{"id":{"repo_id":"ohiolink","oai_identifier":"oai:etd.ohiolink.edu:osu1429772426"},"canonical_url":"https://search.ndltd.org/etd/ohiolink/oai:etd.ohiolink.edu:osu1429772426","repository":{"repo_id":"ohiolink","name":"OhioLINK","base_url":"https://etd.ohiolink.edu/acprod/odb_etd/ws/oai/oai"},"display":{"title":"Fuzzy Time-Delay Model in Fault-Tree Analysis for Critical Path Method","abstract":"Construction projects are always expected to be delayed, but the likelihood of a delay varies between projects because of the particular circumstances and schedule for that project. It is usually left to the scheduler to estimate these future circumstances of the project when preparing the schedule and determining the duration of the project. However, the schedule of the Critical Path Method (CPM) does not indicate the factors that are assumed to participate in determining the likelihood for delay. These deterministic durations, apart from the relationship between the activities, are the dominant contributor to the critical path in the CPM calculation. Risk management focuses on the processes that are considered critical, although delay may emerge from non-critical paths.In this study, a new fuzzy model is proposed to provide a subjective assessment of the likelihood of delay for activities in different periods. Using this model, the scheduler’s assessment of the likelihood of delay for each activity can be combined to determine the likelihood of a project delay. This process is done utilizing fuzzy logic and fault-tree analysis and is then combined with the CPM schedule of the project. The result is a fuzzy fault-tree that shows the potential delay of the project and its contributing paths.Applying this method on a sample project, the results show that risk of delay comes not only from critical paths but also from non-critical paths. Consequently, the CPM schedule duration can be reevaluated such that the project can be rescheduled to account for the new findings and, at the very least, the risk of delay can be accounted for.","abstract_html":"Construction projects are always expected to be delayed, but the likelihood of a delay varies between projects because of the particular circumstances and schedule for that project. It is usually left to the scheduler to estimate these future circumstances of the project when preparing the schedule and determining the duration of the project. However, the schedule of the Critical Path Method (CPM) does not indicate the factors that are assumed to participate in determining the likelihood for delay. These deterministic durations, apart from the relationship between the activities, are the dominant contributor to the critical path in the CPM calculation. Risk management focuses on the processes that are considered critical, although delay may emerge from non-critical paths.In this study, a new fuzzy model is proposed to provide a subjective assessment of the likelihood of delay for activities in different periods. Using this model, the scheduler’s assessment of the likelihood of delay for each activity can be combined to determine the likelihood of a project delay. This process is done utilizing fuzzy logic and fault-tree analysis and is then combined with the CPM schedule of the project. The result is a fuzzy fault-tree that shows the potential delay of the project and its contributing paths.Applying this method on a sample project, the results show that risk of delay comes not only from critical paths but also from non-critical paths. Consequently, the CPM schedule duration can be reevaluated such that the project can be rescheduled to account for the new findings and, at the very least, the risk of delay can be accounted for.","abstract_has_math":false,"creators":["Alsaqqa, Obada"],"institution":"The Ohio State University","degree_name":"Master of Science","degree_level":"masters","degree_discipline":"Civil Engineering","degree_department":null,"school":null,"contributors":[],"advisors":["Tan, Fabian"],"committee_chairs":[],"committee_members":[],"year":2015,"date_issued":"2015-05-21","date_published":"2015-05-21","updated_at":"2026-11-27T04:40:18Z","subjects":["Civil Engineering","Engineering","Mathematics","Logic","Management","Operations Research","Industrial Engineering","Construction Management","CPM","Delay Likelihood","Fault Tree Analysis","FFTA","FTA","Fuzzy Fault Tree","Fuzzy Fault Tree Analysis","Fuzzy Logic","Fuzzy Model","PERT","Project Delay","Risk Management","Scheduling","Time Delay Analysis","Time Overrun","Uncertainty"],"languages":["English"],"rights":["unrestricted","This thesis or dissertation is protected by copyright: all rights reserved. It may not be copied or redistributed beyond the terms of applicable copyright laws."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"http://rave.ohiolink.edu/etdc/view?acc_num=osu1429772426","outbound_label":"Repository record","outbound_source":"dc:identifier","record_url":"http://rave.ohiolink.edu/etdc/view?acc_num=osu1429772426","record_label":"Repository record","record_kind":"record","record_source":"dc:identifier","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Aohiolink%3Aoai%3Aetd.ohiolink.edu%3Aosu1429772426","prefix":"oai_dc"},"source_record":{"url":"https://etd.ohiolink.edu/acprod/odb_etd/ws/oai/oai?verb=GetRecord&metadataPrefix=oai_etdms&identifier=oai%3Aetd.ohiolink.edu%3Aosu1429772426","prefix":"oai_etdms"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Tan, Fabian"]},{"key":"dc:creator","label":"Author","values":["Alsaqqa, Obada"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["2015-05-21"]},{"key":"dc:publisher","label":"Institution","values":["The Ohio State University / OhioLINK"]},{"key":"dc:type","label":"Dc Type","values":["Electronic Thesis or Dissertation"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Civil Engineering"]},{"key":"thesis:degree_level","label":"Degree Level","values":["masters"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["The Ohio State University"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject","label":"Dc Subject","values":["Civil Engineering","Engineering","Mathematics","Logic","Management","Operations Research","Industrial Engineering","Construction Management","CPM","Delay Likelihood","Fault Tree Analysis","FFTA","FTA","Fuzzy Fault Tree","Fuzzy Fault Tree Analysis","Fuzzy Logic","Fuzzy Model","PERT","Project Delay","Risk Management","Scheduling","Time Delay Analysis","Time Overrun","Uncertainty"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language","label":"Dc Language","values":["English"]},{"key":"dc:rights","label":"Dc Rights","values":["unrestricted","This thesis or dissertation is protected by copyright: all rights reserved. It may not be copied or redistributed beyond the terms of applicable copyright laws."