1 |
Identifying demand market participation opportunities available in cement plants / Izak Daniël KrügerKrüger, Izak Daniël January 2014 (has links)
South African cement manufacturers are under financial pressure. Sales have declined due to
the 2008 recession and electricity costs have tripled from 2005 to 2012. Electricity cost
savings are therefore more important than ever. Unfortunately retrofitting highly energyefficient
equipment is not ideal. These installations are costly and take a long time to
implement. Alternative strategies that can produce quick results in reducing electricity costs
are needed. One such alternative is a programme called Demand Market Participation
(DMP).
The DMP programme was implemented by Eskom, South Africa’s national electricity utility,
to reduce electricity demand during supply shortages. This programme offers potential cost
savings for clients with excess production capacity. Clients such as cement plants can switch
off non-essential production equipment in Eskom’s peak demand periods for a financial
incentive. To maximise the benefits for both the clients and Eskom, accurate electricity
forecasting is needed, as are systems enabling a quick response to load reduction requests.
In this study DMP opportunities on typical cement plants were identified. A DMP strategy to
assist cement plants was developed to achieve maximum cost savings without influencing
production, quality and safety. An existing energy management system (EnMS) was adapted
to incorporate the new DMP participation strategy. The new EnMS and DMP strategy were
implemented at a South African cement plant, resulting in savings of R220 000 per month.
This translates into an annual cost-saving potential of R2-million for the plant, and an R13-
million cost-saving potential for the total South African cement industry. / MIng (Mechanical Engineering), North-West University, Potchefstroom Campus, 2014
|
2 |
Techno-economic study of the calcium looping process for CO2 capture from cement and biomass power plantsOzcan, Dursun Can January 2014 (has links)
The first detailed systematic investigation of a cement plant with various carbon capture technologies has been performed. The calcium looping (Ca-looping) process has emerged as a leading option for this purpose, since this process applied to a cement plant provides an opportunity to use the CaO purge for clinker production. The Ca-looping process is comprised of two interconnected reactors where the carbonator captures CO2 from flue gases and the calciner regenerates the CaCO3 into CaO by oxy-combustion. Fully integrated process flowsheets have been developed and simulated in UniSim Design Suite from Honeywell. The detailed carbonator model has been implemented using Matlab and incorporated into UniSim to provide a full flowsheet simulation for an exemplary dry-feed cement plant as a user-defined operation. The base cement plant simulation was also modified to integrate three different carbon capture processes: membrane; indirect calcination; and amine-scrubbing. Furthermore, an advanced configuration of Ca-looping process has been investigated where the energy intensive air separation unit was replaced with a chemical looping combustion (CLC) cycle. Each case has been optimised to minimise its energy consumption and compared in terms of levelised cost of cement and its resulting cost of CO2 avoided at the same CO2 avoidance rate. The proposed integration of the Ca-looping process is capable of achieving over 90% CO2 avoidance with additional fuel consumption of 2.5 to 3.0 GJth/ton CO2 avoided. By using an advanced configuration of the Ca-looping process with a CLC cycle, the additional fuel consumption can be reduced to 1.7 GJth/ton CO2 avoided, but the cost of the oxygen carrier is the major concern for this system. Among the other CO2 capture options, the membrane process is a promising alternative for the Ca-looping process since it has a potential of achieving the target CO2 avoidance rate and purity requiring lower energy consumption. The indirect calcination process provides moderate levels of CO2 avoidance (up to 56%) without a need of an external capture process whereas the integration of the amine process in a cement plant is challenging as a result of the requirement of steam for solvent regeneration. Furthermore, considering zero net CO2 emissions associated with biomass combustion systems, a novel concept has been analysed to capture of CO2 in-situ with the Ca-looping process while operating the combustor of a dedicated biomass power plant at sufficiently low temperature. This process is capable of achieving 84% overall CO2 capture rate with an energy penalty of 5.2% when a proper heat exchanger network is designed with the support of a pinch analysis. The techno-economic performance of the biomass power plant with in-situ Ca-looping CO2 capture process was compared with that of the alternative biomass-air-fired and biomass-oxy-fired power plants.
|
3 |
Techno-Economic Study of CO<sub>2</sub> Capture Process for Cement PlantsHassan, S. M. Nazmul January 2005 (has links)
Carbon dioxide is considered to be the major source of GHG responsible for global warming; man-made CO<sub>2</sub> contributes approximately 63. 5% to all greenhouse gases. The cement industry is responsible for approximately 5% of global anthropogenic carbon dioxide emissions emitting nearly 900 kg of CO<sub>2</sub> for every 1000 kg of cement produced! Amine absorption processes in particular the monoethanolamine (MEA) based process, is considered to be a viable technology for capturing CO<sub>2</sub> from low-pressure flue gas streams because of its fast reaction rate with CO<sub>2</sub> and low cost of raw materials compared to other amines. However, MEA absorption process is associated with high capital and operating costs because a significant amount of energy is required for solvent regeneration and severe operating problems such as corrosion, solvent loss and solvent degradation.
