{"id":{"repo_id":"ucf","oai_identifier":"oai:stars.library.ucf.edu:etd-6288"},"canonical_url":"https://search.ndltd.org/etd/ucf/oai:stars.library.ucf.edu:etd-6288","repository":{"repo_id":"ucf","name":"Central Florida","base_url":"https://stars.library.ucf.edu/do/oai/"},"display":{"title":"Dynamic Modeling Approach to Quantify Change Orders Impact on Labor Productivity","abstract":"In construction projects, change orders are commonly faced. These change orders, which are issued by the owner, may cause interruption to the contractor's work, resulting in damages such as loss of labor productivity, delay damages, and cost overruns which may lead to claims. The relationship between change orders and loss of labor productivity is not well understood because of the difficulty in linking the cause of the productivity loss to the change order. So, to receive compensation, the contractor needs to prove with a credible calculation that the productivity loss was a result of the change order issued by the owner. Compared to all available productivity loss quantification methods, the \"Measured Mile\" approach is considered the most acceptable and popular approach in litigation. In this study, loss of labor productivity due to change orders is studied using a system dynamics method. A system dynamics model is developed using Vensim Software, validated, and utilized to quantitatively measure the impact of the change in the project scope on labor productivity. Different road construction projects were analyzed using both methods: measured mile analysis and system dynamics model; then, the results from those two approaches were compared.","abstract_html":"In construction projects, change orders are commonly faced. These change orders, which are issued by the owner, may cause interruption to the contractor&#x27;s work, resulting in damages such as loss of labor productivity, delay damages, and cost overruns which may lead to claims. The relationship between change orders and loss of labor productivity is not well understood because of the difficulty in linking the cause of the productivity loss to the change order. So, to receive compensation, the contractor needs to prove with a credible calculation that the productivity loss was a result of the change order issued by the owner. Compared to all available productivity loss quantification methods, the &quot;Measured Mile&quot; approach is considered the most acceptable and popular approach in litigation. In this study, loss of labor productivity due to change orders is studied using a system dynamics method. A system dynamics model is developed using Vensim Software, validated, and utilized to quantitatively measure the impact of the change in the project scope on labor productivity. Different road construction projects were analyzed using both methods: measured mile analysis and system dynamics model; then, the results from those two approaches were compared.","abstract_has_math":false,"creators":["Al-Kofahi, Zain"],"institution":"University of Central Florida","degree_name":null,"degree_level":null,"degree_discipline":null,"degree_department":null,"school":null,"contributors":["Oloufa, Amr"],"advisors":[],"committee_chairs":[],"committee_members":[],"year":null,"date_issued":"","date_published":null,"updated_at":"2026-11-19T09:31:33Z","subjects":["Civil Engineering"],"languages":["English"],"rights":[],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier","label":"Identifier","values":["CFE0006430"],"render_values":[{"text":"CFE0006430","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":"https://stars.library.ucf.edu/etd/5288","outbound_label":"Repository record","outbound_source":"dc:identifier.uri","record_url":"https://stars.library.ucf.edu/etd/5288","record_label":"Repository record","record_kind":"record","record_source":"dc:identifier.uri","download_url":null,"download_label":null,"download_source":null,"access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"https://stars.library.ucf.edu/do/oai/?verb=GetRecord&metadataPrefix=oai_etdms&identifier=oai%3Astars.library.ucf.edu%3Aetd-6288","prefix":"oai_etdms"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor","label":"Contributor","values":["Oloufa, Amr"]},{"key":"dc:creator","label":"Author","values":["Al-Kofahi, Zain"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date.created","label":"Dc Date Created","values":["2016-01-01T08:00:00Z","Fall","2017-12-15T08:00:00Z"]},{"key":"dc:publisher","label":"Institution","values":["University of Central Florida"]},{"key":"dc:type","label":"Dc Type","values":["Doctoral Dissertation (Open