{"id":{"repo_id":"pohang","oai_identifier":"oai:oasis.postech.ac.kr:2014.oak/2204"},"canonical_url":"https://search.ndltd.org/etd/pohang/oai:oasis.postech.ac.kr:2014.oak/2204","repository":{"repo_id":"pohang","name":"Pohang University of Science and Technology","base_url":"http://oasis.postech.ac.kr/oai/request"},"display":{"title":"Optimal NGL Extraction Process for the Development of Front-End Engineering Design (FEED) of Floating Liquefied Natural Gas (FLNG) Facilities","abstract":"The global energy demand has been rising with the global economic growth and the world has also faced the environmental responsibility to suppress the greenhouse effect. As a key enabler to most efficiently balance these issues, natural gas has gained more interest than the other energy sources and LNG is more compelling for its easiness of handling and storing. However, the increase of the raw material cost and the development of the “easy gas” reservoirs have declined land based LNG facility projects. Unlocking and monetizing the offshore stranded gas reservoir have been pursued and a concept of floating LNG production facility (FLNG) has been considered as a viable option. All shipyards have sought to be involved in this new industry therefore needs to gain capability to develop the Front-End Engineering Design of this facility have arisen. This study focused on selecting a suitable NGL extraction process, which is a process in FLNG, with considerations of practical engineering practice and offshore constraints. With the selection, a process simulation was performed with sensitivity analysis to figure out the most optimal operating parameters. In addition, factors to affect designs in Detailed Design phase and downstream discipline work were considered and discussed. Finally, the optimal parameters have been setup and the core FEED deliverables: Process Flow Diagram (PFD) and Heat and Material Balance are provided.","abstract_html":"The global energy demand has been rising with the global economic growth and the world has also faced the environmental responsibility to suppress the greenhouse effect. As a key enabler to most efficiently balance these issues, natural gas has gained more interest than the other energy sources and LNG is more compelling for its easiness of handling and storing. However, the increase of the raw material cost and the development of the “easy gas” reservoirs have declined land based LNG facility projects. Unlocking and monetizing the offshore stranded gas reservoir have been pursued and a concept of floating LNG production facility (FLNG) has been considered as a viable option. All shipyards have sought to be involved in this new industry therefore needs to gain capability to develop the Front-End Engineering Design of this facility have arisen. This study focused on selecting a suitable NGL extraction process, which is a process in FLNG, with considerations of practical engineering practice and offshore constraints. With the selection, a process simulation was performed with sensitivity analysis to figure out the most optimal operating parameters. In addition, factors to affect designs in Detailed Design phase and downstream discipline work were considered and discussed. Finally, the optimal parameters have been setup and the core FEED deliverables: Process Flow Diagram (PFD) and Heat and Material Balance are provided.","abstract_has_math":false,"creators":["이승민"],"institution":null,"degree_name":null,"degree_level":null,"degree_discipline":null,"degree_department":null,"school":null,"contributors":[],"advisors":[],"committee_chairs":[],"committee_members":[],"year":2014,"date_issued":"2014","date_published":"2014","updated_at":"2026-11-26T04:05:45Z","subjects":[],"languages":[],"rights":[],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier","label":"Identifier","values":["hdl:2014.oak/2204"],"render_values":[{"text":"hdl:2014.oak/2204","href":null,"code":true}]},{"key":"mods:identifier.other","label":"Mods Identifier Other","values":["OAK-2014-01702"],"render_values":[{"text":"OAK-2014-01702","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"http://postech.dcollection.net/jsp/common/DcLoOrgPer.jsp?sItemId=000001677528","outbound_label":"Repository record","outbound_source":"mods:identifier.uri","record_url":"http://postech.dcollection.net/jsp/common/DcLoOrgPer.jsp?sItemId=000001677528","record_label":"Repository record","record_kind":"record","record_source":"mods:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"oai_pmh_record":{"url":"https://union.ndltd.org/oai-pmh/?verb=GetRecord&metadataPrefix=oai_dc&identifier=oai%3Aunion.ndltd.org%3Arepo%3Apohang%3Aoai%3Aoasis.postech.ac.kr%3A2014.oak%2F2204","prefix":"oai_dc"},"source_record":{"url":"http://oasis.postech.ac.kr/oai/request?verb=GetRecord&metadataPrefix=mets&identifier=oai%3Aoasis.postech.ac.kr%3A2014.oak%2F2204","prefix":"mets"},"metadata_groups":[{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.issued","label":"Date","values":["2014"]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier","label":"Identifier","values":["hdl:2014.oak/2204"]},{"key":"mods:identifier.other","label":"Mods