{"id":{"repo_id":"whiterose","oai_identifier":"oai:etheses.whiterose.ac.uk:17769"},"canonical_url":"https://search.ndltd.org/etd/whiterose/oai:etheses.whiterose.ac.uk:17769","repository":{"repo_id":"whiterose","name":"White Rose University Consortium","base_url":"https://etheses.whiterose.ac.uk/cgi/oai2"},"display":{"title":"Progressive collapse assessment of structures","abstract":"The collapse of buildings over the last century as a result of abnormal loads has renewed interest in the field of structural engineering. Key events such as the disproportionate collapse of the Ronan Point building in London, the collapse of the Alfred Murray Building and the World Trade Centre are structural failures that have triggered more research into progressive collapse. Consequently, new design guidelines around the globe with a prescriptive recommendation for improving structural integrity based on tying force provision have been developed. However, in existing design guidelines and codes throughout the world, there is a lack of a codified modelling technique for progressive collapse. As a result of this limitation, researchers adopt different methods. Generally, during the progressive collapse, structural members experiencing significant displacements and rotations, while the beam-column connections are subjected to large tensile forces not envisaged at the conventional design phase. Hence, this study presents an assessment of the effect of column removal time, the modelling techniques and the susceptibility of simple connections designed to Eurocode 3 Part: 1-8 to progressive collapse. A computationally efficient approach and column removal time for progressive collapse assessment are proposed. The findings show that a braced framed system is likely to exhibit at least 35% progressive collapse when compared with a moment resisting frame system using the joint displacement and rotation criteria. Furthermore, the research shows that the UK tie provision in EN1991-1-7 underestimates the magnitude of the catenary force developed under the progressive collapse scenario. Consequently, the connection is disposed to progressive collapse with the shear force in the column and catenary action in the beam as the critical internal forces. Based on this assessment, five times the tensile force specified in EC3 for tensile force connection design checks is recommended. Shear force in the column and catenary force action in the beam are the internal governing forces that determine the maximum dynamic amplification factor of a simple connection. The work provides evidence that the tie beam-column web connection at the corner column is more critical under progressive collapse scenario as compared with the primary beam. Column web failure in yielding is attributed to the large catenary force developed in the tie beam connected to the web of the column.","abstract_html":"The collapse of buildings over the last century as a result of abnormal loads has renewed interest in the field of structural engineering. Key events such as the disproportionate collapse of the Ronan Point building in London, the collapse of the Alfred Murray Building and the World Trade Centre are structural failures that have triggered more research into progressive collapse. Consequently, new design guidelines around the globe with a prescriptive recommendation for improving structural integrity based on tying force provision have been developed. However, in existing design guidelines and codes throughout the world, there is a lack of a codified modelling technique for progressive collapse. As a result of this limitation, researchers adopt different methods. Generally, during the progressive collapse, structural members experiencing significant displacements and rotations, while the beam-column connections are subjected to large tensile forces not envisaged at the conventional design phase. Hence, this study presents an assessment of the effect of column removal time, the modelling techniques and the susceptibility of simple connections designed to Eurocode 3 Part: 1-8 to progressive collapse. A computationally efficient approach and column removal time for progressive collapse assessment are proposed. The findings show that a braced framed system is likely to exhibit at least 35% progressive collapse when compared with a moment resisting frame system using the joint displacement and rotation criteria. Furthermore, the research shows that the UK tie provision in EN1991-1-7 underestimates the magnitude of the catenary force developed under the progressive collapse scenario. Consequently, the connection is disposed to progressive collapse with the shear force in the column and catenary action in the beam as the critical internal forces. Based on this assessment, five times the tensile force specified in EC3 for tensile force connection design checks is recommended. Shear force in the column and catenary force action in the beam are the internal governing forces that determine the maximum dynamic amplification factor of a simple connection. The work provides evidence that the tie beam-column web connection at the corner column is more critical under progressive collapse scenario as compared with the primary beam. Column web failure in yielding is attributed to the large catenary force developed in the tie beam connected to the web of the column.","abstract_has_math":false,"creators":["Stephen, David Ojonimi"],"institution":"University of Leeds","degree_name":"Ph.D","degree_level":"doctoral","degree_discipline":null,"degree_department":null,"school":null,"contributors":[],"advisors":["Forth, John","Lam, Dennis","Tsavdaridis, Konstantinos Daniel"],"committee_chairs":[],"committee_members":[],"year":2017,"date_issued":"2017-01","date_published":"2017-01","updated_at":"2026-11-18T22:22:11Z","subjects":[],"languages":["eng"],"rights":[],"rights_urls":[],"identifier_entries":[{"key":"dc:identifier","label":"Identifier","values":["uk.bl.ethos.718806"],"render_values":[{"text":"uk.bl.ethos.718806","href":null,"code":true}]}],"person_identifier_entries":[]},"links":{"outbound_url":null,"outbound_label":null,"outbound_source":null,"record_url":null,"record_label":null,"record_kind":null,"record_source":null,"download_url":"https://etheses.whiterose.ac.uk/id/eprint/17769/1/Stephen_D.0_Civil%20Engineering_PhD_2017.pdf","download_label":"Download PDF","download_source":"dc:identifier.uri","access_status":null,"embargo_until":null,"access_note":null},"source_record":{"url":"https://etheses.whiterose.ac.uk/cgi/oai2?verb=GetRecord&metadataPrefix=uketd_dc&identifier=oai%3Aetheses.whiterose.ac.uk%3A17769","prefix":"uketd_dc"},"metadata_groups":[{"id":"people","label":"People","entries":[{"key":"dc:contributor.advisor","label":"Advisor","values":["Forth, John","Lam, Dennis","Tsavdaridis, Konstantinos Daniel"]},{"key":"dc:contributor.sponsor","label":"Sponsor","values":["Petroleum Technology Development Fund (PTDF)"]},{"key":"dc:creator","label":"Author","values":["Stephen, David Ojonimi"]}]},{"id":"academic_context","label":"Academic Context","entries":[{"key":"dc:date","label":"Dc Date","values":["2017-01"]},{"key":"dc:date.issued","label":"Date","values":["2017-01"]},{"key":"dc:publisher.commercial","label":"Dc Publisher Commercial","values":["University of Leeds"]},{"key":"dc:publisher.department","label":"Dc Publisher Department","values":["Faculty of Engineering (Leeds)","School of Civil Engineering (Leeds)"]},{"key":"dc:publisher.institution","label":"Dc Publisher Institution","values":["University of Leeds"]},{"key":"dc:relation.isreferencedby","label":"Dc Relation Isreferencedby","values":["https://etheses.whiterose.ac.uk/id/eprint/17769/"]},{"key":"dc:relation.references","label":"Dc Relation References","values":["REFERENCES ABAQUS (2011). ABAQUS Documentation, Dassault Systèmes, Providence, RI ,USA. Abolmaali, A., Matthys, J.H., Farooqi, M. and Choi, Y. (2005). Development of moment–rotation model equations for flush end-plate connections. Journal of Constructional Steel Research. 61(12), pp.1595-1612. Abruzzo, J., Matta, A. and Panariello, G. (2006). Study of Mitigation Strategies for Progressive Collapse of a Reinforced Concrete Commercial Building. Journal of Performance of Constructed Facilities. 20(4), pp.384-390. Adey, B.T., Grondin, G.Y. and Cheng, J.J. (2000). Cyclic loading of end plate moment connections. Canadian Journal of Civil Engineering. 27(4), pp.683-701. Agarwal, A. and Varma, A.H. (2014). Fire induced progressive collapse of steel building structures: The role of interior gravity columns. Engineering Structures. 58, pp.129-140. Agarwal, J. and England, J. (2008). Recent developments in robustness and relation with risk. In: Proceedings of the ICE - Structures and Buildings, pp.183-188. Aggarwal, A.K. (1994). Comparative tests on endplate beam-to-column connections. Journal of Constructional Steel Research. 30(2), pp.151-175. Alashker, Y. and El-Tawil, S. (2010). Design Model for Collapse Capacity of Composite Floors. In: Structures Congress 2010. pp.1160-1170. Alexander, S. (2004). New approach to disproportionate collapse. The Structural Engineer. 7(23), pp.14 - 18. Ang, K.M. and Morris, G.A. (1984). Analysis of three-dimensional frames with flexible beam–column connections. Canadian Journal of Civil Engineering. 11(2), pp.245-254. Aristizabal-Ochoa, J.D. (2010). Second-order slope–deflection equations for imperfect beam–column structures with semi-rigid connections. Engineering Structures. 32(8), pp.2440-2454. Arros, J. and Doumbalski, N. (2007). Analysis of aircraft impact to concrete structures. Nuclear Engineering and Design. 