{"id":{"repo_id":"ubc","oai_identifier":"oai:circle.library.ubc.ca:2429/21886"},"canonical_url":"https://search.ndltd.org/etd/ubc/oai:circle.library.ubc.ca:2429/21886","repository":{"repo_id":"ubc","name":"University of British Columbia","base_url":"http://circle.library.ubc.ca/oai/request"},"display":{"title":"An evaluation of CP Rail’s proposed Beaver Tunnel","abstract":"CP Rail is experiencing capacity constraints on its western mainline between Calgary, Alberta and Vancouver, B.C. The critical bottleneck has been identified as the Roger's Pass section, which is between Golden, B.C. and Revelstoke, B.C. CP Rail has examined several alternatives, and has concluded that this bottleneck can best be overcome by nineteen miles of doubletracking. This would require the construction of an eight-Mile tunnel under Roger's Pass. CP Rail's financial evaluation of this project reveals an unacceptably low rate of return on capital invested. This paper has two objectives, namely 1) to examine the potential conflict between the public desirability of the tunnel investment and the financial viability of the investment, and 2) regardless of the outcome of the first objective, to identify and analyze alternative methods of providing financial compensation to CP Rail so that it will proceed with the tunnel investment. The analysis concludes that potential benefits brought on by the construction of the tunnel may make this project desirable from a public point of view, even if it is established that the tunnel is not financially viable to CP Rail. The analysis of the alternative methods of providing financial compensation point out that user pay financing alternatives are preferable from an economic viewpoint, but the analysis concludes that time constraints are such that public financing alternatives are optimal.","abstract_html":"CP Rail is experiencing capacity constraints on its western mainline between Calgary, Alberta and Vancouver, B.C. The critical bottleneck has been identified as the Roger&#x27;s Pass section, which is between Golden, B.C. and Revelstoke, B.C. CP Rail has examined several alternatives, and has concluded that this bottleneck can best be overcome by nineteen miles of doubletracking. This would require the construction of an eight-Mile tunnel under Roger&#x27;s Pass. CP Rail&#x27;s financial evaluation of this project reveals an unacceptably low rate of return on capital invested. This paper has two objectives, namely 1) to examine the potential conflict between the public desirability of the tunnel investment and the financial viability of the investment, and 2) regardless of the outcome of the first objective, to identify and analyze alternative methods of providing financial compensation to CP Rail so that it will proceed with the tunnel investment. The analysis concludes that potential benefits brought on by the construction of the tunnel may make this project desirable from a public point of view, even if it is established that the tunnel is not financially viable to CP Rail. The analysis of the alternative methods of providing financial compensation point out that user pay financing alternatives are preferable from an economic viewpoint, but the analysis concludes that time constraints are such that public financing alternatives are optimal.","abstract_has_math":false,"creators":["Friesen, Ted John"],"institution":"University of British Columbia","degree_name":"Master of Science in Business - MScB","degree_level":"master's","degree_discipline":"Business Administration","degree_department":null,"school":null,"contributors":[],"advisors":[],"committee_chairs":[],"committee_members":[],"year":1980,"date_issued":"1980","date_published":"1980","updated_at":"2026-11-19T14:39:40Z","subjects":[],"languages":["eng"],"rights":["For non-commercial purposes only, such as research, private study and education. Additional conditions apply, see Terms of Use https://open.library.ubc.ca/terms_of_use."],"rights_urls":[],"identifier_entries":[],"person_identifier_entries":[]},"links":{"outbound_url":"http://hdl.handle.net/2429/21886","outbound_label":"Handle","outbound_source":"dc:identifier","record_url":"http://hdl.handle.net/2429/21886","record_label":"Repository record","record_kind":"handle","record_source":"dc:identifier","download_url":"http://circle.library.ubc.ca/bitstream/2429/21886/1/UBC_1980_A4_6+F75.pdf","download_label":"Download PDF","download_source":"dc:identifier","access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"http://circle.library.ubc.ca/oai/request?verb=GetRecord&metadataPrefix=etdms&identifier=oai%3Acircle.library.ubc.ca%3A2429%2F21886","prefix":"etdms"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:creator","label":"Author","values":["Friesen, Ted John"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["1980"]},{"key":"dc:publisher","label":"Institution","values":["University of British Columbia"]},{"key":"dc:type","label":"Dc Type","values":["Text"]},{"key":"thesis:degree_discipline","label":"Discipline","values":["Business Administration"]},{"key":"thesis:degree_level","label":"Degree Level","values":["master's"]},{"key":"thesis:degree_name","label":"Degree Name","values":["Master of Science in Business - MScB"]},{"key":"thesis:institution_name","label":"Thesis Institution Name","values":["University of British Columbia"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language","label":"Dc Language","values":["eng"]},{"key":"dc:rights","label":"Dc Rights","values":["For non-commercial purposes only, such as research, private study and education. Additional conditions apply, see Terms of Use https://open.library.ubc.ca/terms_of_use."]