This research was motivated by the need to design size and cost analysis of CO<sub>2</sub> capture process from cement industry. MEA based absorption process was used as a potential technique to model CO<sub>2</sub> capture from cement plants. In this research four cases were considered all to reach a CO<sub>2</sub> purity of 98% i) the plant operates at the highest capacity ii) the plant operates at average load iii) the plant operates at minimum operating capacity and iv) switching to a lower carbon content fuel at average plant load. A comparison among four cases were performed to determine the best operating conditions for capturing CO<sub>2</sub> from cement plants. A sensitivity analysis of the economics to the lean loading and percent recovery were carried out as well as the different absorber and striper tray combinations.
|
4 |
Techno-Economic Study of CO<sub>2</sub> Capture Process for Cement PlantsHassan, S. M. Nazmul January 2005 (has links)
Carbon dioxide is considered to be the major source of GHG responsible for global warming; man-made CO<sub>2</sub> contributes approximately 63. 5% to all greenhouse gases. The cement industry is responsible for approximately 5% of global anthropogenic carbon dioxide emissions emitting nearly 900 kg of CO<sub>2</sub> for every 1000 kg of cement produced! Amine absorption processes in particular the monoethanolamine (MEA) based process, is considered to be a viable technology for capturing CO<sub>2</sub> from low-pressure flue gas streams because of its fast reaction rate with CO<sub>2</sub> and low cost of raw materials compared to other amines. However, MEA absorption process is associated with high capital and operating costs because a significant amount of energy is required for solvent regeneration and severe operating problems such as corrosion, solvent loss and solvent degradation.
This research was motivated by the need to design size and cost analysis of CO<sub>2</sub> capture process from cement industry. MEA based absorption process was used as a potential technique to model CO<sub>2</sub> capture from cement plants. In this research four cases were considered all to reach a CO<sub>2</sub> purity of 98% i) the plant operates at the highest capacity ii) the plant operates at average load iii) the plant operates at minimum operating capacity and iv) switching to a lower carbon content fuel at average plant load. A comparison among four cases were performed to determine the best operating conditions for capturing CO<sub>2</sub> from cement plants. A sensitivity analysis of the economics to the lean loading and percent recovery were carried out as well as the different absorber and striper tray combinations.
|
5 |
Modelling for integrated energy optimisation in cement production plants / J.A. Swanepoel.Swanepoel, Jan Adriaan January 2013 (has links)
Cement production is an energy intensive process. In South Africa the cost of energy increased since 2006, while cement sales have dropped dramatically. It has become important to focus on methods to optimise energy consumption to achieve cost savings in the cement industry. Various methods of reducing production cost by improving energy efficiency are available, but require extended installation periods and high initial capital expenditure. Other methods such as operational optimisation can reduce production cost, but offer limited savings.
The aim of this study is to integrate the optimisation of multiple component operations to improve savings and reduce interruption during implementation. Although integrated optimisation models have been developed, no literature could be found on the application of these models in the cement industry.
This thesis reports on the development and implementation of an energy management system at four South African cement plants. The total electricity costs were reduced without installing costly infrastructure upgrades. The results summarise the success of the improved production planning. A conclusion regarding the feasibility of this implementation is compiled by comparing the savings achieved by the implementation of the energy management system to other energy saving methods. Recommendations are also made for further study and the implementation of the energy management system in similar industries. / Thesis (MIng (Mechanical Engineering))--North-West University, Potchefstroom Campus, 2013.
|
6 |
Identifying demand market participation opportunities available in cement plants / Izak Daniël KrügerKrüger, Izak Daniël January 2014 (has links)
South African cement manufacturers are under financial pressure. Sales have declined due to
the 2008 recession and electricity costs have tripled from 2005 to 2012. Electricity cost
savings are therefore more important than ever. Unfortunately retrofitting highly energyefficient
equipment is not ideal. These installations are costly and take a long time to
implement. Alternative strategies that can produce quick results in reducing electricity costs
are needed. One such alternative is a programme called Demand Market Participation
(DMP).
The DMP programme was implemented by Eskom, South Africa’s national electricity utility,
to reduce electricity demand during supply shortages. This programme offers potential cost
savings for clients with excess production capacity. Clients such as cement plants can switch
off non-essential production equipment in Eskom’s peak demand periods for a financial
incentive. To maximise the benefits for both the clients and Eskom, accurate electricity
forecasting is needed, as are systems enabling a quick response to load reduction requests.
In this study DMP opportunities on typical cement plants were identified. A DMP strategy to
assist cement plants was developed to achieve maximum cost savings without influencing
production, quality and safety. An existing energy management system (EnMS) was adapted
to incorporate the new DMP participation strategy. The new EnMS and DMP strategy were
implemented at a South African cement plant, resulting in savings of R220 000 per month.
This translates into an annual cost-saving potential of R2-million for the plant, and an R13-
million cost-saving potential for the total South African cement industry. / MIng (Mechanical Engineering), North-West University, Potchefstroom Campus, 2014
|
7 |
Modelling for integrated energy optimisation in cement production plants / J.A. Swanepoel.Swanepoel, Jan Adriaan January 2013 (has links)
Cement production is an energy intensive process. In South Africa the cost of energy increased since 2006, while cement sales have dropped dramatically. It has become important to focus on methods to optimise energy consumption to achieve cost savings in the cement industry. Various methods of reducing production cost by improving energy efficiency are available, but require extended installation periods and high initial capital expenditure. Other methods such as operational optimisation can reduce production cost, but offer limited savings.
The aim of this study is to integrate the optimisation of multiple component operations to improve savings and reduce interruption during implementation. Although integrated optimisation models have been developed, no literature could be found on the application of these models in the cement industry.
This thesis reports on the development and implementation of an energy management system at four South African cement plants. The total electricity costs were reduced without installing costly infrastructure upgrades. The results summarise the success of the improved production planning. A conclusion regarding the feasibility of this implementation is compiled by comparing the savings achieved by the implementation of the energy management system to other energy saving methods. Recommendations are also made for further study and the implementation of the energy management system in similar industries. / Thesis (MIng (Mechanical Engineering))--North-West University, Potchefstroom Campus, 2013.
|
Page generated in 0.0742 seconds