237(12–13), pp.1241-1249. Ashraf, M., Nethercot, D.A. and Ahmed, B. (2007). Sway of semi-rigid steel frames, part 2: Irregular frames. Engineering Structures. 29(8), pp.1854-1863. Azizinamini, A., Bradburn, J.H., Radziminski, J.B. (1985). Static and Cyclic Behavior of Semi-rigid Steel Beam-column Connections: Final Report : a Report of an Investigation Conducted by the Civil Engineering Department, University of South Carolina. University of South Carolina. Baker, J.W., Schubert, M. and Faber, M.H. (2008). On the assessment of robustness. Structural Safety. 30(3), pp.253-267. Bao, Y., Kunnath, S., El-Tawil, S. and Lew, H. (2008). Macromodel-Based Simulation of Progressive Collapse: RC Frame Structures. Journal of Structural Engineering. 134(7), pp.1079-1091. Bayo, E., Cabrero, J.M. and Gil, B. (2006). An effective component-based method to model semi-rigid connections for the global analysis of steel and composite structures. Engineering Structures. 28(1), pp.97-108. Bažant, Z. and Zhou, Y. (2002). Why Did the World Trade Centre Collapse?—Simple Analysis. Journal of Engineering Mechanics. 128(1), pp.2-6. Beeby, A.W. (1999). Safety of structures, and a new approach to robustness. The Structural Engineer. 77(4), pp.16-19. Bennetts, I.D. and Thomas, I.R. (2002). Design of steel structures under fire conditions. Progress in Structural Engineering and Materials. 4(1), pp.6-17. Biondini, F., Frangopol, D.M. and Restelli, S. (2008). On Structural Robustness, Redundancy, and Static Indeterminacy. In: Structures Congress 2008 pp.1-10. Bjorhovde, R., Colson, A. and Brozzetti, J. (1990). Classification System for Beam‐to‐Column Connections. Journal of Structural Engineering. 116(11), pp.3059-3076. Bose, B., Wang, Z. and Sarkar, S. (1997). Finite-Element Analysis of Unstiffened Flush End-Plate Bolted Joints. Journal of Structural Engineering. 123(12), pp.1614-1621. Braham, M. and Jaspart, J.-P. (2004). Is it safe to design a building structure with simple joints, when they are known to exhibit a semi-rigid behaviour? Journal of Constructional Steel Research. 60(3–5), pp.713-723. British Standards Institution. (2005).European committee for standardization. Eurocode 3: design of steel structures-Part1-1: general rules and rules for buildings, BS EN 1993-1-1:2005. UK. BS5950. (2001). Structural use of steelworks in building. Part 1: Code of practice for the design of simple and continuous costruction: Hot rolled section. London. BS 8110. (1997). The structural use of concrete in building - Part 1: Code of practice for design construction. London, UK Bursi, O.S. and Jaspart, J.P. (1998). Basic issues in the finite element simulation of extended end plate connections. Computers and Structures. 69(3), pp.361-382. Buscemi, N. and Marjanishvili, S. (2005). SDOF Model for Progressive Collapse Analysis. In: Structures Congress pp.1-12. Cabrero, J.M. and Bayo, E. (2005). Development of practical design methods for steel structures with semi-rigid connections. Engineering Structures. 27(8), pp.1125-1137. Cabrero, J.M. and Bayo, E. (2007). The semi-rigid behaviour of three-dimensional steel beam-to-column steel joints subjected to proportional loading. Part II: Theoretical model and validation. Journal of Constructional Steel Research. 63(9), pp.1254-1267. Cabrero, J.M. and Bayo, E. (2007). The semi-rigid behaviour of three-dimensional steel beam-to-column joints subjected to proportional loading. Part I. Experimental evaluation. Journal of Constructional Steel Research. 63(9), pp.1241-1253. CEN. (1994).General Actions - Accidental actions Eurocode 1 - Actions on structures - Part 1- Basis of Design, European Pre Standard ENV 1991-1, Comite Europeen de Normalaization 250.Brussels, Belgium. Chen, W. and Kishi, N. (1989). Semirigid Steel Beam‐to‐Column Connections: Data Base and Modeling. Journal of Structural Engineering. 115(1), pp.105-119. Choi, H.-J., Magallanes, J.M. and Crawford, J.E. (2007). Incorporating Uncertainties in the Blast-Resistant Design. In: New Horizons and Better Practices, pp.1-9. Corley, W., Sr., P., Sozen, M. and Thornton, C. (1998). The Oklahoma City Bombing: Summary and Recommendations for Multihazard Mitigation. Journal of Performance of Constructed Facilities. 12(3), pp.100-112. da S. Vellasco, P.C.G., de Andrade, S.A.L., da Silva, J.G.S., de Lima, L.R.O. and Brito Jr, O. (2006). A parametric analysis of steel and composite portal frames with semi-rigid connections. Engineering Structures. 28(4), pp.543-556. da Silva, J.G.S., de Lima, L.R.O., da S. Vellasco, P.C.G., de Andrade, S.A.L. and de Castro, R.A. (2008). Nonlinear dynamic analysis of steel portal frames with semi-rigid connections. Engineering Structures. 30(9), pp.2566-2579. Díaz, C., Martí, P., Victoria, M. and Querin, O.M. (2011). Review on the modelling of joint behaviour in steel frames. Journal of Constructional Steel Research. 67(5), pp.741-758. Department of Defence (DoD), (2005). “Design of building to resist progressive collapse.” Unified Facility Criteria, UFC 4-023-03, Washington, DC. Department of Defence (DoD), (2009). “Design of building to resist progressive collapse.” Unified Facility Criteria, UFC 4-023-03, Washington, DC. Dusenberry, D. (2002). Review of existing guidelines and provisions related to progressive collapse In: Worshop on prevention of progressive collapse, National Institute of Building Science, Washington, D.C,. Dusenberry, D. and Hamburger, R. (2006). Practical Means for Energy-Based Analyses of Disproportionate Collapse Potential. Journal of Performance of Constructed Facilities. 20(4), pp.336-348. Duthinh, D., Phan, L. and Simiu, E. (2013). Discussion of “Review of Methods to Assess, Design for, and Mitigate Multiple Hazards” by Yue Li, Aakash Ahuja, and Jamie E. Padgett. Journal of Performance of Constructed Facilities. 27(2), pp.215-216. Ellingwood, B. (2005). Strategies for Mitigating Risk of Progressive Collapse. In: Structures Congress 2005: American Society of Civil Engineers, pp.1-6. Ellingwood, B. (2006). Mitigating Risk from Abnormal Loads and Progressive Collapse. Journal of Performance of Constructed Facilities. 20(4), pp.315-323. Ellingwood, B., Marjanishvili, S., Mlakar, P., Sasani, M. and Williamson, E. (2009). Disproportionate Collapse Research Needs. In: Structures Congress pp.1-12. Ellingwood, B.R. and Dusenberry, D.O. (2005). Building Design for Abnormal Loads and Progressive Collapse. Computer-Aided Civil and Infrastructure Engineering. 20(3), pp.194-205. Ellingwood. B.R and Leyendecker E. V. (1978). Approaches for Design against Progressive Collapse. Journal of the Structural Division. 105(1), pp.413-423. Elsanadedy, H.M., Almusallam, T.H., Alharbi, Y.R., Al-Salloum, Y.A. and Abbas, H. (2014). Progressive collapse potential of a typical steel building due to blast attacks. Journal of Constructional Steel Research. 101, pp.143-157. EN1991 -1-7: (2006). Action on Structures - Part 1-7: General actions -accidental action. London, UK EN 1990: (2002). Eurocode: Basis for structural design. EN 1993-1-8. (2005).Design of steel structures. Brussels. England, J., Agarwal, J. and Blockley, D. (2008). The vulnerability of structures to unforeseen events. Computers and Structures. 86(10), pp.1042-1051. Faber, M. (2006). Robustness of structures: an introduction. Structural Engineering International. 16(2), pp.101-107. FEMA 356. (2000).Prestandard and commentary for the seismic rehabilitation of buildings.Reston, Virginia. FEMA 427. (2003).Primer for Design of Commercial Buildings to Mitigate Terrorist Attacks. Risk Mangement Series. Feng, J. and Cai, J. (2009). Progressive Collapse of Cable-Stayed Bridges. In: International Conference on Transportation Engineering pp.2483-2489. Fontaine, M. and Steinemann, A. (2009). Assessing Vulnerability to Natural Hazards: Impact-Based Method and Application to Drought in Washington State. Natural Hazards Review. 10(1), pp.11-18. Formisano, A., Landolfo, R. and Mazzolani, F.M. (2015). Robustness assessment approaches for steel framed structures under catastrophic events. Computers and Structures. 147, pp.216-228. Fu, F. (2010). 3-D nonlinear dynamic progressive collapse analysis of multi-storey steel composite frame buildings — Parametric study. Engineering Structures. 32(12), pp.3974-3980. Fu, F. (2012). Response of a multi-storey steel composite building with concentric bracing under consutive column removal scenarios. Journal of Constructional Steel Research. 70, pp.115-126. Galvão, A.S., Silva, A.R.D., Silveira, R.A.M. and Gonçalves, P.B. (2010). Nonlinear dynamic behaviour and instability of slender frames with semi-rigid connections. International Journal of Mechanical Sciences. 52(12), pp.1547-1562. Garlock, M., Ricles, J. and Sause, R. (2003). Cyclic Load Tests and Analysis of Bolted Top-and-Seat Angle Connections. Journal of Structural Engineering. 129(12), pp.1615-1625. General Service Administration (GSA). (2003). Progressive collapse analysis and design guidelines for new federal office buildings and major modernization projects, U.S. General Service Administration, Washington, DC. Gerasimidis, S. and Baniotopoulos, C.C. (2011). Steel moment frames column loss analysis: The influence of time step size. Journal of Constructional Steel Research. 67(4), pp.557-564. Ghobarah, A., Korol, R. and Osman, A. (1992). Cyclic Behaviour of Extended End‐Plate Joints. Journal of Structural Engineering. 118(5), pp.1333-1353. Godschalk, D. (2003). Urban Hazard Mitigation: Creating Resilient Cities. Natural Hazards Review. 4(3), pp.136-143. Goel, R.K. (1997). Period Formulas for Moment-Resisting Frame Buildings. Journal of Structural Engineering. 