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier","label":"Identifier","values":["http://hdl.handle.net/2429/21886","http://circle.library.ubc.ca/bitstream/2429/21886/1/UBC_1980_A4_6+F75.pdf"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description","label":"Description","values":["CP Rail is experiencing capacity constraints on its western mainline between Calgary, Alberta and Vancouver, B.C. The critical bottleneck has been identified as the Roger's Pass section, which is between Golden, B.C. and Revelstoke, B.C. CP Rail has examined several alternatives, and has concluded that this bottleneck can best be overcome by nineteen miles of doubletracking. This would require the construction of an eight-Mile tunnel under Roger's Pass. CP Rail's financial evaluation of this project reveals an unacceptably low rate of return on capital invested. This paper has two objectives, namely 1) to examine the potential conflict between the public desirability of the tunnel investment and the financial viability of the investment, and 2) regardless of the outcome of the first objective, to identify and analyze alternative methods of providing financial compensation to CP Rail so that it will proceed with the tunnel investment. The analysis concludes that potential benefits brought on by the construction of the tunnel may make this project desirable from a public point of view, even if it is established that the tunnel is not financially viable to CP Rail. The analysis of the alternative methods of providing financial compensation point out that user pay financing alternatives are preferable from an economic viewpoint, but the analysis concludes that time constraints are such that public financing alternatives are optimal."]},{"key":"dc:format","label":"Dc Format","values":["4840218","application/pdf"]},{"key":"dc:title","label":"Title","values":["An evaluation of CP Rail’s proposed Beaver Tunnel"]}]}],"canonical_facts":{"dc:creator":["Friesen, Ted John"],"dc:date":["1980"],"dc:description":["CP Rail is experiencing capacity constraints on its western mainline between Calgary, Alberta and Vancouver, B.C. The critical bottleneck has been identified as the Roger's Pass section, which is between Golden, B.C. and Revelstoke, B.C. CP Rail has examined several alternatives, and has concluded that this bottleneck can best be overcome by nineteen miles of doubletracking. This would require the construction of an eight-Mile tunnel under Roger's Pass. CP Rail's financial evaluation of this project reveals an unacceptably low rate of return on capital invested. This paper has two objectives, namely 1) to examine the potential conflict between the public desirability of the tunnel investment and the financial viability of the investment, and 2) regardless of the outcome of the first objective, to identify and analyze alternative methods of providing financial compensation to CP Rail so that it will proceed with the tunnel investment. The analysis concludes that potential benefits brought on by the construction of the tunnel may make this project desirable from a public point of view, even if it is established that the tunnel is not financially viable to CP Rail. The analysis of the alternative methods of providing financial compensation point out that user pay financing alternatives are preferable from an economic viewpoint, but the analysis concludes that time constraints are such that public financing alternatives are optimal."],"dc:format":["4840218","application/pdf"],"dc:identifier":["http://hdl.handle.net/2429/21886","http://circle.library.ubc.ca/bitstream/2429/21886/1/UBC_1980_A4_6+F75.pdf"],"dc:language":["eng"],"dc:publisher":["University of British Columbia"],"dc:rights":["For non-commercial purposes only, such as research, private study and education. Additional conditions apply, see Terms of Use https://open.library.ubc.ca/terms_of_use."],"dc:title":["An evaluation of CP Rail’s proposed Beaver Tunnel"],"dc:type":["Text"],"thesis:degree_discipline":["Business Administration"],"thesis:degree_level":["master's"],"thesis:degree_name":["Master of Science in Business - MScB"],"thesis:institution_name":["University of British Columbia"]},"updated_at":"2026-11-19T14:39:40Z"}