Access)"]}]},{"id":"subjects_keywords","label":"Subjects and Keywords","entries":[{"key":"dc:subject","label":"Dc Subject","values":["Civil Engineering"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language","label":"Dc Language","values":["English"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier","label":"Identifier","values":["CFE0006430"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://stars.library.ucf.edu/etd/5288"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description","label":"Description","values":["Doctor of Philosophy (Ph.D.)","Civil, Environmental, and Construction Engineering","<p>If this is your thesis or dissertation, and want to learn how to access it or for more information about readership statistics, contact us at <a href=\"mailto:STARS@ucf.edu\">STARS@ucf.edu</a></p>","College of Engineering and Computer Science","Civil Engineering"]},{"key":"dc:description.abstract","label":"Abstract","values":["In construction projects, change orders are commonly faced. These change orders, which are issued by the owner, may cause interruption to the contractor's work, resulting in damages such as loss of labor productivity, delay damages, and cost overruns which may lead to claims. The relationship between change orders and loss of labor productivity is not well understood because of the difficulty in linking the cause of the productivity loss to the change order. So, to receive compensation, the contractor needs to prove with a credible calculation that the productivity loss was a result of the change order issued by the owner. Compared to all available productivity loss quantification methods, the \"Measured Mile\" approach is considered the most acceptable and popular approach in litigation. In this study, loss of labor productivity due to change orders is studied using a system dynamics method. A system dynamics model is developed using Vensim Software, validated, and utilized to quantitatively measure the impact of the change in the project scope on labor productivity. Different road construction projects were analyzed using both methods: measured mile analysis and system dynamics model; then, the results from those two approaches were compared."]},{"key":"dc:format","label":"Dc Format","values":["application/pdf"]},{"key":"dc:title","label":"Title","values":["Dynamic Modeling Approach to Quantify Change Orders Impact on Labor Productivity"]}]}],"canonical_facts":{"dc:contributor":["Oloufa, Amr"],"dc:creator":["Al-Kofahi, Zain"],"dc:date.created":["2016-01-01T08:00:00Z","Fall","2017-12-15T08:00:00Z"],"dc:description":["Doctor of Philosophy (Ph.D.)","Civil, Environmental, and Construction Engineering","<p>If this is your thesis or dissertation, and want to learn how to access it or for more information about readership statistics, contact us at <a href=\"mailto:STARS@ucf.edu\">STARS@ucf.edu</a></p>","College of Engineering and Computer Science","Civil Engineering"],"dc:description.abstract":["In construction projects, change orders are commonly faced. These change orders, which are issued by the owner, may cause interruption to the contractor's work, resulting in damages such as loss of labor productivity, delay damages, and cost overruns which may lead to claims. The relationship between change orders and loss of labor productivity is not well understood because of the difficulty in linking the cause of the productivity loss to the change order. So, to receive compensation, the contractor needs to prove with a credible calculation that the productivity loss was a result of the change order issued by the owner. Compared to all available productivity loss quantification methods, the \"Measured Mile\" approach is considered the most acceptable and popular approach in litigation. In this study, loss of labor productivity due to change orders is studied using a system dynamics method. A system dynamics model is developed using Vensim Software, validated, and utilized to quantitatively measure the impact of the change in the project scope on labor productivity. Different road construction projects were analyzed using both methods: measured mile analysis and system dynamics model; then, the results from those two approaches were compared."],"dc:format":["application/pdf"],"dc:identifier":["CFE0006430"],"dc:identifier.uri":["https://stars.library.ucf.edu/etd/5288"],"dc:language":["English"],"dc:publisher":["University of Central Florida"],"dc:subject":["Civil Engineering"],"dc:title":["Dynamic Modeling Approach to Quantify Change Orders Impact on Labor Productivity"],"dc:type":["Doctoral Dissertation (Open Access)"]},"updated_at":"2026-11-19T09:31:33Z"}