{"id":{"repo_id":"odu","oai_identifier":"oai:digitalcommons.odu.edu:mae_etds-1574"},"canonical_url":"https://search.ndltd.org/etd/odu/oai:digitalcommons.odu.edu:mae_etds-1574","repository":{"repo_id":"odu","name":"Old Dominion University","base_url":"https://digitalcommons.odu.edu/do/oai/"},"display":{"title":"Theory of Constraints Project Management in A Manufacturing Environment","abstract":"The following thesis covers the concepts of Theory of Constraints (TOC) Project Management. Introduced by Eliyahu M. Goldratt in I 984, TOC is a management philosophy that focuses on the use of critical chain project management to prioritize everyday tasks in a company. In TOC Project Management, there is always at least one resource constraint that limits the speed at which projects are completed. TOC management philosophy also recognizes that most projects in the manufacturing industry face unknown schedule delays that could cause projects to be completed late or over the planned budget. During project plan creation, plans are developed by managers to expect uncertainty and delays to occur, while also creating feeder buffers and project buffers to protect against variation. The following thesis uses an extensive study of a manufacturing scenario to show how to properly budget for a project, protect schedules against the unexpected delays that occur in project tasks, how to plan for a schedule recovery, and finally how to properly execute schedule recovery to complete projects on the promised delivery date and finish within the planned budget. The solutions that were derived from Mr. Goldratt's TOC Project Management style is expanded and combined with new risk management techniques to determine the optimal solutions for project schedule recovery.","abstract_html":"The following thesis covers the concepts of Theory of Constraints (TOC) Project Management. Introduced by Eliyahu M. Goldratt in I 984, TOC is a management philosophy that focuses on the use of critical chain project management to prioritize everyday tasks in a company. In TOC Project Management, there is always at least one resource constraint that limits the speed at which projects are completed. TOC management philosophy also recognizes that most projects in the manufacturing industry face unknown schedule delays that could cause projects to be completed late or over the planned budget. During project plan creation, plans are developed by managers to expect uncertainty and delays to occur, while also creating feeder buffers and project buffers to protect against variation. The following thesis uses an extensive study of a manufacturing scenario to show how to properly budget for a project, protect schedules against the unexpected delays that occur in project tasks, how to plan for a schedule recovery, and finally how to properly execute schedule recovery to complete projects on the promised delivery date and finish within the planned budget. The solutions that were derived from Mr. Goldratt&#x27;s TOC Project Management style is expanded and combined with new risk management techniques to determine the optimal solutions for project schedule recovery.","abstract_has_math":false,"creators":["Kraft, Shihching"],"institution":null,"degree_name":"Master of Science (MS)","degree_level":"Thesis","degree_discipline":"Mechanical & Aerospace Engineering","degree_department":null,"school":null,"contributors":["Han P. Bao","Gene J.-W. Hou","Rafael E. Landaeta"],"advisors":[],"committee_chairs":[],"committee_members":[],"year":null,"date_issued":"","date_published":null,"updated_at":"2026-11-27T04:11:26Z","subjects":["Manufacturing industries","Theory of constraints","Project management","Manufacturing","Operational Research","Organizational Behavior and Theory"],"languages":[],"rights":["<p>In Copyright. URI: <a href=\"http://rightsstatements.org/vocab/InC/1.0/\">http://rightsstatements.org/vocab/InC/1.0/</a> This Item is protected by copyright and/or related rights. You are free to use this Item in any way that is permitted by the copyright and related rights legislation that applies to your use. For other uses you need to obtain permission from the rights-holder(s).</p>"],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"https://digitalcommons.odu.edu/mae_etds/581","outbound_label":"Repository record","outbound_source":"dc:identifier","record_url":"https://digitalcommons.odu.edu/mae_etds/581","record_label":"Repository record","record_kind":"record","record_source":"dc:identifier","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Aodu%3Aoai%3Adigitalcommons.odu.edu%3Amae_etds-1574","prefix":"oai_dc"},"source_record":{"url":"https://digitalcommons.odu.edu/do/oai/?verb=GetRecord&metadataPrefix=oai_etdms&identifier=oai%3Adigitalcommons.odu.edu%3Amae_etds-1574","prefix":"oai_etdms"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor","label":"Contributor","values":["Han P. Bao","Gene J.