{"id":{"repo_id":"nps","oai_identifier":"oai:calhoun.nps.edu:10945/7860"},"canonical_url":"https://search.ndltd.org/etd/nps/oai:calhoun.nps.edu:10945/7860","repository":{"repo_id":"nps","name":"Naval Postgraduate School","base_url":"https://calhoun.nps.edu/server/oai/request"},"display":{"title":"Affect of contractor's estimating system deficiencies and disapprovals on DoD procuring contracting officers","abstract":"Contractor estimating systems that produce reliable proposals are a key safeguard for the Government to obtain fair and reasonable contract prices for goods and services. Government Administrative Contracting Officers (ACO), with the help of the Defense Contract Audit Agency (DCAA), are responsible for determining the adequacy of contractor's estimating systems. If a DCAA audit finds estimating systems deficiencies, the ACO may take several actions including disapproving the contractor's system, in part or in whole. The process of formal disapproval and deficiencies resolution is a series of contractor written responses, corrective action plans and ACO evaluations. This process can take years before a final determination is made. This thesis will focus on how the Procuring Contracting Officer (PCO) obtains the information about deficiencies or disapproval and what actions he/she takes to insure the Government is receiving a fair and reasonable price for the goods and services it buys.","abstract_html":"Contractor estimating systems that produce reliable proposals are a key safeguard for the Government to obtain fair and reasonable contract prices for goods and services. Government Administrative Contracting Officers (ACO), with the help of the Defense Contract Audit Agency (DCAA), are responsible for determining the adequacy of contractor&#x27;s estimating systems. If a DCAA audit finds estimating systems deficiencies, the ACO may take several actions including disapproving the contractor&#x27;s system, in part or in whole. The process of formal disapproval and deficiencies resolution is a series of contractor written responses, corrective action plans and ACO evaluations. This process can take years before a final determination is made. This thesis will focus on how the Procuring Contracting Officer (PCO) obtains the information about deficiencies or disapproval and what actions he/she takes to insure the Government is receiving a fair and reasonable price for the goods and services it buys.","abstract_has_math":false,"creators":["Crow, Dwin Charles"],"institution":"Monterey, California. Naval Postgraduate School","degree_name":"M.S. in Contract Management","degree_level":"Masters","degree_discipline":"Contract Management","degree_department":"Department of Systems Management","school":null,"contributors":[],"advisors":["Shockley, Danny A.","Lamm, David V."],"committee_chairs":[],"committee_members":[],"year":1996,"date_issued":"1996-12","date_published":"1996-12","updated_at":"2026-11-21T23:36:05Z","subjects":[],"languages":[],"rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://hdl.handle.net/10945/7860","outbound_label":"Handle","outbound_source":"dc:identifier.uri","record_url":"https://hdl.handle.net/10945/7860","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Anps%3Aoai%3Acalhoun.nps.edu%3A10945%2F7860","prefix":"oai_dc"},"source_record":{"url":"https://calhoun.nps.edu/server/oai/request?verb=GetRecord&metadataPrefix=dim&identifier=oai%3Acalhoun.nps.edu%3A10945%2F7860","prefix":"dim"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Shockley, Danny A.","Lamm, David V."]},{"key":"dc:contributor.department","label":"Department","values":["Department of Systems Management"]},{"key":"dc:contributor.other","label":"Dc Contributor Other","values":["Naval Postgraduate School"]},{"key":"dc:creator","label":"Author","values":["Crow, Dwin Charles"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["December 1996"]},{"key":"dc:date.accessioned","label":"Dc Date Accessioned","values":["2012-08-09T19:16:55Z"]},{"key":"dc:date.available","label":"Dc Date Available","values":["2012-08-09T19:16:55Z"]},{"key":"dc:date.issued","label":"Date","values":["1996-12"]},{"key":"dc:publisher","label":"Institution","values":["Monterey, California. Naval Postgraduate School"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Contract Management"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["M.S. in Contract Management"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["Naval