Identifier Other","values":["OAK-2014-01702"]},{"key":"mods:identifier.uri","label":"Mods Identifier URI","values":["http://postech.dcollection.net/jsp/common/DcLoOrgPer.jsp?sItemId=000001677528"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.other","label":"Dc Description Other","values":["The global energy demand has been rising with the global economic growth and the world has also faced the environmental responsibility to suppress the greenhouse effect. As a key enabler to most efficiently balance these issues, natural gas has gained more interest than the other energy sources and LNG is more compelling for its easiness of handling and storing. However, the increase of the raw material cost and the development of the “easy gas” reservoirs have declined land based LNG facility projects. Unlocking and monetizing the offshore stranded gas reservoir have been pursued and a concept of floating LNG production facility (FLNG) has been considered as a viable option. All shipyards have sought to be involved in this new industry therefore needs to gain capability to develop the Front-End Engineering Design of this facility have arisen. This study focused on selecting a suitable NGL extraction process, which is a process in FLNG, with considerations of practical engineering practice and offshore constraints. With the selection, a process simulation was performed with sensitivity analysis to figure out the most optimal operating parameters. In addition, factors to affect designs in Detailed Design phase and downstream discipline work were considered and discussed. Finally, the optimal parameters have been setup and the core FEED deliverables: Process Flow Diagram (PFD) and Heat and Material Balance are provided."]},{"key":"dc:title","label":"Title","values":["Optimal NGL Extraction Process for the Development of Front-End Engineering Design (FEED) of Floating Liquefied Natural Gas (FLNG) Facilities"]},{"key":"mods:accesscondition.useandreproduction","label":"Mods Accesscondition Useandreproduction","values":["BY_NC_ND"]},{"key":"mods:dateaccessioned","label":"Mods Dateaccessioned","values":["2014-12-01T11:49:16Z"]},{"key":"mods:dateavailable","label":"Mods Dateavailable","values":["2014-12-01T11:49:16Z"]},{"key":"mods:namepart","label":"Mods Namepart","values":["이승민","일반대학원 엔지니어링특성화협동과정"]},{"key":"mods:roleterm.text","label":"Mods Roleterm Text","values":["author","college"]}]}],"canonical_facts":{"dc:date.issued":["2014"],"dc:description.other":["The global energy demand has been rising with the global economic growth and the world has also faced the environmental responsibility to suppress the greenhouse effect. As a key enabler to most efficiently balance these issues, natural gas has gained more interest than the other energy sources and LNG is more compelling for its easiness of handling and storing. However, the increase of the raw material cost and the development of the “easy gas” reservoirs have declined land based LNG facility projects. Unlocking and monetizing the offshore stranded gas reservoir have been pursued and a concept of floating LNG production facility (FLNG) has been considered as a viable option. All shipyards have sought to be involved in this new industry therefore needs to gain capability to develop the Front-End Engineering Design of this facility have arisen. This study focused on selecting a suitable NGL extraction process, which is a process in FLNG, with considerations of practical engineering practice and offshore constraints. With the selection, a process simulation was performed with sensitivity analysis to figure out the most optimal operating parameters. In addition, factors to affect designs in Detailed Design phase and downstream discipline work were considered and discussed. Finally, the optimal parameters have been setup and the core FEED deliverables: Process Flow Diagram (PFD) and Heat and Material Balance are provided."],"dc:identifier":["hdl:2014.oak/2204"],"dc:title":["Optimal NGL Extraction Process for the Development of Front-End Engineering Design (FEED) of Floating Liquefied Natural Gas (FLNG) Facilities"],"dc:type":["Thesis"],"mods:accesscondition.useandreproduction":["BY_NC_ND"],"mods:dateaccessioned":["2014-12-01T11:49:16Z"],"mods:dateavailable":["2014-12-01T11:49:16Z"],"mods:identifier.other":["OAK-2014-01702"],"mods:identifier.uri":["http://postech.dcollection.net/jsp/common/DcLoOrgPer.jsp?sItemId=000001677528"],"mods:namepart":["이승민","일반대학원 엔지니어링특성화협동과정"],"mods:roleterm.text":["author","college"]},"updated_at":"2026-11-26T04:05:45Z"}