123(11), pp.1454-1461. Goverdham, A.V. (1983). A collection of experimental moment rotation curves and evaluation of prediction equations for semi rigid connections, In partial fulfilment for the award of Master of Science. Master of Science thesis, Vanderbilt University, at Nashville, Tenn. Goverdhan, A.V. (1983). A collection of experimental moment-rotation curves and evaluation of prediction equations for semi-rigid connections. M. Sc. thesis, Vanderbilt University. Griffiths, H., Pugsley, A. G., and Saunders, O. (1968). Report of the inquiry into the collapse of flats at Ronan Point, Canning Town. Her Majesty’s Stationery Office,. In: London. Gross, J. and McGuire, W. (1983). Progressive Collapse Resistant Design. Journal of Structural Engineering. 109(1), pp.1-15. GSA. (2013).General Service Admnistration, Alternate Path Analysis and Design Guidelines for Progressive Collapse Resistance. Hadi, M.N.S. and Alrudaini, T.M.S. (2011). Preventing the Progressive Collapse of Reinforced Concrete Buildings. In: Proceedings of the thirteenth international conference on civil, structural and environmental engineering computing, UK. Civil-Comp Press, Stirlingshire. Hadianfard, M.A. and Razani, R. (2003). Effects of semi-rigid behaviour of connections in the reliability of steel frames. Structural Safety. 25(2), pp.123-138. Hartmann, D., Breidt, M., Nguyen, V., Stangenberg, F. and Höhler, S., Schweizerhof, K. (2008). Structural collapse simulation under consideration of uncertainty - Fundamental concept and results. Computer Structure. 86, pp.2064-2078. Hueste, M.B.D. and Bai, J.-W. (2007). Seismic retrofit of a reinforced concrete flat-slab structure: Part I — seismic performance evaluation. Engineering Structures. 29(6), pp.1165-1177. Humay, F.K. and Baldridge, S.M. (2005). Multi Hazard Approach to Progressive Collapse Mitigation. In: Structures Congress pp.1-12. Izzuddin, B.A., Vlassis, A.G., Elghazouli, A.Y. and Nethercot, D.A. (2008). Progressive collapse of multi-storey buildings due to sudden column loss — Part I: Simplified assessment framework. Engineering Structures. 30(5), pp.1308-1318. Jaspart, J.-P. (1988). Extending of the merchant-rankine formula for the assessment of the ultimate load of frames with semi-rigid joints. Journal of Constructional Steel Research. 11(4), pp.283-312. Jaspart, J.-P. and Maquoi, R. (1990). Guidelines for the design of braced frames with semi-rigid connections. Journal of Constructional Steel Research. 16(4), pp.319-328. Jenkins, W.M., Tong, C.S. and Prescott, A.T. (1986). Moment transmitting endplate connections in Steel construction, and a proposed basis for flush endplate design. The structural Engineer. 64A(5), pp.121-131. Jeong, S.-H. and Elnashai, A.S. (2007). Fragility relationships for torsionally-imbalanced buildings using three-dimensional damage characterization. Engineering Structures. 29(9), pp.2172-2182. Kim, J. and Park, J., (2008). Design of steel moment frames considering progressive collapse. Steel and Composite Structures, 8(1), pp.85-98. Kim, J., Ghaboussi, J. and Elnashai, A.S. (2010). Mechanical and informational modeling of steel beam-to-column connections. Engineering Structures. 32(2), pp.449-458. Kaewkulchai, G. and Williamson, E.B. (2004). Beam element formulation and solution procedure for dynamic progressive collapse analysis. Computers and Structures. 82(7–8), pp.639-651. Khandelwal, K., El-Tawil, S., Kunnath, S. and Lew, H. (2008). Macromodel-Based Simulation of Progressive Collapse: Steel Frame Structures. Journal of Structural Engineering. 134(7), pp.1070-1078. Khandelwal, K., El-Tawil, S. and Sadek, F. (2009). Progressive collapse analysis of seismically designed steel braced frames. Journal of Constructional Steel Research. 65(3), pp.699-708. Kim, H.-S., Kim, J. and An, D.-W. (2009). Development of integrated system for progressive collapse analysis of building structures considering dynamic effects. Advances in Engineering Software. 40(1), pp.1-8. Kim, J. and Choi, H. (2004). Behaviour and design of structures with buckling-restrained braces. Engineering Structures. 26(6), pp.693-706. Kim, J. and Kim, T. (2009a). Assessment of progressive collapse-resisting capacity of steel moment frames. Journal of Constructional Steel Research. 65(1), pp.169-179. Kim, T. and Kim, J. (2009b). Collapse analysis of steel moment frames with various seismic connections. Journal of Constructional Steel Research. 65(6), pp.1316-1322. Kishi, N. and Chen, W. (1990). Moment‐Rotation Relations of Semirigid Connections with Angles. Journal of Structural Engineering. 116(7), pp.1813-1834. Kokot, S., Anthoine, A., Negro, P. and Solomos, G. (2012). Static and dynamic analysis of a reinforced concrete flat slab frame building for progressive collapse. Engineering Structures. 40, pp.205-217. Kwasniewski, L. (2010). Nonlinear dynamic simulations of progressive collapse for a multistory building. Engineering Structures. 32(5), pp.1223-1235. Lee, C.-H., Kim, S., Han, K.-H. and Lee, K. (2009). Simplified nonlinear progressive collapse analysis of welded steel moment frames. Journal of Constructional Steel Research. 65(5), pp.1130-1137. Lee, K., Kim, J., Hall, B.E., Karns, J.E. and Houghton, D.L. (2007). Analytical Verification of Blast Testing of Steel Frame Moment Connection Assemblies. Structural Engineering Research Frontiers. pp.1-19. Lew, H., Main, J., Robert, S., Sadek, F. and Chiarito, V. (2012). Performance of Steel Moment Connections under a Column Removal Scenario. I: Experiments. Journal of Structural Engineering. 139(1), pp.98-107. Lew, H., Main, J., Robert, S., Sadek, F. and Chiarito, V. (2013). Performance of Steel Moment Connections under a Column Removal Scenario. I: Experiments. Journal of Structural Engineering. 139(1), pp.98-107. Li, Y., Ahuja, A. and Padgett, J. (2012). Review of Methods to Assess, Design for, and Mitigate Multiple Hazards. Journal of Performance of Constructed Facilities. 26(1), pp.104-117. Li, Y. and Padgett, J. (2013). Closure to “Review of Methods to Assess, Design for, and Mitigate Multiple Hazards” by Yue Li, Aakash Ahuja, and Jamie E. Padgett. Journal of Performance of Constructed Facilities. 27(2), pp.216-216. Liu, J.L. (2010). Preventing progressive collapse through strengthening beam-to-column connection, Part 2: Finite element analysis. Journal of Constructional Steel Research. 66(2), pp.238-247. Liu, M. (2013). A new dynamic increase factor for nonlinear static alternate path analysis of building frames against progressive collapse. Engineering Structures. 48, pp.666-673. Liu, R., Davison, B. and Tyas, A. (2005). A Study of Progressive Collapse in Multi-Storey Steel Frames. Structures Congress pp.1-9. Liu Y, Xu L and Grierson D.E. (2010). Influence of Semi-Rigid Connections and Local Joint Damage on Progressive Collapse of Steel Frameworks. Computer - Aided Civil and Infrastructural Engineering. 25(3), pp.pp184-204. Lu, L.-W., Ricles, J.M., Mao, C. and Fisher, J.W. (2000). Critical issues in achieving ductile behaviour of welded moment connections. Journal of Constructional Steel Research. 55(1–3), pp.325-341. Maggi, Y.I., Gonçalves, R.M., Leon, R.T. and Ribeiro, L.F.L. (2005). Parametric analysis of steel bolted end plate connections using finite element modeling. Journal of Constructional Steel Research. 61(5), pp.689-708. Mahin, S.A. (1998). Lessons from damage to steel buildings during the Northridge earthquake. Engineering Structures. 20(4–6), pp.261-270. Malla, R.B., Agarwal, P. and Ahmad, R. (2011). Dynamic analysis methodology for progressive failure of truss structures considering inelastic postbuckling cyclic member behaviour. Engineering Structures. 33(5), pp.1503-1513. Marjanishvili, S. (2004). Progressive Analysis Procedure for Progressive Collapse. Journal of Performance of Constructed Facilities. 18(2), pp.79-85. Marjanishvili, S. and Agnew, E. (2006). Comparison of Various Procedures for Progressive Collapse Analysis. Journal of Performance of Constructed Facilities. 20(4), pp.365-374. Marjanishvili, S. and Buscemi, N. (2005). SDOF Model for Progressive Collapse Analysis. Structures Congress. pp.1-12. Mark Adom-Asamoah and Ankamah, N.O. (2016). Effect of Design Ductility on the Progressive Collapse Potential of RC Frame Structures Designed to Eurocode 8. American Journal of Civil Engineering. 4(2), pp. 40-49. Mashaly, E., El-Heweity, M., Abou-Elfath, H. and Osman, M. (2011). Finite element analysis of beam-to-column joints in steel frames under cyclic loading. Alexandria Engineering Journal. 50(1), pp.91-104. McKay, A., Marchand, K. and Diaz, M. (2012). Alternate Path Method in Progressive Collapse Analysis: Variation of Dynamic and Nonlinear Load Increase Factors. Practice Periodical on Structural Design and Construction. 17(4), pp.152-160. Mitchell, D. and Cook, W. (1984). Preventing Progressive Collapse of Slab Structures. Journal of Structural Engineering. 110(7), pp.1513-1532. Mlakar, P. (2005). The Pentagon Building Performance Study. Journal of Performance of Constructed Facilities. 19(3), pp.188-188. Mohamadi-Shoore, M.R. and Mofid, M. (2011). New modeling for moment–rotation behaviour of bolted endplate connections. Scientia Iranica. 18(4), pp.827-834. Mohamadi-Shooreh, M., Mofid, M. and McCabe, S.L. (2013). Empirical Model of the Moment-Rotation Curve of Beam-to-Beam Bolted Flush Endplate Connections. Journal of Structural Engineering. 139(1), pp.66-72. Mohamadi-shooreh, M.R. and Mofid, M. (2008). Parametric analyses on the initial stiffness of flush end-plate splice connections using FEM. Journal of Constructional Steel Research. 