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier","label":"Identifier","values":["http://rave.ohiolink.edu/etdc/view?acc_num=osu1429772426"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description","label":"Description","values":["Construction projects are always expected to be delayed, but the likelihood of a delay varies between projects because of the particular circumstances and schedule for that project. It is usually left to the scheduler to estimate these future circumstances of the project when preparing the schedule and determining the duration of the project. However, the schedule of the Critical Path Method (CPM) does not indicate the factors that are assumed to participate in determining the likelihood for delay. These deterministic durations, apart from the relationship between the activities, are the dominant contributor to the critical path in the CPM calculation. Risk management focuses on the processes that are considered critical, although delay may emerge from non-critical paths.In this study, a new fuzzy model is proposed to provide a subjective assessment of the likelihood of delay for activities in different periods. Using this model, the scheduler’s assessment of the likelihood of delay for each activity can be combined to determine the likelihood of a project delay. This process is done utilizing fuzzy logic and fault-tree analysis and is then combined with the CPM schedule of the project. The result is a fuzzy fault-tree that shows the potential delay of the project and its contributing paths.Applying this method on a sample project, the results show that risk of delay comes not only from critical paths but also from non-critical paths. Consequently, the CPM schedule duration can be reevaluated such that the project can be rescheduled to account for the new findings and, at the very least, the risk of delay can be accounted for."]},{"key":"dc:format","label":"Dc Format","values":["application/pdf","p.137","3.02 MB"]},{"key":"dc:title","label":"Title","values":["Fuzzy Time-Delay Model in Fault-Tree Analysis for Critical Path Method"]}]}],"canonical_facts":{"dc:contributor.advisor":["Tan, Fabian"],"dc:creator":["Alsaqqa, Obada"],"dc:date":["2015-05-21"],"dc:description":["Construction projects are always expected to be delayed, but the likelihood of a delay varies between projects because of the particular circumstances and schedule for that project. It is usually left to the scheduler to estimate these future circumstances of the project when preparing the schedule and determining the duration of the project. However, the schedule of the Critical Path Method (CPM) does not indicate the factors that are assumed to participate in determining the likelihood for delay. These deterministic durations, apart from the relationship between the activities, are the dominant contributor to the critical path in the CPM calculation. Risk management focuses on the processes that are considered critical, although delay may emerge from non-critical paths.In this study, a new fuzzy model is proposed to provide a subjective assessment of the likelihood of delay for activities in different periods. Using this model, the scheduler’s assessment of the likelihood of delay for each activity can be combined to determine the likelihood of a project delay. This process is done utilizing fuzzy logic and fault-tree analysis and is then combined with the CPM schedule of the project. The result is a fuzzy fault-tree that shows the potential delay of the project and its contributing paths.Applying this method on a sample project, the results show that risk of delay comes not only from critical paths but also from non-critical paths. Consequently, the CPM schedule duration can be reevaluated such that the project can be rescheduled to account for the new findings and, at the very least, the risk of delay can be accounted for."],"dc:format":["application/pdf","p.137","3.02 MB"],"dc:identifier":["http://rave.ohiolink.edu/etdc/view?acc_num=osu1429772426"],"dc:language":["English"],"dc:publisher":["The Ohio State University / OhioLINK"],"dc:rights":["unrestricted","This thesis or dissertation is protected by copyright: all rights reserved. It may not be copied or redistributed beyond the terms of applicable copyright laws."],"dc:subject":["Civil Engineering","Engineering","Mathematics","Logic","Management","Operations Research","Industrial Engineering","Construction Management","CPM","Delay Likelihood","Fault Tree Analysis","FFTA","FTA","Fuzzy Fault Tree","Fuzzy Fault Tree Analysis","Fuzzy Logic","Fuzzy Model","PERT","Project Delay","Risk Management","Scheduling","Time Delay Analysis","Time Overrun","Uncertainty"],"dc:title":["Fuzzy Time-Delay Model in Fault-Tree Analysis for Critical Path Method"],"dc:type":["Electronic Thesis or Dissertation"],"thesis:degree_discipline":["Civil Engineering"],"thesis:degree_level":["masters"],"thesis:degree_name":["Master of Science"],"thesis:institution_name":["The Ohio State University"]},"updated_at":"2026-11-27T04:40:18Z"}