeffrey R."],"dc:contributor.department":["Department of Acquisition, Finance and Manpower (DAFM)"],"dc:creator":["Anhold, Jay D."],"dc:date.accessioned":["2026-09-03T16:56:02Z"],"dc:date.available":["2026-09-03T16:56:02Z"],"dc:date.issued":["2026-06"],"dc:description.abstract":["This case study examines the U.S. Navy’s cruiser modernization effort and evaluates how limited technical oversight, fragmented organizational authority, compressed planning timelines, contractor sequencing conflicts, and insufficient knowledge transfer contributed to cost growth, schedule delay, rework, and delivery of non-operational capability. The background is the Navy’s cruiser modernization effort where compressed schedules, limited shipyard capacity, firm-fixed-price contracting pressures, and fragmented authority complicated execution. Using a qualitative case study approach, the research examined planning, installation sequencing, oversight relationships, contractor interaction, technical discrepancies, and system operational verification test readiness. Results show knowledgeable personnel existed in the project team, yet organizational structures often prevented that knowledge from shaping execution. Sequencing conflicts, weak surveillance, dismissed technical guidance, poor continuity, and adversarial contractor relationships contributed to rework, schedule delay, cost growth, and non-operational capability. Findings show that modernization output quality depends on people who are trained, heard, and authorized to act. The study recommends initiating competency pathways, stronger Navy technical representative authority, lessons-learned repositories, governance, readiness reviews, quality-based contract incentives, and continuity plans."],"dc:identifier.programcode":["836, Acquisition (Program Management) (DL)"],"dc:identifier.uri":["https://hdl.handle.net/10945/75651"],"dc:publisher":["Monterey, CA; Naval Postgraduate School"],"dc:relation.ispartofseries":["Capstone Applied Project Reports"],"dc:relation.orgunit":["ff28ff54-a1d6-4c99-955a-999e99bd8f6d"],"dc:relation.seriesentity":["409d700c-a0df-4ded-8bb7-9da7660ceddb"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Distribution Statement A. Approved for public release: Distribution is unlimited."],"dc:subject.keyword":["knowledge management","continuous learning","knowledge mapping","Aegis Combat System","alteration installation team","anti-submarine warfare","ASW","Aegis Weapon System","guided-missile cruiser","Contract Management Body of Knowledge","combat systems","Defense Acquisition Workforce Improvement Act","Federal Acquisition Regulation","Government Accountability Office","integrated master schedule","incremental selected restricted availability","integrated warfare systems","lead maintenance activity"],"dc:title":["CRUISER MODERNIZATION: AN ORGANIZATIONAL KNOWLEDGE CAPTURE"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Civilian, Department of the Navy"],"thesis:degree_discipline":["Program Management"],"thesis:degree_level":["Masters"],"thesis:degree_name":["Master of Science in Program Management"],"thesis:institution_name":["Naval Postgraduate School"],"thesis:thesis_identifier":["39400"]},"updated_at":"2026-11-19T06:43:32Z"}