64(10), pp.1129-1141. Mohamed, O. (2006). Progressive Collapse of Structures: Annotated Bibliography and Comparison of Codes and Standards. Journal of Performance of Constructed Facilities. 20(4), pp.418-425. Mohamed, O.A. (2009). Assessment of progressive collapse potential in corner floor panels of reinforced concrete buildings. Engineering Structures. 31(3), pp.749-757. Möller, B., Liebscher, M., Schweizerhof, K., Mattern, S. and Blankenhorn, G. (2008). Structural collapse simulation under consideration of uncertainty - Improvement of numerical efficiency. Comput Struct. 86, pp.1875-1884. Morris, G.A. and Packer, J.A. (1987). Beam-to-column connections in steel frames. Canadian Journal of Civil Engineering. 14(1), pp.68-76. Nair, R. (2006). Preventing Disproportionate Collapse. Journal of Performance of Constructed Facilities. 20(4), pp.309-314. Nair, R.S. (2004). Progressive collapse basics,. In: The Steel Conference, Mordern Steel Construction, North America. pp.1-3. Neal, M., Garlock, M., Quiel, S. and Marjanishvili, S. (2012). Effects of Fire on a Tall Steel Building Designed to Resist Progressive Collapse. Structures Congress pp.246-256. NEHRP. (1994) Building Seismic Safety Council. Recommended provisions for the development of seismic regulations for new buildings.Washington. D.C. Nethercot, D.A. (2011). Design of Building Structures to Improve their Resistance to Progressive Collapse. Procedia Engineering. 14, pp.1-13. NIST. (2007).Best Practices for Reducing the Potential for Progressive Collapse in Buildings. National Institute of Standards and Technology (NIST) Washinton, D.C: Technology Administration, Department of Commerce, U.S Osteraas, J. (2006). Murrah Building Bombing Revisited: A Qualitative Assessment of Blast Damage and Collapse Patterns. Journal of Performance of Constructed Facilities. 20(4), pp.330-335. Park, J. and Kim, J. (2010). Fragility analysis of steel moment frames with various seismic connections subjected to sudden loss of a column. Engineering Structures. 32(6), pp.1547-1555. Pearson, C. and Delatte, N. (2003). Lessons from the Progressive Collapse of the Ronan Point Apartment Tower. Forensic Engineering pp.190-200. Pearson, C. and Delatte, N. (2005). Ronan Point Apartment Tower Collapse and its Effect on Building Codes. Journal of Performance of Constructed Facilities. 19(2), pp.172-177. Picard, A., Giroux, Y.-M. and P.Brun. (1976). Analysis of flexibly connected steel frames: Discussion. Canadian Journal of Civil Engineering. 3(2), pp.350-352. Powell, G. (2005). Progressive Collapse: Case studies Using Nonlinear Analysis. In: Structures Congress 2005, pp.1-14. Prabha, P., Marimuthu, V., Saravanan, M. and Arul Jayachandran, S. (2010). Evaluation of connection flexibility in cold formed steel racks. Journal of Constructional Steel Research. 66(7), pp.863-872. Prater, C. and Lindell, M. (2000). Politics of Hazard Mitigation. Natural Hazards Review. 1(2), pp.73-82. Pujol, S. and Paul Smith-Pardo, J. (2009). A new perspective on the effects of abrupt column removal. Engineering Structures. 31(4), pp.869-874. Qian, J., Yu, H., Yan, F., Dong, H., Li, J. and Liu, Y. (2005). Experimental study on full-scale steel beam-to-column moment connections. Earthquake Engineering and Engineering Vibration. 4(2), pp.311-323. Richard R. M. and Abbot B. J. (1975). Versatile elastic-plastic stress-strain formula. Journal of the Engineering Mechanics Division. 101(4), pp.511-515. Ruth, P., Marchand, K. and Williamson, E. (2006). Static Equivalency in Progressive Collapse Alternate Path Analysis: Reducing Conservatism while Retaining Structural Integrity. Journal of Performance of Constructed Facilities. 20(4), pp.349-364. Sadek, F., Main, J., Lew, H. and El-Tawil, S. (2012). Performance of Steel Moment Connections under a Column Removal Scenario. II: Analysis. Journal of Structural Engineering. 139(1), pp.108-119. Salama, I.M. (2015). Estimation of period of vibration for concrete moment-resisting frame buildings. HBRC Journal. 11(1), pp.16-21. Samuel Tan and Astaneh-Asl, A. (2003). Use of steel cables to prevent progressive collapse of existing buildings. In: Proceedings of sixth conference on tall buildings in seismic regions, Los Angeles, California,. pp.1-20. SAP 2000.Integrated software for structural analysis and design. Computers and Structures. Berkeley, California. SEI/ASCE 7-05. American Society of Civil Engineers. Minimum Design Loads for Building and Other Structures Reston (VA, USA). Sherbourne, A. and Bahaari, M. (1994). 3D Simulation of End‐Plate Bolted Connections. Journal of Structural Engineering. 120(11), pp.3122-3136. Sherbourne, A. and Bahaari, M. (1997). Finite Element Prediction of End Plate Bolted Connection Behaviour. I: Parametric Study. Journal of Structural Engineering. 123(2), pp.157-164. Shi, Y., Chan, S. and Wong, Y. (1996). Modeling for Moment-Rotation Characteristics for End-Plate Connections. Journal of Structural Engineering. 122(11), pp.1300-1306. Simões da Silva, L., Santiago, A. and Vila Real, P. (2001). A component model for the behaviour of steel joints at elevated temperatures. Journal of Constructional Steel Research. 57(11), pp.1169-1195. Sozen, Thornton, C., Corley, W. and Sr. (1998). The Oklahoma City Bombing: Structure and Mechanisms of the Murrah Building. Journal of Performance of Constructed Facilities. 12(3), pp.120-136. Starossek, U. and Haberland, M. (2009). Evaluating Measures of Structural Robustness. In: Structures Congress 2009, pp.1-8. Stephen, D., Ye, J. and Lam, D. (2011). Realistic Modelling of High Rise Steel Structures subjected to progressive collapse. In: Thirteenth International Conference on Civil, Structural and Environmental Engineering Computing, UK: Civil Comp Press,Stirlingshire UK. Stephen, D., Ye, J. and Lam, D. (2012). Progressive Collapse Evaluation of High Rise Steel Structures due to Sudden Loss of Structural Members. In: 10th International Conference on Advances in steel Concrete Composite and Hybrid Structures, Singapore. pp.1179-1186. Stephen, O.D., Lam, D. and Toropov, V.V. (2013). Assessment of column removal time for progressive collapse evaluation of high rise structures. Research and Applications in Structural Engineering, Mechanics and Computation. CRC Press, pp.699-704. Stevens, D., Crowder, B., Sunshine, D., Marchand, K., Smilowitz, R., Williamson, E. and Waggoner, M. (2011). DoD Research and Criteria for the Design of Buildings to Resist Progressive Collapse. Journal of Structural Engineering. 137(9), pp.870-880. Tohidi, M., Yang, J. and Baniotopoulos, C. (2014b). Numerical evaluations of codified design methods for progressive collapse resistance of precast concrete cross wall structures. Engineering Structures. 76, pp.177-186. Tsai, M.-H. (2010). An analytical methodology for the dynamic amplification factor in progressive collapse evaluation of building structures. Mechanics Research Communications. 37(1), pp.61-66. Tsai, M.-H. (2012). A performance-based design approach for retrofitting regular building frames with steel braces against sudden column loss. Journal of Constructional Steel Research. 77, pp.1-11. Tsai, M.-H. and Lin, B.-H. (2009). Dynamic amplification factor for progressive collapse resistance analysis of an RC building. The Structural Design of Tall and Special Buildings. 18(5), pp.539-557. Türker, T. and Bayraktar, A. (2011). Experimental and numerical investigation of brace configuration effects on steel structures. Journal of Constructional Steel Research. 67(5), pp.854-865. Usmani, A.S., Chung, Y.C. and Torero, J.L. (2003). How did the WTC towers collapse: A new theory. Fire Safety Journal. 38, pp.501-533. Vlassis, A.G., Izzuddin, B.A., Elghazouli, A.Y. and Nethercot, D.A. (2006). Design Oriented Approach for Progressive Collapse Assessment of Steel Framed Buildings. Structural Engineering International. 16(2), pp.129-136 Vlassis, A.G., Izzuddin, B.A., Elghazouli, A.Y. and Nethercot, D.A. (2008). Progressive collapse of multi-storey buildings due to sudden column loss—Part II: Application. Engineering Structures. 30(5), pp.1424-1438. Vlassis, A.G., Izzuddin, B.A., Elghazouli, A.Y. and Nethercot, D.A. (2009). Progressive collapse of multi-storey buildings due to failed floor impact. Engineering Structures. 31(7), pp.1522-1534. Wada, A., Ohi, K., Suzuki, H., Kohno, M. and Sakumoto, Y. (2004). A Study on the Collapse Control Design Method for High-Rise Steel Buildings. Structural Engineering International. 16(2), pp.137-141. Xu, G. and Ellingwood, B.R. (2011). Disproportionate collapse performance of partially restrained steel frames with bolted T-stub connections. Engineering Structures. 33(1), pp.32-43. Yang, B. and Tan, K. (2012a). Robustness of Bolted-Angle Connections against Progressive Collapse: Experimental Tests of Beam-Column Joints and Development of Component-Based Models. Journal of Structural Engineering. 139(9), pp.1498-1514. Yang, B. and Tan, K.H. (2012b). Numerical analyses of steel beam–column joints subjected to catenary action. Journal of Constructional Steel Research. 70, pp.1-11. Yang, B. and Tan, K.H. (2013). Experimental tests of different types of bolted steel beam–column joints under a central-column-removal scenario. Engineering Structures. 54, pp.112-130. Yang, B., Tan, K.H. and Xiong, G. (2015). Behaviour of composite beam–column joints under a middle-column-removal scenario: Component-based modelling. Journal of Constructional Steel Research. 104, pp.137-154. Yee, Y. and Melchers, R. (1986). Moment‐rotation curves for bolted connections. Journal of Structural Engineering. 