-W. Hou","Rafael E. Landaeta"]},{"key":"dc:creator","label":"Author","values":["Kraft, Shihching"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.available","label":"Dc Date Available","values":["2025-01-24T08:00:00Z"]},{"key":"dc:date.created","label":"Dc Date Created","values":["2013-10-01T07:00:00Z"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Mechanical & Aerospace Engineering"]},{"key":"thesis:degree_level","label":"Degree Level","values":["Thesis"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science (MS)"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject","label":"Dc Subject","values":["Manufacturing industries","Theory of constraints","Project management","Manufacturing","Operational Research","Organizational Behavior and Theory"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:rights","label":"Dc Rights","values":["<p>In Copyright. URI: <a href=\"http://rightsstatements.org/vocab/InC/1.0/\">http://rightsstatements.org/vocab/InC/1.0/</a> This Item is protected by copyright and/or related rights. You are free to use this Item in any way that is permitted by the copyright and related rights legislation that applies to your use. For other uses you need to obtain permission from the rights-holder(s).</p>"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier","label":"Identifier","values":["https://digitalcommons.odu.edu/mae_etds/581"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["The following thesis covers the concepts of Theory of Constraints (TOC) Project Management. Introduced by Eliyahu M. Goldratt in I 984, TOC is a management philosophy that focuses on the use of critical chain project management to prioritize everyday tasks in a company. In TOC Project Management, there is always at least one resource constraint that limits the speed at which projects are completed. TOC management philosophy also recognizes that most projects in the manufacturing industry face unknown schedule delays that could cause projects to be completed late or over the planned budget. During project plan creation, plans are developed by managers to expect uncertainty and delays to occur, while also creating feeder buffers and project buffers to protect against variation. The following thesis uses an extensive study of a manufacturing scenario to show how to properly budget for a project, protect schedules against the unexpected delays that occur in project tasks, how to plan for a schedule recovery, and finally how to properly execute schedule recovery to complete projects on the promised delivery date and finish within the planned budget. The solutions that were derived from Mr. Goldratt's TOC Project Management style is expanded and combined with new risk management techniques to determine the optimal solutions for project schedule recovery."]},{"key":"dc:title","label":"Title","values":["Theory of Constraints Project Management in A Manufacturing Environment"]}]}],"canonical_facts":{"dc:contributor":["Han P. Bao","Gene J.-W. Hou","Rafael E. Landaeta"],"dc:creator":["Kraft, Shihching"],"dc:date.available":["2025-01-24T08:00:00Z"],"dc:date.created":["2013-10-01T07:00:00Z"],"dc:description.abstract":["The following thesis covers the concepts of Theory of Constraints (TOC) Project Management. Introduced by Eliyahu M. Goldratt in I 984, TOC is a management philosophy that focuses on the use of critical chain project management to prioritize everyday tasks in a company. In TOC Project Management, there is always at least one resource constraint that limits the speed at which projects are completed. TOC management philosophy also recognizes that most projects in the manufacturing industry face unknown schedule delays that could cause projects to be completed late or over the planned budget. During project plan creation, plans are developed by managers to expect uncertainty and delays to occur, while also creating feeder buffers and project buffers to protect against variation. The following thesis uses an extensive study of a manufacturing scenario to show how to properly budget for a project, protect schedules against the unexpected delays that occur in project tasks, how to plan for a schedule recovery, and finally how to properly execute schedule recovery to complete projects on the promised delivery date and finish within the planned budget. The solutions that were derived from Mr. Goldratt's TOC Project Management style is expanded and combined with new risk management techniques to determine the optimal solutions for project schedule recovery."],"dc:identifier":["https://digitalcommons.odu.edu/mae_etds/581"],"dc:rights":["<p>In Copyright. URI: <a href=\"http://rightsstatements.org/vocab/InC/1.0/\">http://rightsstatements.org/vocab/InC/1.0/</a> This Item is protected by copyright and/or related rights. You are free to use this Item in any way that is permitted by the copyright and related rights legislation that applies to your use. For other uses you need to obtain permission from the rights-holder(s).</p>"],"dc:subject":["Manufacturing industries","Theory of constraints","Project management","Manufacturing","Operational Research","Organizational Behavior and Theory"],"dc:title":["Theory of Constraints Project Management in A Manufacturing Environment"],"thesis:degree_discipline":["Mechanical & Aerospace Engineering"],"thesis:degree_level":["Thesis"],"thesis:degree_name":["Master of Science (MS)"]},"updated_at":"2026-11-27T04:11:26Z"}