Postgraduate School"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject.keyword","label":"Dc Subject Keyword","values":["Cost estimating systems","Procuring contracting officer","Estimating"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://hdl.handle.net/10945/7860"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["Contractor estimating systems that produce reliable proposals are a key safeguard for the Government to obtain fair and reasonable contract prices for goods and services. Government Administrative Contracting Officers (ACO), with the help of the Defense Contract Audit Agency (DCAA), are responsible for determining the adequacy of contractor's estimating systems. If a DCAA audit finds estimating systems deficiencies, the ACO may take several actions including disapproving the contractor's system, in part or in whole. The process of formal disapproval and deficiencies resolution is a series of contractor written responses, corrective action plans and ACO evaluations. This process can take years before a final determination is made. This thesis will focus on how the Procuring Contracting Officer (PCO) obtains the information about deficiencies or disapproval and what actions he/she takes to insure the Government is receiving a fair and reasonable price for the goods and services it buys."]},{"key":"dc:description.uri","label":"Dc Description URI","values":["http://archive.org/details/affectofcontract109457860"]},{"key":"dc:format.extent","label":"Dc Format Extent","values":["ix, 95 p."]},{"key":"dc:title","label":"Title","values":["Affect of contractor's estimating system deficiencies and disapprovals on DoD procuring contracting officers"]},{"key":"dspace:entity.type","label":"Dspace Entity Type","values":["Publication"]},{"key":"local:contributor.affiliation","label":"Local Contributor Affiliation","values":["Lieutenant Commander, United States Navy"]}]}],"canonical_facts":{"dc:contributor.advisor":["Shockley, Danny A.","Lamm, David V."],"dc:contributor.department":["Department of Systems Management"],"dc:contributor.other":["Naval Postgraduate School"],"dc:creator":["Crow, Dwin Charles"],"dc:date":["December 1996"],"dc:date.accessioned":["2012-08-09T19:16:55Z"],"dc:date.available":["2012-08-09T19:16:55Z"],"dc:date.issued":["1996-12"],"dc:description.abstract":["Contractor estimating systems that produce reliable proposals are a key safeguard for the Government to obtain fair and reasonable contract prices for goods and services. Government Administrative Contracting Officers (ACO), with the help of the Defense Contract Audit Agency (DCAA), are responsible for determining the adequacy of contractor's estimating systems. If a DCAA audit finds estimating systems deficiencies, the ACO may take several actions including disapproving the contractor's system, in part or in whole. The process of formal disapproval and deficiencies resolution is a series of contractor written responses, corrective action plans and ACO evaluations. This process can take years before a final determination is made. This thesis will focus on how the Procuring Contracting Officer (PCO) obtains the information about deficiencies or disapproval and what actions he/she takes to insure the Government is receiving a fair and reasonable price for the goods and services it buys."],"dc:description.uri":["http://archive.org/details/affectofcontract109457860"],"dc:format.extent":["ix, 95 p."],"dc:identifier.uri":["https://hdl.handle.net/10945/7860"],"dc:publisher":["Monterey, California. Naval Postgraduate School"],"dc:rights":["This publication is a work of the U.S. Government as defined in Title 17, United States Code, Section 101. Copyright protection is not available for this work in the United States.","Approved for public release; distribution is unlimited."],"dc:subject.keyword":["Cost estimating systems","Procuring contracting officer","Estimating"],"dc:title":["Affect of contractor's estimating system deficiencies and disapprovals on DoD procuring contracting officers"],"dc:type":["Thesis"],"dspace:entity.type":["Publication"],"local:contributor.affiliation":["Lieutenant Commander, United States Navy"],"thesis:degree_discipline":["Contract Management"],"thesis:degree_level":["Masters"],"thesis:degree_name":["M.S. in Contract Management"],"thesis:institution_name":["Naval Postgraduate School"]},"updated_at":"2026-11-21T23:36:05Z"}