112(3), pp.615-635. Yu, H., Burgess, I.W., Davison, J.B. and Plank, R.J. (2009). Tying capacity of web cleat connections in fire, Part 2: Development of component-based model. Engineering Structures. 31(3), pp.697-708. Yu, M., Zha, X. and Ye, J. (2010). The influence of joints and composite floor slabs on effective tying of steel structures in preventing progressive collapse. Journal of Constructional Steel Research. 66(3), pp.442-451."]},{"key":"dc:type","label":"Dc Type","values":["Thesis"]},{"key":"dc:type.qualificationlevel","label":"Dc Type Qualificationlevel","values":["doctoral"]},{"key":"dc:type.qualificationname","label":"Dc Type Qualificationname","values":["Ph.D"]}]},{"id":"language_rights","label":"Language and Rights","entries":[{"key":"dc:language.dcterms_iso639_2","label":"Language (ISO 639-2)","values":["eng"]}]},{"id":"identifiers","label":"Identifiers","entries":[{"key":"dc:identifier","label":"Identifier","values":["uk.bl.ethos.718806"]},{"key":"dc:identifier.uri","label":"Identifier URI","values":["https://etheses.whiterose.ac.uk/id/eprint/17769/1/Stephen_D.0_Civil%20Engineering_PhD_2017.pdf"]}]},{"id":"additional","label":"Additional Metadata","entries":[{"key":"dc:description.abstract","label":"Abstract","values":["The collapse of buildings over the last century as a result of abnormal loads has renewed interest in the field of structural engineering. Key events such as the disproportionate collapse of the Ronan Point building in London, the collapse of the Alfred Murray Building and the World Trade Centre are structural failures that have triggered more research into progressive collapse. Consequently, new design guidelines around the globe with a prescriptive recommendation for improving structural integrity based on tying force provision have been developed. However, in existing design guidelines and codes throughout the world, there is a lack of a codified modelling technique for progressive collapse. As a result of this limitation, researchers adopt different methods. Generally, during the progressive collapse, structural members experiencing significant displacements and rotations, while the beam-column connections are subjected to large tensile forces not envisaged at the conventional design phase. Hence, this study presents an assessment of the effect of column removal time, the modelling techniques and the susceptibility of simple connections designed to Eurocode 3 Part: 1-8 to progressive collapse. A computationally efficient approach and column removal time for progressive collapse assessment are proposed. The findings show that a braced framed system is likely to exhibit at least 35% progressive collapse when compared with a moment resisting frame system using the joint displacement and rotation criteria. Furthermore, the research shows that the UK tie provision in EN1991-1-7 underestimates the magnitude of the catenary force developed under the progressive collapse scenario. Consequently, the connection is disposed to progressive collapse with the shear force in the column and catenary action in the beam as the critical internal forces. Based on this assessment, five times the tensile force specified in EC3 for tensile force connection design checks is recommended. Shear force in the column and catenary force action in the beam are the internal governing forces that determine the maximum dynamic amplification factor of a simple connection. The work provides evidence that the tie beam-column web connection at the corner column is more critical under progressive collapse scenario as compared with the primary beam. Column web failure in yielding is attributed to the large catenary force developed in the tie beam connected to the web of the column."]},{"key":"dc:format","label":"Dc Format","values":["text"]},{"key":"dcterms:accessrights","label":"Dcterms Accessrights","values":["public"]},{"key":"dc:title","label":"Title","values":["Progressive collapse assessment of structures"]}]}],"canonical_facts":{"dc:contributor.advisor":["Forth, John","Lam, Dennis","Tsavdaridis, Konstantinos Daniel"],"dc:contributor.sponsor":["Petroleum Technology Development Fund (PTDF)"],"dc:creator":["Stephen, David Ojonimi"],"dc:date":["2017-01"],"dc:date.issued":["2017-01"],"dc:description.abstract":["The collapse of buildings over the last century as a result of abnormal loads has renewed interest in the field of structural engineering. Key events such as the disproportionate collapse of the Ronan Point building in London, the collapse of the Alfred Murray Building and the World Trade Centre are structural failures that have triggered more research into progressive collapse. Consequently, new design guidelines around the globe with a prescriptive recommendation for improving structural integrity based on tying force provision have been developed. However, in existing design guidelines and codes throughout the world, there is a lack of a codified modelling technique for progressive collapse. As a result of this limitation, researchers adopt different methods. Generally, during the progressive collapse, structural members experiencing significant displacements and rotations, while the beam-column connections are subjected to large tensile forces not envisaged at the conventional design phase. Hence, this study presents an assessment of the effect of column removal time, the modelling techniques and the susceptibility of simple connections designed to Eurocode 3 Part: 1-8 to progressive collapse. A computationally efficient approach and column removal time for progressive collapse assessment are proposed. The findings show that a braced framed system is likely to exhibit at least 35% progressive collapse when compared with a moment resisting frame system using the joint displacement and rotation criteria. Furthermore, the research shows that the UK tie provision in EN1991-1-7 underestimates the magnitude of the catenary force developed under the progressive collapse scenario. Consequently, the connection is disposed to progressive collapse with the shear force in the column and catenary action in the beam as the critical internal forces. Based on this assessment, five times the tensile force specified in EC3 for tensile force connection design checks is recommended. Shear force in the column and catenary force action in the beam are the internal governing forces that determine the maximum dynamic amplification factor of a simple connection. The work provides evidence that the tie beam-column web connection at the corner column is more critical under progressive collapse scenario as compared with the primary beam. Column web failure in yielding is attributed to the large catenary force developed in the tie beam connected to the web of the column."],"dc:format":["text"],"dc:identifier":["uk.bl.ethos.718806"],"dc:identifier.uri":["https://etheses.whiterose.ac.uk/id/eprint/17769/1/Stephen_D.0_Civil%20Engineering_PhD_2017.pdf"],"dc:language.dcterms_iso639_2":["eng"],"dc:publisher.commercial":["University of Leeds"],"dc:publisher.department":["Faculty of Engineering (Leeds)","School of Civil Engineering (Leeds)"],"dc:publisher.institution":["University of Leeds"],"dc:relation.isreferencedby":["https://etheses.whiterose.ac.uk/id/eprint/17769/"],"dc:relation.references":["REFERENCES ABAQUS (2011). ABAQUS Documentation, Dassault Systèmes, Providence, RI ,USA. Abolmaali, A., Matthys, J.H., Farooqi, M. and Choi, Y. (2005). Development of moment–rotation model equations for flush end-plate connections. Journal of Constructional Steel Research. 61(12), pp.1595-1612. Abruzzo, J., Matta, A. and Panariello, G. (2006). Study of Mitigation Strategies for Progressive Collapse of a Reinforced Concrete Commercial Building. Journal of Performance of Constructed Facilities. 20(4), pp.384-390. Adey, B.T., Grondin, G.Y. and Cheng, J.J. (2000). Cyclic loading of end plate moment connections. Canadian Journal of Civil Engineering. 27(4), pp.683-701. Agarwal, A. and Varma, A.H. (2014). Fire induced progressive collapse of steel building structures: The role of interior gravity columns. Engineering Structures. 58, pp.129-140. Agarwal, J. and England, J. (2008). Recent developments in robustness and relation with risk. In: Proceedings of the ICE - Structures and Buildings, pp.183-188. Aggarwal, A.K. (1994). Comparative tests on endplate beam-to-column connections. Journal of Constructional Steel Research. 30(2), pp.151-175. Alashker, Y. and El-Tawil, S. (2010). Design Model for Collapse Capacity of Composite Floors. In: Structures Congress 2010. pp.1160-1170. Alexander, S. (2004). New approach to disproportionate collapse. The Structural Engineer. 7(23), pp.14 - 18. Ang, K.M. and Morris, G.A. (1984). Analysis of three-dimensional frames with flexible beam–column connections. Canadian Journal of Civil Engineering. 11(2), pp.245-254. Aristizabal-Ochoa, J.D. (2010). Second-order slope–deflection equations for imperfect beam–column structures with semi-rigid connections. Engineering Structures. 32(8), pp.2440-2454. Arros, J. and Doumbalski, N. (2007). Analysis of aircraft impact to concrete structures. Nuclear Engineering and Design. 237(12–13), pp.1241-1249. Ashraf, M., Nethercot, D.A. and Ahmed, B. (2007). Sway of semi-rigid steel frames, part 2: Irregular frames. Engineering Structures. 29(8), pp.1854-1863. Azizinamini, A., Bradburn, J.H., Radziminski, J.B. (1985). Static and Cyclic Behavior of Semi-rigid Steel Beam-column Connections: Final Report : a Report of an Investigation Conducted by the Civil Engineering Department, University of South Carolina. University of South Carolina. Baker, J.W., Schubert, M. and Faber, M.H. (2008). On the assessment of robustness. Structural Safety. 30(3), pp.253-267. Bao, Y., Kunnath, S., El-Tawil, S. and Lew, H. (2008). Macromodel-Based Simulation of Progressive Collapse: RC Frame Structures. Journal of Structural Engineering. 134(7), pp.1079-1091. Bayo, E., Cabrero, J.M. and Gil, B. (2006). An effective component-based method to model semi-rigid connections for the global analysis of steel and composite structures. Engineering Structures. 28(1), pp.97-108. Bažant, Z. and Zhou, Y. (2002). Why Did the World Trade Centre Collapse?—Simple Analysis. Journal of Engineering Mechanics. 128(1), pp.2-6. Beeby, A.W. (1999). Safety of structures, and a new approach to robustness. The Structural Engineer. 77(4), pp.16-19. Bennetts, I.D. and Thomas, I.R. (2002). Design of steel structures under fire conditions. Progress in Structural Engineering and Materials. 4(1), pp.6-17. Biondini, F., Frangopol, D.M. and Restelli, S. (2008). On Structural Robustness, Redundancy, and Static Indeterminacy. In: Structures Congress 2008 pp.1-10. Bjorhovde, R., Colson, A. and Brozzetti, J. (1990). Classification System for Beam‐to‐Column Connections. Journal of Structural Engineering. 116(11), pp.3059-3076. Bose, B., Wang, Z. and Sarkar, S. (1997). Finite-Element Analysis of Unstiffened Flush End-Plate Bolted Joints. Journal of Structural Engineering. 123(12), pp.1614-1621. Braham, M. and Jaspart, J.-P. (2004). Is it safe to design a building structure with simple joints, when they are known to exhibit a semi-rigid behaviour? Journal of Constructional Steel Research. 60(3–5), pp.713-723. British Standards Institution. (2005).European committee for standardization. Eurocode 3: design of steel structures-Part1-1: general rules and rules for buildings, BS EN 1993-1-1:2005. UK. BS5950. (2001). Structural use of steelworks in building. Part 1: Code of practice for the design of simple and continuous costruction: Hot rolled section. London. BS 8110. (1997). The structural use of concrete in building - Part 1: Code of practice for design construction. London, UK Bursi, O.S. and Jaspart, J.P. (1998). Basic issues in the finite element simulation of extended end plate connections. Computers and Structures. 69(3), pp.361-382. Buscemi, N. and Marjanishvili, S. (2005). SDOF Model for Progressive Collapse Analysis. In: Structures Congress pp.1-12. Cabrero, J.M. and Bayo, E. (2005). Development of practical design methods for steel structures with semi-rigid connections. Engineering Structures. 27(8), pp.1125-1137. Cabrero, J.M. and Bayo, E. (2007). The semi-rigid behaviour of three-dimensional steel beam-to-column steel joints subjected to proportional loading. Part II: Theoretical model and validation. Journal of Constructional Steel Research. 63(9), pp.1254-1267. Cabrero, J.M. and Bayo, E. (2007). The semi-rigid behaviour of three-dimensional steel beam-to-column joints subjected to proportional loading. Part I. Experimental evaluation. Journal of Constructional Steel Research. 63(9), pp.1241-1253. CEN. (1994).General Actions - Accidental actions Eurocode 1 - Actions on structures - Part 1- Basis of Design, European Pre Standard ENV 1991-1, Comite Europeen de Normalaization 250.Brussels, Belgium. Chen, W. and Kishi, N. (1989). Semirigid Steel Beam‐to‐Column Connections: Data Base and Modeling. Journal of Structural Engineering. 115(1), pp.105-119. Choi, H.-J., Magallanes, J.M. and Crawford, J.E. (2007). Incorporating Uncertainties in the Blast-Resistant Design. In: New Horizons and Better Practices, pp.1-9. Corley, W., Sr., P., Sozen, M. and Thornton, C. (1998). The Oklahoma City Bombing: Summary and Recommendations for Multihazard Mitigation. Journal of Performance of Constructed Facilities. 12(3), pp.100-112. da S. Vellasco, P.C.G., de Andrade, S.A.L., da Silva, J.G.S., de Lima, L.R.O. and Brito Jr, O. (2006). A parametric analysis of steel and composite portal frames with semi-rigid connections. Engineering Structures. 28(4), pp.543-556. da Silva, J.G.S., de Lima, L.R.O., da S. Vellasco, P.C.G., de Andrade, S.A.L. and de Castro, R.A. (2008). Nonlinear dynamic analysis of steel portal frames with semi-rigid connections. Engineering Structures. 30(9), pp.2566-2579. Díaz, C., Martí, P., Victoria, M. and Querin, O.M. (2011). Review on the modelling of joint behaviour in steel frames. Journal of Constructional Steel Research. 67(5), pp.741-758. Department of Defence (DoD), (2005). “Design of building to resist progressive collapse.” Unified Facility Criteria, UFC 4-023-03, Washington, DC. Department of Defence (DoD), (2009). “Design of building to resist progressive collapse.” Unified Facility Criteria, UFC 4-023-03, Washington, DC. Dusenberry, D. (2002). Review of existing guidelines and provisions related to progressive collapse In: Worshop on prevention of progressive collapse, National Institute of Building Science, Washington, D.C,. Dusenberry, D. and Hamburger, R. (2006). Practical Means for Energy-Based Analyses of Disproportionate Collapse Potential. Journal of Performance of Constructed Facilities. 20(4), pp.336-348. Duthinh, D., Phan, L. and Simiu, E. (2013). Discussion of “Review of Methods to Assess, Design for, and Mitigate Multiple Hazards” by Yue Li, Aakash Ahuja, and Jamie E. Padgett. Journal of Performance of Constructed Facilities. 27(2), pp.215-216. Ellingwood, B. (2005). Strategies for Mitigating Risk of Progressive Collapse. In: Structures Congress 2005: American Society of Civil Engineers, pp.1-6. Ellingwood, B. (2006). Mitigating Risk from Abnormal Loads and Progressive Collapse. Journal of Performance of Constructed Facilities. 20(4), pp.315-323. Ellingwood, B., Marjanishvili, S., Mlakar, P., Sasani, M. and Williamson, E. (2009). Disproportionate Collapse Research Needs. In: Structures Congress pp.1-12. Ellingwood, B.R. and Dusenberry, D.O. (2005). Building Design for Abnormal Loads and Progressive Collapse. Computer-Aided Civil and Infrastructure Engineering. 20(3), pp.194-205. Ellingwood. B.R and Leyendecker E. V. (1978). Approaches for Design against Progressive Collapse. Journal of the Structural Division. 105(1), pp.413-423. Elsanadedy, H.M., Almusallam, T.H., Alharbi, Y.R., Al-Salloum, Y.A. and Abbas, H. (2014). Progressive collapse potential of a typical steel building due to blast attacks. Journal of Constructional Steel Research. 101, pp.143-157. EN1991 -1-7: (2006). Action on Structures - Part 1-7: General actions -accidental action. London, UK EN 1990: (2002). Eurocode: Basis for structural design. EN 1993-1-8. (2005).Design of steel structures. Brussels. England, J., Agarwal, J. and Blockley, D. (2008). The vulnerability of structures to unforeseen events. Computers and Structures. 86(10), pp.1042-1051. Faber, M. (2006). Robustness of structures: an introduction. Structural Engineering International. 16(2), pp.101-107. FEMA 356. (2000).Prestandard and commentary for the seismic rehabilitation of buildings.Reston, Virginia. FEMA 427. (2003).Primer for Design of Commercial Buildings to Mitigate Terrorist Attacks. Risk Mangement Series. Feng, J. and Cai, J. (2009). Progressive Collapse of Cable-Stayed Bridges. In: International Conference on Transportation Engineering pp.2483-2489. Fontaine, M. and Steinemann, A. (2009). Assessing Vulnerability to Natural Hazards: Impact-Based Method and Application to Drought in Washington State. Natural Hazards Review. 10(1), pp.11-18. Formisano, A., Landolfo, R. and Mazzolani, F.M. (2015). Robustness assessment approaches for steel framed structures under catastrophic events. Computers and Structures. 147, pp.216-228. Fu, F. (2010). 3-D nonlinear dynamic progressive collapse analysis of multi-storey steel composite frame buildings — Parametric study. Engineering Structures. 32(12), pp.3974-3980. Fu, F. (2012). Response of a multi-storey steel composite building with concentric bracing under consutive column removal scenarios. Journal of Constructional Steel Research. 70, pp.115-126. Galvão, A.S., Silva, A.R.D., Silveira, R.A.M. and Gonçalves, P.B. (2010). Nonlinear dynamic behaviour and instability of slender frames with semi-rigid connections. International Journal of Mechanical Sciences. 52(12), pp.1547-1562. Garlock, M., Ricles, J. and Sause, R. (2003). Cyclic Load Tests and Analysis of Bolted Top-and-Seat Angle Connections. Journal of Structural Engineering. 129(12), pp.1615-1625. General Service Administration (GSA). (2003). Progressive collapse analysis and design guidelines for new federal office buildings and major modernization projects, U.S. General Service Administration, Washington, DC. Gerasimidis, S. and Baniotopoulos, C.C. (2011). Steel moment frames column loss analysis: The influence of time step size. Journal of Constructional Steel Research. 67(4), pp.557-564. Ghobarah, A., Korol, R. and Osman, A. (1992). Cyclic Behaviour of Extended End‐Plate Joints. Journal of Structural Engineering. 118(5), pp.1333-1353. Godschalk, D. (2003). Urban Hazard Mitigation: Creating Resilient Cities. Natural Hazards Review. 4(3), pp.136-143. Goel, R.K. (1997). Period Formulas for Moment-Resisting Frame Buildings. Journal of Structural Engineering. 123(11), pp.1454-1461. Goverdham, A.V. (1983). A collection of experimental moment rotation curves and evaluation of prediction equations for semi rigid connections, In partial fulfilment for the award of Master of Science. Master of Science thesis, Vanderbilt University, at Nashville, Tenn. Goverdhan, A.V. (1983). A collection of experimental moment-rotation curves and evaluation of prediction equations for semi-rigid connections. M. Sc. thesis, Vanderbilt University. Griffiths, H., Pugsley, A. G., and Saunders, O. (1968). Report of the inquiry into the collapse of flats at Ronan Point, Canning Town. Her Majesty’s Stationery Office,. In: London. Gross, J. and McGuire, W. (1983). Progressive Collapse Resistant Design. Journal of Structural Engineering. 109(1), pp.1-15. GSA. (2013).General Service Admnistration, Alternate Path Analysis and Design Guidelines for Progressive Collapse Resistance. Hadi, M.N.S. and Alrudaini, T.M.S. (2011). Preventing the Progressive Collapse of Reinforced Concrete Buildings. In: Proceedings of the thirteenth international conference on civil, structural and environmental engineering computing, UK. Civil-Comp Press, Stirlingshire. Hadianfard, M.A. and Razani, R. (2003). Effects of semi-rigid behaviour of connections in the reliability of steel frames. Structural Safety. 25(2), pp.123-138. Hartmann, D., Breidt, M., Nguyen, V., Stangenberg, F. and Höhler, S., Schweizerhof, K. (2008). Structural collapse simulation under consideration of uncertainty - Fundamental concept and results. Computer Structure. 86, pp.2064-2078. Hueste, M.B.D. and Bai, J.-W. (2007). Seismic retrofit of a reinforced concrete flat-slab structure: Part I — seismic performance evaluation. Engineering Structures. 29(6), pp.1165-1177. Humay, F.K. and Baldridge, S.M. (2005). Multi Hazard Approach to Progressive Collapse Mitigation. In: Structures Congress pp.1-12. Izzuddin, B.A., Vlassis, A.G., Elghazouli, A.Y. and Nethercot, D.A. (2008). Progressive collapse of multi-storey buildings due to sudden column loss — Part I: Simplified assessment framework. Engineering Structures. 30(5), pp.1308-1318. Jaspart, J.-P. (1988). Extending of the merchant-rankine formula for the assessment of the ultimate load of frames with semi-rigid joints. Journal of Constructional Steel Research. 11(4), pp.283-312. Jaspart, J.-P. and Maquoi, R. (1990). Guidelines for the design of braced frames with semi-rigid connections. Journal of Constructional Steel Research. 16(4), pp.319-328. Jenkins, W.M., Tong, C.S. and Prescott, A.T. (1986). Moment transmitting endplate connections in Steel construction, and a proposed basis for flush endplate design. The structural Engineer. 64A(5), pp.121-131. Jeong, S.-H. and Elnashai, A.S. (2007). Fragility relationships for torsionally-imbalanced buildings using three-dimensional damage characterization. Engineering Structures. 29(9), pp.2172-2182. Kim, J. and Park, J., (2008). Design of steel moment frames considering progressive collapse. Steel and Composite Structures, 8(1), pp.85-98. Kim, J., Ghaboussi, J. and Elnashai, A.S. (2010). Mechanical and informational modeling of steel beam-to-column connections. Engineering Structures. 32(2), pp.449-458. Kaewkulchai, G. and Williamson, E.B. (2004). Beam element formulation and solution procedure for dynamic progressive collapse analysis. Computers and Structures. 82(7–8), pp.639-651. Khandelwal, K., El-Tawil, S., Kunnath, S. and Lew, H. (2008). Macromodel-Based Simulation of Progressive Collapse: Steel Frame Structures. Journal of Structural Engineering. 134(7), pp.1070-1078. Khandelwal, K., El-Tawil, S. and Sadek, F. (2009). Progressive collapse analysis of seismically designed steel braced frames. Journal of Constructional Steel Research. 65(3), pp.699-708. Kim, H.-S., Kim, J. and An, D.-W. (2009). Development of integrated system for progressive collapse analysis of building structures considering dynamic effects. Advances in Engineering Software. 40(1), pp.1-8. Kim, J. and Choi, H. (2004). Behaviour and design of structures with buckling-restrained braces. Engineering Structures. 26(6), pp.693-706. Kim, J. and Kim, T. (2009a). Assessment of progressive collapse-resisting capacity of steel moment frames. Journal of Constructional Steel Research. 65(1), pp.169-179. Kim, T. and Kim, J. (2009b). Collapse analysis of steel moment frames with various seismic connections. Journal of Constructional Steel Research. 65(6), pp.1316-1322. Kishi, N. and Chen, W. (1990). Moment‐Rotation Relations of Semirigid Connections with Angles. Journal of Structural Engineering. 116(7), pp.1813-1834. Kokot, S., Anthoine, A., Negro, P. and Solomos, G. (2012). Static and dynamic analysis of a reinforced concrete flat slab frame building for progressive collapse. Engineering Structures. 40, pp.205-217. Kwasniewski, L. (2010). Nonlinear dynamic simulations of progressive collapse for a multistory building. Engineering Structures. 32(5), pp.1223-1235. Lee, C.-H., Kim, S., Han, K.-H. and Lee, K. (2009). Simplified nonlinear progressive collapse analysis of welded steel moment frames. Journal of Constructional Steel Research. 65(5), pp.1130-1137. Lee, K., Kim, J., Hall, B.E., Karns, J.E. and Houghton, D.L. (2007). Analytical Verification of Blast Testing of Steel Frame Moment Connection Assemblies. Structural Engineering Research Frontiers. pp.1-19. Lew, H., Main, J., Robert, S., Sadek, F. and Chiarito, V. (2012). Performance of Steel Moment Connections under a Column Removal Scenario. I: Experiments. Journal of Structural Engineering. 139(1), pp.98-107. Lew, H., Main, J., Robert, S., Sadek, F. and Chiarito, V. (2013). Performance of Steel Moment Connections under a Column Removal Scenario. I: Experiments. Journal of Structural Engineering. 139(1), pp.98-107. Li, Y., Ahuja, A. and Padgett, J. (2012). Review of Methods to Assess, Design for, and Mitigate Multiple Hazards. Journal of Performance of Constructed Facilities. 26(1), pp.104-117. Li, Y. and Padgett, J. (2013). Closure to “Review of Methods to Assess, Design for, and Mitigate Multiple Hazards” by Yue Li, Aakash Ahuja, and Jamie E. Padgett. Journal of Performance of Constructed Facilities. 27(2), pp.216-216. Liu, J.L. (2010). Preventing progressive collapse through strengthening beam-to-column connection, Part 2: Finite element analysis. Journal of Constructional Steel Research. 66(2), pp.238-247. Liu, M. (2013). A new dynamic increase factor for nonlinear static alternate path analysis of building frames against progressive collapse. Engineering Structures. 48, pp.666-673. Liu, R., Davison, B. and Tyas, A. (2005). A Study of Progressive Collapse in Multi-Storey Steel Frames. Structures Congress pp.1-9. Liu Y, Xu L and Grierson D.E. (2010). Influence of Semi-Rigid Connections and Local Joint Damage on Progressive Collapse of Steel Frameworks. Computer - Aided Civil and Infrastructural Engineering. 25(3), pp.pp184-204. Lu, L.-W., Ricles, J.M., Mao, C. and Fisher, J.W. (2000). Critical issues in achieving ductile behaviour of welded moment connections. Journal of Constructional Steel Research. 55(1–3), pp.325-341. Maggi, Y.I., Gonçalves, R.M., Leon, R.T. and Ribeiro, L.F.L. (2005). Parametric analysis of steel bolted end plate connections using finite element modeling. Journal of Constructional Steel Research. 61(5), pp.689-708. Mahin, S.A. (1998). Lessons from damage to steel buildings during the Northridge earthquake. Engineering Structures. 20(4–6), pp.261-270. Malla, R.B., Agarwal, P. and Ahmad, R. (2011). Dynamic analysis methodology for progressive failure of truss structures considering inelastic postbuckling cyclic member behaviour. Engineering Structures. 33(5), pp.1503-1513. Marjanishvili, S. (2004). Progressive Analysis Procedure for Progressive Collapse. Journal of Performance of Constructed Facilities. 18(2), pp.79-85. Marjanishvili, S. and Agnew, E. (2006). Comparison of Various Procedures for Progressive Collapse Analysis. Journal of Performance of Constructed Facilities. 20(4), pp.365-374. Marjanishvili, S. and Buscemi, N. (2005). SDOF Model for Progressive Collapse Analysis. Structures Congress. pp.1-12. Mark Adom-Asamoah and Ankamah, N.O. (2016). Effect of Design Ductility on the Progressive Collapse Potential of RC Frame Structures Designed to Eurocode 8. American Journal of Civil Engineering. 4(2), pp. 40-49. Mashaly, E., El-Heweity, M., Abou-Elfath, H. and Osman, M. (2011). Finite element analysis of beam-to-column joints in steel frames under cyclic loading. Alexandria Engineering Journal. 50(1), pp.91-104. McKay, A., Marchand, K. and Diaz, M. (2012). Alternate Path Method in Progressive Collapse Analysis: Variation of Dynamic and Nonlinear Load Increase Factors. Practice Periodical on Structural Design and Construction. 17(4), pp.152-160. Mitchell, D. and Cook, W. (1984). Preventing Progressive Collapse of Slab Structures. Journal of Structural Engineering. 110(7), pp.1513-1532. Mlakar, P. (2005). The Pentagon Building Performance Study. Journal of Performance of Constructed Facilities. 19(3), pp.188-188. Mohamadi-Shoore, M.R. and Mofid, M. (2011). New modeling for moment–rotation behaviour of bolted endplate connections. Scientia Iranica. 18(4), pp.827-834. Mohamadi-Shooreh, M., Mofid, M. and McCabe, S.L. (2013). Empirical Model of the Moment-Rotation Curve of Beam-to-Beam Bolted Flush Endplate Connections. Journal of Structural Engineering. 139(1), pp.66-72. Mohamadi-shooreh, M.R. and Mofid, M. (2008). Parametric analyses on the initial stiffness of flush end-plate splice connections using FEM. Journal of Constructional Steel Research. 64(10), pp.1129-1141. Mohamed, O. (2006). Progressive Collapse of Structures: Annotated Bibliography and Comparison of Codes and Standards. Journal of Performance of Constructed Facilities. 20(4), pp.418-425. Mohamed, O.A. (2009). Assessment of progressive collapse potential in corner floor panels of reinforced concrete buildings. Engineering Structures. 31(3), pp.749-757. Möller, B., Liebscher, M., Schweizerhof, K., Mattern, S. and Blankenhorn, G. (2008). Structural collapse simulation under consideration of uncertainty - Improvement of numerical efficiency. Comput Struct. 86, pp.1875-1884. Morris, G.A. and Packer, J.A. (1987). Beam-to-column connections in steel frames. Canadian Journal of Civil Engineering. 14(1), pp.68-76. Nair, R. (2006). Preventing Disproportionate Collapse. Journal of Performance of Constructed Facilities. 20(4), pp.309-314. Nair, R.S. (2004). Progressive collapse basics,. In: The Steel Conference, Mordern Steel Construction, North America. pp.1-3. Neal, M., Garlock, M., Quiel, S. and Marjanishvili, S. (2012). Effects of Fire on a Tall Steel Building Designed to Resist Progressive Collapse. Structures Congress pp.246-256. NEHRP. (1994) Building Seismic Safety Council. Recommended provisions for the development of seismic regulations for new buildings.Washington. D.C. Nethercot, D.A. (2011). Design of Building Structures to Improve their Resistance to Progressive Collapse. Procedia Engineering. 14, pp.1-13. NIST. (2007).Best Practices for Reducing the Potential for Progressive Collapse in Buildings. National Institute of Standards and Technology (NIST) Washinton, D.C: Technology Administration, Department of Commerce, U.S Osteraas, J. (2006). Murrah Building Bombing Revisited: A Qualitative Assessment of Blast Damage and Collapse Patterns. Journal of Performance of Constructed Facilities. 20(4), pp.330-335. Park, J. and Kim, J. (2010). Fragility analysis of steel moment frames with various seismic connections subjected to sudden loss of a column. Engineering Structures. 32(6), pp.1547-1555. Pearson, C. and Delatte, N. (2003). Lessons from the Progressive Collapse of the Ronan Point Apartment Tower. Forensic Engineering pp.190-200. Pearson, C. and Delatte, N. (2005). Ronan Point Apartment Tower Collapse and its Effect on Building Codes. Journal of Performance of Constructed Facilities. 19(2), pp.172-177. Picard, A., Giroux, Y.-M. and P.Brun. (1976). Analysis of flexibly connected steel frames: Discussion. Canadian Journal of Civil Engineering. 3(2), pp.350-352. Powell, G. (2005). Progressive Collapse: Case studies Using Nonlinear Analysis. In: Structures Congress 2005, pp.1-14. Prabha, P., Marimuthu, V., Saravanan, M. and Arul Jayachandran, S. (2010). Evaluation of connection flexibility in cold formed steel racks. Journal of Constructional Steel Research. 66(7), pp.863-872. Prater, C. and Lindell, M. (2000). Politics of Hazard Mitigation. Natural Hazards Review. 1(2), pp.73-82. Pujol, S. and Paul Smith-Pardo, J. (2009). A new perspective on the effects of abrupt column removal. Engineering Structures. 31(4), pp.869-874. Qian, J., Yu, H., Yan, F., Dong, H., Li, J. and Liu, Y. (2005). Experimental study on full-scale steel beam-to-column moment connections. Earthquake Engineering and Engineering Vibration. 4(2), pp.311-323. Richard R. M. and Abbot B. J. (1975). Versatile elastic-plastic stress-strain formula. Journal of the Engineering Mechanics Division. 101(4), pp.511-515. Ruth, P., Marchand, K. and Williamson, E. (2006). Static Equivalency in Progressive Collapse Alternate Path Analysis: Reducing Conservatism while Retaining Structural Integrity. Journal of Performance of Constructed Facilities. 20(4), pp.349-364. Sadek, F., Main, J., Lew, H. and El-Tawil, S. (2012). Performance of Steel Moment Connections under a Column Removal Scenario. II: Analysis. Journal of Structural Engineering. 139(1), pp.108-119. Salama, I.M. (2015). Estimation of period of vibration for concrete moment-resisting frame buildings. HBRC Journal. 11(1), pp.16-21. Samuel Tan and Astaneh-Asl, A. (2003). Use of steel cables to prevent progressive collapse of existing buildings. In: Proceedings of sixth conference on tall buildings in seismic regions, Los Angeles, California,. pp.1-20. SAP 2000.Integrated software for structural analysis and design. Computers and Structures. Berkeley, California. SEI/ASCE 7-05. American Society of Civil Engineers. Minimum Design Loads for Building and Other Structures Reston (VA, USA). Sherbourne, A. and Bahaari, M. (1994). 3D Simulation of End‐Plate Bolted Connections. Journal of Structural Engineering. 120(11), pp.3122-3136. Sherbourne, A. and Bahaari, M. (1997). Finite Element Prediction of End Plate Bolted Connection Behaviour. I: Parametric Study. Journal of Structural Engineering. 123(2), pp.157-164. Shi, Y., Chan, S. and Wong, Y. (1996). Modeling for Moment-Rotation Characteristics for End-Plate Connections. Journal of Structural Engineering. 122(11), pp.1300-1306. Simões da Silva, L., Santiago, A. and Vila Real, P. (2001). A component model for the behaviour of steel joints at elevated temperatures. Journal of Constructional Steel Research. 57(11), pp.1169-1195. Sozen, Thornton, C., Corley, W. and Sr. (1998). The Oklahoma City Bombing: Structure and Mechanisms of the Murrah Building. Journal of Performance of Constructed Facilities. 12(3), pp.120-136. Starossek, U. and Haberland, M. (2009). Evaluating Measures of Structural Robustness. In: Structures Congress 2009, pp.1-8. Stephen, D., Ye, J. and Lam, D. (2011). Realistic Modelling of High Rise Steel Structures subjected to progressive collapse. In: Thirteenth International Conference on Civil, Structural and Environmental Engineering Computing, UK: Civil Comp Press,Stirlingshire UK. Stephen, D., Ye, J. and Lam, D. (2012). Progressive Collapse Evaluation of High Rise Steel Structures due to Sudden Loss of Structural Members. In: 10th International Conference on Advances in steel Concrete Composite and Hybrid Structures, Singapore. pp.1179-1186. Stephen, O.D., Lam, D. and Toropov, V.V. (2013). Assessment of column removal time for progressive collapse evaluation of high rise structures. Research and Applications in Structural Engineering, Mechanics and Computation. CRC Press, pp.699-704. Stevens, D., Crowder, B., Sunshine, D., Marchand, K., Smilowitz, R., Williamson, E. and Waggoner, M. (2011). DoD Research and Criteria for the Design of Buildings to Resist Progressive Collapse. Journal of Structural Engineering. 137(9), pp.870-880. Tohidi, M., Yang, J. and Baniotopoulos, C. (2014b). Numerical evaluations of codified design methods for progressive collapse resistance of precast concrete cross wall structures. Engineering Structures. 76, pp.177-186. Tsai, M.-H. (2010). An analytical methodology for the dynamic amplification factor in progressive collapse evaluation of building structures. Mechanics Research Communications. 37(1), pp.61-66. Tsai, M.-H. (2012). A performance-based design approach for retrofitting regular building frames with steel braces against sudden column loss. Journal of Constructional Steel Research. 77, pp.1-11. Tsai, M.-H. and Lin, B.-H. (2009). Dynamic amplification factor for progressive collapse resistance analysis of an RC building. The Structural Design of Tall and Special Buildings. 18(5), pp.539-557. Türker, T. and Bayraktar, A. (2011). Experimental and numerical investigation of brace configuration effects on steel structures. Journal of Constructional Steel Research. 67(5), pp.854-865. Usmani, A.S., Chung, Y.C. and Torero, J.L. (2003). How did the WTC towers collapse: A new theory. Fire Safety Journal. 38, pp.501-533. Vlassis, A.G., Izzuddin, B.A., Elghazouli, A.Y. and Nethercot, D.A. (2006). Design Oriented Approach for Progressive Collapse Assessment of Steel Framed Buildings. Structural Engineering International. 16(2), pp.129-136 Vlassis, A.G., Izzuddin, B.A., Elghazouli, A.Y. and Nethercot, D.A. (2008). Progressive collapse of multi-storey buildings due to sudden column loss—Part II: Application. Engineering Structures. 30(5), pp.1424-1438. Vlassis, A.G., Izzuddin, B.A., Elghazouli, A.Y. and Nethercot, D.A. (2009). Progressive collapse of multi-storey buildings due to failed floor impact. Engineering Structures. 31(7), pp.1522-1534. Wada, A., Ohi, K., Suzuki, H., Kohno, M. and Sakumoto, Y. (2004). A Study on the Collapse Control Design Method for High-Rise Steel Buildings. Structural Engineering International. 16(2), pp.137-141. Xu, G. and Ellingwood, B.R. (2011). Disproportionate collapse performance of partially restrained steel frames with bolted T-stub connections. Engineering Structures. 33(1), pp.32-43. Yang, B. and Tan, K. (2012a). Robustness of Bolted-Angle Connections against Progressive Collapse: Experimental Tests of Beam-Column Joints and Development of Component-Based Models. Journal of Structural Engineering. 139(9), pp.1498-1514. Yang, B. and Tan, K.H. (2012b). Numerical analyses of steel beam–column joints subjected to catenary action. Journal of Constructional Steel Research. 70, pp.1-11. Yang, B. and Tan, K.H. (2013). Experimental tests of different types of bolted steel beam–column joints under a central-column-removal scenario. Engineering Structures. 54, pp.112-130. Yang, B., Tan, K.H. and Xiong, G. (2015). Behaviour of composite beam–column joints under a middle-column-removal scenario: Component-based modelling. Journal of Constructional Steel Research. 104, pp.137-154. Yee, Y. and Melchers, R. (1986). Moment‐rotation curves for bolted connections. Journal of Structural Engineering. 112(3), pp.615-635. Yu, H., Burgess, I.W., Davison, J.B. and Plank, R.J. (2009). Tying capacity of web cleat connections in fire, Part 2: Development of component-based model. Engineering Structures. 31(3), pp.697-708. Yu, M., Zha, X. and Ye, J. (2010). The influence of joints and composite floor slabs on effective tying of steel structures in preventing progressive collapse. Journal of Constructional Steel Research. 66(3), pp.442-451."],"dcterms:accessrights":["public"],"dc:title":["Progressive collapse assessment of structures"],"dc:type":["Thesis"],"dc:type.qualificationlevel":["doctoral"],"dc:type.qualificationname":["Ph.D"]},"updated_at":"2026-11-18T22:22:11Z"}